1405 N HUDSON AVE 90028
Certificate Information: 1405 N HUDSON AVE 90028
- Application / Permit
- 19010-10000-03783
- Plan Check / Job No.
- B19LA17859
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX AT REAR (BUILDING A) (3 OF 3) (DO NOT ISSUE C OF O UNTIL C OF O FOR 17016-70000-37359 IS ISSUED)
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | KEVIN MORALES |
| Corrections Issued | 9/17/2019 | KEVIN MORALES |
| Quality Review Completed | 9/28/2019 | YOUNG KIM |
| Building Plans Picked Up | 10/9/2019 | APPLICANT |
| Green Plans Picked Up | 5/29/2020 | APPLICANT |
| Applicant returned to address corrections | 10/20/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 11/5/2020 | KEVIN MORALES |
| Plan Check Approved | 8/25/2021 | KEVIN MORALES |
| Issued | 10/28/2021 | APPLICANT |
| CofO in Progress | 8/10/2024 | ROY SPAULDING |
| Permit Finaled | 8/20/2024 | RONALD MYRICK |
| CofO Issued | 8/20/2024 | RONALD MYRICK |
| Permit Finaled | 8/20/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Permit | Cleared | 9/13/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/16/2019 | ERIK BEASLEY |
| Trees in Parkway | Cleared | 9/25/2019 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/22/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 5/28/2020 | KEVIN MORALES |
| Project located in CRA area | Cleared | 8/7/2020 | GISELLE CORELLA |
| Low Impact Development | Cleared | 9/1/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/1/2020 | JAMES KHO |
| Address approval | Cleared | 9/2/2020 | CECILIO NAVARRO |
| Frnt yard landscape/Water mgmt | Cleared | 10/13/2020 | JASON CHAN |
| Opn space landscape/Water mgmt | Cleared | 10/13/2020 | JASON CHAN |
Contact Information
| Contractor | Stream Development Inc; Lic. No.: 1062718-B | 669 N 3RD AVENUE UPLAND, CA 91786 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/15/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 12/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 12/22/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 12/22/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Approved | BRIAN SULLIVAN |
| Structural Steel Frame | 1/24/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Steel/Welding | 1/25/2022 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 1/26/2022 | Partial Approval | RUBEN SALAS |
| Deputy Steel/Welding | 1/27/2022 | Partial Approval | RUBEN SALAS |
| Deputy Steel/Welding | 1/28/2022 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 1/31/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 2/1/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 2/2/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 2/3/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Structural Steel Frame | 2/8/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 2/23/2022 | Conditional Approval | BRIAN SULLIVAN |
| Special/Order Compliance | 3/1/2022 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Deputy Wood Construction | 3/9/2022 | Conditional Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/3/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/3/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/3/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/29/2022 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 6/29/2022 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/29/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/5/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 7/5/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/5/2022 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 7/12/2022 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 7/12/2022 | Approved | RUBEN SALAS |
| HVAC-Rough | 7/25/2022 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 8/1/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/2/2022 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Wood Construction | 8/2/2022 | Conditional Approval | BRIAN SULLIVAN |
| Green Building Rough | 8/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Shower Pan | 8/2/2022 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 8/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 8/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | No Access for Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 8/19/2022 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 8/26/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/26/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 9/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/26/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 9/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 9/26/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/3/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/3/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 10/19/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 11/7/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 11/18/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 11/18/2022 | Approved | JOAQUIN GREENOUGH |
| Pre-Inspection | 4/18/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 8/11/2023 | Approved | JOAQUIN GREENOUGH |
| Sewer | 8/11/2023 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 8/11/2023 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/23/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/24/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 11/15/2023 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 12/28/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 12/28/2023 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Final | 2/28/2024 | Corrections Issued | ROY SPAULDING |
| HVAC-Final | 2/28/2024 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Final | 2/28/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Final | 3/29/2024 | Approved | ROY SPAULDING |
| Gas Test | 3/29/2024 | Approved | ROY SPAULDING |
| HVAC-Final | 3/29/2024 | Approved | ROY SPAULDING |
| PLUMBING-Final | 3/29/2024 | Approved | ROY SPAULDING |
| Service/Power Release | 5/1/2024 | Not Ready for Inspection | ROY SPAULDING |
| Service/Power Release | 5/3/2024 | Partial Inspection | BRIAN SULLIVAN |
| Service/Power Release | 5/28/2024 | Corrections Issued | BRIAN SULLIVAN |
| Final | 6/20/2024 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 6/20/2024 | Approved | ROY SPAULDING |
| Green Building Final | 6/20/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 6/20/2024 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 6/20/2024 | Approved | ROY SPAULDING |
| Final | 8/8/2024 | OK to Issue CofO | ROY SPAULDING |
| Service/Power Release | 8/8/2024 | Approved | ROY SPAULDING |