1 S LMU DR 90045

Certificate Information: 1 S LMU DR 90045

Application / Permit
19010-10000-03769
Plan Check / Job No.
B19LA17812
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(18) School Building
Work Description
NEW 4 STORY, TYPE IIA, UNDERGRADUATE BUILDING WITH PRIMARILY CLASSROOMS AND 1 STORY LECTURE HALL.
Permit Issued
Issued on 2/5/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2019 APPLICANT
Disabled Access Plans Picked Up 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 KESETE HAREGOT
Green Plans Picked Up 9/20/2019 APPLICANT
Corrections Issued 10/8/2019 KESETE HAREGOT
Quality Review Completed 10/25/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 10/28/2019 APPLICANT
Applicant returned to address corrections 11/26/2019 KESETE HAREGOT
Applicant returned to address corrections 12/19/2019 KESETE HAREGOT
Plan Check Approved 1/30/2020 KESETE HAREGOT
Plan Check Approved 1/30/2020 KESETE HAREGOT
Issued 2/5/2020 LADBS
TCO Issued (Expire Date: 01-12-2022) 7/16/2021 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 07-11-2022) 1/12/2022 NICK LAROCCA
TCO Issued (Expire Date: 02-20-2023) 8/24/2022 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 07-29-2023) 1/30/2023 NICK LAROCCA
TCO Issued (Expire Date: 01-29-2024) 8/2/2023 NICK LAROCCA
CofO in Progress 1/31/2024 NICK LAROCCA
Permit Finaled 2/12/2024 HENRY BAGHDASSARIAN
CofO Issued 2/12/2024 HENRY BAGHDASSARIAN
Permit Finaled 2/12/2024 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/8/2019 CELINA MORENO
Hydrant and Access approval Cleared 10/18/2019 JOHN CONNEALLY
Address approval Cleared 10/21/2019 ANTHONY MAINEZ
Green Code Cleared 11/26/2019 COLIN LOREDO
Specific Plan Cleared 12/12/2019 PEDRO AYALA
Frnt yard landscape/Water mgmt Cleared 1/15/2020 JASON CHAN
Low Impact Development Cleared 1/17/2020 SARAH YOUSSEF
Specific Plan Cleared 1/17/2020 ESTHER AMAYA
Roof/Waste drainage to street Cleared 1/22/2020 JUAN ASHTON
DAS Clearance Cleared 1/23/2020 WAI LAU
Sewer availability Cleared 1/23/2020 AVALYN KAMACHI
Fire Marshall Fire Life Safety Cleared 1/27/2020 WILLIAM JOHNS
Building over 3-story or 36-ft Cleared 1/30/2020 CALOSHA APPROVED
GPI Written Notices Cleared 1/30/2020 KESETE HAREGOT
Grading Pre-Inspection Cleared 1/30/2020 KESETE HAREGOT

Contact Information

Architect Danna,, Paul Andrews; Lic. No.: C21705 8807 HOLLYWOOD HILLS ROAD      LOS ANGELES, CA 90046
Contractor O'Neil W E Construction Co Of California; Lic. No.: 494031-B 909 N PACIFIC COAST HWY   STE 400    EL SEGUNDO, CA 90245
Engineer Rana,, Masood Sarwar; Lic. No.: C70659 19560 SHADOW RIDGE WY      NORTHRIDGE, CA 91326
Engineer Sarkisian,, Mark Peter; Lic. No.: S4639 ONE FRONT ST STE 24      SAN FRANCISCO, CA 94111

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/6/2020 Approved NICK LAROCCA
Verify Sprinkler Sign Off 2/11/2020 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/2/2020 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 4/2/2020 Approved NICK LAROCCA
Deputy Methane Barrier 4/23/2020 Approved NICK LAROCCA
Deputy Methane Barrier 4/24/2020 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/24/2020 Partial Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/29/2020 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 4/29/2020 Partial Approval NICK LAROCCA
METHANE-Barrier 4/29/2020 Partial Approval NICK LAROCCA
METHANE-Subgrade 4/29/2020 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/30/2020 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 5/8/2020 Partial Approval NICK LAROCCA
Green Building Rough 5/12/2020 Approved NICK LAROCCA
METHANE-Rough 5/12/2020 Not Ready for Inspection NICK LAROCCA
Reinforced Concrete Frame 5/12/2020 Partial Inspection NICK LAROCCA
Verify Sprinkler Sign Off 5/12/2020 Approved NICK LAROCCA
Reinforced Concrete Frame 5/13/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 5/14/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/15/2020 Approved NICK LAROCCA
Deputy Methane Barrier 5/22/2020 Approved JEFF BYTHEWAY
Deputy Methane Barrier 5/28/2020 Approved NICK LAROCCA
Deputy Methane Barrier 5/29/2020 Approved NICK LAROCCA
METHANE-Barrier 6/1/2020 Not Ready for Inspection NICK LAROCCA
METHANE-Subgrade 6/1/2020 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/2/2020 Partial Approval NICK LAROCCA
METHANE-Rough 6/10/2020 Not Ready for Inspection NICK LAROCCA
Reinforced Concrete Frame 6/10/2020 Not Ready for Inspection NICK LAROCCA
Footing/Foundation/Slab 6/11/2020 Not Ready for Inspection NICK LAROCCA
METHANE-Barrier 6/11/2020 Not Ready for Inspection NICK LAROCCA
METHANE-Subgrade 6/11/2020 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/12/2020 Partial Approval NICK LAROCCA
METHANE-Rough 6/12/2020 Approved NICK LAROCCA
Deputy Methane Barrier 6/18/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 6/18/2020 Partial Approval NICK LAROCCA
METHANE-Barrier 6/18/2020 Approved NICK LAROCCA
METHANE-Subgrade 6/18/2020 Approved NICK LAROCCA
Deputy Methane Barrier 6/19/2020 Conditional Approval TED RIES
Deputy Methane Barrier 6/22/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 6/22/2020 Approved NICK LAROCCA
Deputy Methane Barrier 6/23/2020 Approved NICK LAROCCA
Deputy Methane Barrier 6/29/2020 Approved NICK LAROCCA
Deputy Methane Barrier 6/30/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/1/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 7/2/2020 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 7/10/2020 Partial Approval NICK LAROCCA
Deputy Other (see comments) 7/13/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 7/23/2020 Approved DERRICK SPENCER
Deputy Reinf. Concrete 7/23/2020 Approved DERRICK SPENCER
Deputy Pre-Stress Concrete 7/24/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/24/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 7/24/2020 Partial Approval NICK LAROCCA
Deputy Pre-Stress Concrete 7/27/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/27/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 7/28/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/28/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 7/30/2020 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 7/30/2020 Partial Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 7/31/2020 Partial Approval NICK LAROCCA
Deputy Pre-Stress Concrete 8/7/2020 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/7/2020 Approved TED RIES
Deputy Pre-Stress Concrete 8/10/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/10/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 8/11/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/11/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 8/12/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/12/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 8/21/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/21/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 8/21/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 8/24/2020 Partial Approval NICK LAROCCA
Deputy Pre-Stress Concrete 8/25/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/25/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 8/26/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/26/2020 Approved NICK LAROCCA
Reinforced Concrete Frame 8/26/2020 Partial Approval NICK LAROCCA
Deputy Pre-Stress Concrete 8/27/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/27/2020 Approved NICK LAROCCA
Piling/Pier/Caisson 8/27/2020 Not Ready for Inspection NICK LAROCCA
Piling/Pier/Caisson 8/28/2020 Partial Approval NICK LAROCCA
Deputy Pre-Stress Concrete 9/17/2020 Approved JOEY BUCHANAN
Deputy Pre-Stress Concrete 9/18/2020 Approved JOEY BUCHANAN
Footing/Foundation/Slab 9/18/2020 Partial Approval JOEY BUCHANAN
Deputy Pre-Stress Concrete 9/21/2020 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 9/21/2020 Not Ready for Inspection NICK LAROCCA
Piling/Pier/Caisson 9/24/2020 Partial Inspection NICK LAROCCA
Deputy Reinf. Concrete 9/25/2020 Approved NICK LAROCCA
Reinforced Concrete Frame 9/25/2020 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/8/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 10/13/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 10/16/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 10/26/2020 Approved NICK LAROCCA
Deputy Steel/Welding 10/28/2020 Approved NICK LAROCCA
Light Gage Steel Frame 11/5/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 11/12/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 11/18/2020 Approved NICK LAROCCA
Drywall Nailing 11/19/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 11/23/2020 Partial Inspection JOEY BUCHANAN
Reinforced Concrete Frame 11/24/2020 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 12/1/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 12/4/2020 Partial Approval JOEY BUCHANAN
Drywall Nailing 12/8/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 12/8/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 12/15/2020 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 12/17/2020 Approved NICK LAROCCA
Interior/Exterior Lathing 12/18/2020 Approved NICK LAROCCA
Reinforced Concrete Frame 12/22/2020 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 1/7/2021 Order to Comply Issued JOEY BUCHANAN
Light Gage Steel Frame 1/7/2021 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 1/11/2021 Approved JOEY BUCHANAN
Insulation 1/11/2021 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 1/11/2021 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 1/12/2021 Approved NICK LAROCCA
Light Gage Steel Frame 1/14/2021 Partial Approval NICK LAROCCA
Insulation 1/19/2021 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 1/19/2021 Partial Approval PAUL DAVIDSON
Drywall Nailing 1/22/2021 Partial Approval JOEY BUCHANAN
Insulation 1/22/2021 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 1/22/2021 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 1/26/2021 Partial Approval TED RIES
Drywall Nailing 2/1/2021 Partial Approval DERRICK SPENCER
Insulation 2/1/2021 Partial Approval DERRICK SPENCER
Drywall Nailing 2/3/2021 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/3/2021 Partial Approval DERRICK SPENCER
Drywall Nailing 2/8/2021 Partial Approval TED RIES
Light Gage Steel Frame 2/10/2021 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 2/12/2021 Approved DERRICK SPENCER
Drywall Nailing 2/16/2021 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 2/16/2021 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/16/2021 Not Ready for Inspection DERRICK SPENCER
Drywall Nailing 2/18/2021 Partial Approval DERRICK SPENCER
Drywall Nailing 2/25/2021 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 2/26/2021 Partial Approval JOEY BUCHANAN
Drywall Nailing 3/2/2021 Partial Approval NICK LAROCCA
Deputy Steel/Welding 3/4/2021 Approved NICK LAROCCA
Interior/Exterior Lathing 3/10/2021 Partial Approval NICK LAROCCA
Light Gage Steel Frame 3/11/2021 Not Ready for Inspection NICK LAROCCA
Light Gage Steel Frame 3/12/2021 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 3/15/2021 Partial Approval NICK LAROCCA
Drywall Nailing 3/16/2021 Approved NICK LAROCCA
Interior/Exterior Lathing 3/16/2021 Approved NICK LAROCCA
T-Bar Ceiling 3/24/2021 Partial Approval NICK LAROCCA
T-Bar Ceiling 4/9/2021 Not Ready for Inspection NICK LAROCCA
T-Bar Ceiling 4/13/2021 Partial Approval NICK LAROCCA
Structural Steel Frame 4/19/2021 Conditional Approval NICK LAROCCA
Light Gage Steel Frame 5/3/2021 Partial Approval DERRICK SPENCER
Final 6/9/2021 Partial Inspection NICK LAROCCA
Footing/Foundation/Slab 6/9/2021 Approved NICK LAROCCA
Green Building Final 6/9/2021 Approved NICK LAROCCA
Reinforced Concrete Frame 6/9/2021 Approved NICK LAROCCA
Reinforced Masonry Frame 6/9/2021 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 6/9/2021 SGSOV Approved NICK LAROCCA
Smoke Detectors 6/9/2021 Approved NICK LAROCCA
Pre-Inspection 7/1/2021 Partial Inspection NICK LAROCCA
Final 7/2/2021 Not Ready for Inspection NICK LAROCCA
Deputy Steel/Welding 7/6/2021 Approved NICK LAROCCA
Pre-Inspection 7/6/2021 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 7/7/2021 Approved NICK LAROCCA
Deputy Steel/Welding 7/8/2021 Approved NICK LAROCCA
Deputy Steel/Welding 7/9/2021 Approved NICK LAROCCA
Final 7/9/2021 Corrections Issued NICK LAROCCA
T-Bar Ceiling 7/12/2021 Approved NICK LAROCCA
Deputy Steel/Welding 7/13/2021 Approved NICK LAROCCA
Deputy Steel/Welding 7/14/2021 Approved NICK LAROCCA
Deputy Steel/Welding 7/15/2021 Approved NICK LAROCCA
Deputy Steel/Welding 7/16/2021 Approved NICK LAROCCA
Deputy Steel/Welding 7/19/2021 Approved NICK LAROCCA
Special/Order Compliance 12/15/2021 Approved NICK LAROCCA
Special/Order Compliance 6/15/2022 Approved DERRICK SPENCER
Special/Order Compliance 1/25/2023 Approved NICK LAROCCA
Special/Order Compliance 7/6/2023 Approved NICK LAROCCA
Special/Order Compliance 1/3/2024 Approved NICK LAROCCA
Final 1/31/2024 OK to Issue CofO NICK LAROCCA