14207-14207 1/2 W ERWIN ST 91401
Certificate Information: 14207-14207 1/2 W ERWIN ST 91401
- Application / Permit
- 19010-10000-03755
- Plan Check / Job No.
- B19LA17720
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH ATTACHED GARAGE (2 OF 2)
- Permit Issued
- Issued on 12/9/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 12/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | DINA ELKINAWY |
| Corrections Issued | 9/16/2019 | DINA ELKINAWY |
| Quality Review Completed | 9/26/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Green Plans Picked Up | 10/15/2019 | APPLICANT |
| Plan Check Approved | 11/12/2019 | DINA ELKINAWY |
| Issued | 12/9/2019 | LADBS |
| CofO in Progress | 12/2/2022 | RYAN SALAZAR |
| CofO Issued | 12/19/2022 | MICHAEL SMITH |
| Permit Finaled | 12/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2019 | ELENA LOPEZ |
| Highway dedication | Cleared | 10/28/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 10/28/2019 | ELENA LOPEZ |
| "Q" conditions | Cleared | 11/8/2019 | JOSE ROMERO-NAVARRO |
| Certificate of Compliance | Cleared | 11/8/2019 | MARC WOERSCHING |
| Green Code | Cleared | 11/8/2019 | COLIN LOREDO |
| Green Code | Cleared | 11/8/2019 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 11/12/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 11/12/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/12/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Zamora Juan Jr; Lic. No.: 854854-B | 14318 POLK ST SYLMAR, CA 91342 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 26851 GRAYSLAKE ROAD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/26/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/3/2020 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | Partial Approval | RAYMOND KEHOE |
| PLUMBING-Rough | 1/27/2021 | Corrections Issued | BEAU COLLINS |
| ELECTRICAL-Rough | 2/2/2021 | Not Ready for Inspection | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 2/3/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 2/3/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 2/3/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/3/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/8/2021 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 4/8/2021 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 4/16/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/19/2021 | Approved | DANIEL ORRANTE |
| PLUMBING-Rough | 4/20/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/11/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/11/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/11/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/11/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/11/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/11/2021 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 6/11/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 6/21/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 7/23/2021 | Corrections Issued | AMY COLIN |
| Drywall Nailing | 9/7/2021 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 9/14/2021 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 10/25/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/25/2022 | No Access for Inspection | RICHARD DOCKUS |
| HVAC-Final | 10/25/2022 | No Access for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 10/25/2022 | No Access for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 11/1/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 11/1/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 11/4/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 11/4/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 11/10/2022 | Approved | RAUL OLAGI |
| Green Building Final | 11/16/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/29/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | RYAN SALAZAR |
| Final | 12/1/2022 | OK to Issue CofO | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 12/1/2022 | Approved | RYAN SALAZAR |
| Smoke Detectors | 12/1/2022 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 12/1/2022 | Approved | RYAN SALAZAR |