2212 N OROS ST 90031

Certificate Information: 2212 N OROS ST 90031

Application / Permit
19010-10000-03749
Plan Check / Job No.
B19LA17700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW ACCESSORY DWELLING UNIT PER AB494 AND SB 229
Permit Issued
Issued on 1/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 SINA KHOSRAVI
Corrections Issued 9/20/2019 SINA KHOSRAVI
Green Plans Picked Up 9/20/2019 APPLICANT
Quality Review Completed 9/28/2019 YOUNG KIM
Building Plans Picked Up 10/4/2019 APPLICANT
Applicant returned to address corrections 10/23/2019 SINA KHOSRAVI
Plan Check Approved 10/23/2019 SINA KHOSRAVI
Issued 1/6/2020 LADBS
CofO in Progress 10/19/2020 RUBEN SALAS
Permit Finaled 10/19/2020 DEROLD HAUFF
CofO Issued 10/19/2020 DEROLD HAUFF
Permit Finaled 10/19/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/4/2019 THOMAS LANG
Sewer availability Cleared 10/4/2019 THOMAS LANG
Green Code Cleared 10/18/2019 COLIN LOREDO
Low Impact Development Cleared 10/23/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/23/2019 CELINA MORENO
ZI Cleared 10/23/2019 TERRI OSBORNE

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/29/2020 Approved AJA COLLAY
Underground Mechanical 1/30/2020 Partial Approval AJA COLLAY
Excavation/Setback/Form/Re-Bar 2/4/2020 Not Ready for Inspection AJA COLLAY
Footing/Foundation/Slab 2/5/2020 Approved AJA COLLAY
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Approved AJA COLLAY
Green Building Rough 2/20/2020 Not Ready for Inspection AJA COLLAY
MERV13>=Rough 2/20/2020 Not Ready for Inspection AJA COLLAY
Verify Sprinkler Sign Off 2/20/2020 Not Ready for Inspection AJA COLLAY
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Not Ready for Inspection AJA COLLAY
Wood Frame 3/6/2020 Not Ready for Inspection AJA COLLAY
Deputy Wood Construction 3/12/2020 Conditional Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 3/16/2020 Not Ready for Inspection AJA COLLAY
Deputy Wood Construction 3/17/2020 Conditional Approval MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 4/15/2020 Corrections Issued RUBEN SALAS
PLUMBING-Rough 4/16/2020 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 5/11/2020 Conditional Approval MATTHEW NUCKOLLS
HVAC-Rough 5/11/2020 Approved MATTHEW NUCKOLLS
Interior/Exterior Lathing 5/11/2020 Not Ready for Inspection MATTHEW NUCKOLLS
PLUMBING-Rough 5/11/2020 Conditional Approval MATTHEW NUCKOLLS
BUILDING-Rough-Frame 5/14/2020 Approved SCOTT FINNILA
Green Building Rough 5/14/2020 Approved SCOTT FINNILA
MERV13>=Rough 5/14/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 5/14/2020 Approved SCOTT FINNILA
Insulation 5/22/2020 Approved ROBERT VORHIS
Interior/Exterior Lathing 5/27/2020 Partial Approval THOMAS LOGRASSO
Drywall Nailing 6/3/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 6/3/2020 Approved RUBEN SALAS
Sewer 6/15/2020 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 6/15/2020 Corrections Issued STUART CHAPMAN
Sewer 6/17/2020 Approved COREY HUPP
Underground Mechanical 6/19/2020 Not Ready for Inspection COREY HUPP
Underground Mechanical 6/22/2020 Not Ready for Inspection COREY HUPP
Underground Mechanical 6/24/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 9/2/2020 Partial Inspection RUBEN SALAS
ELECTRICAL-Final 9/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 9/17/2020 Corrections Issued ENRIQUE MIRELES
Green Building Final 9/17/2020 Approved ENRIQUE MIRELES
HVAC-Final 9/17/2020 Not Ready for Inspection ENRIQUE MIRELES
MERV13>=Final 9/17/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 9/17/2020 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV Not Ready ENRIQUE MIRELES
Service/Power Release 9/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 9/17/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 9/22/2020 Approved RUBEN SALAS
HVAC-Final 9/22/2020 Approved RUBEN SALAS
PLUMBING-Final 9/22/2020 Approved RUBEN SALAS
Pre-Inspection 9/22/2020 Approved RUBEN SALAS
Final 10/15/2020 OK to Issue CofO RUBEN SALAS
Gas Test 10/15/2020 Approved RUBEN SALAS
MERV13>=Final 10/15/2020 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved RUBEN SALAS
Service/Power Release 10/15/2020 Approved RUBEN SALAS
Smoke Detectors 10/15/2020 Approved RUBEN SALAS