7040 N SEPULVEDA BLVD 91405

Certificate Information: 7040 N SEPULVEDA BLVD 91405

Application / Permit
19010-10000-03733
Plan Check / Job No.
B19LA17585
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
New Restaurant with Drive Thru and Outdoor Dining Area.
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
CofO Issued on 1/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 SALVADOR QUINTANILLA
Corrections Issued 9/16/2019 SALVADOR QUINTANILLA
Quality Review Completed 9/18/2019 KEN GILL
Building Plans Picked Up 9/26/2019 APPLICANT
Disabled Access Plans Picked Up 9/26/2019 APPLICANT
Green Plans Picked Up 9/26/2019 APPLICANT
Applicant returned to address corrections 11/6/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 11/19/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 8/20/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/2/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/15/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/16/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/17/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/24/2020 SALVADOR QUINTANILLA
Plan Check Approved 9/28/2020 SALVADOR QUINTANILLA
Issued 10/9/2020 APPLICANT
CofO in Progress 7/30/2021 CAMERON CHABAN
Permit Finaled 1/25/2022 RICKEY JACKSON
CofO Issued 1/25/2022 RICKEY JACKSON
Permit Finaled 1/25/2022 RICKEY JACKSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/8/2019 JEREMY CARTER
Miscellaneous Cleared 10/8/2019 RICHARD REASER
ZA Case Cleared 10/8/2019 RICHARD REASER
ZA Case Cleared 10/8/2019 RICHARD REASER
ZA Case Cleared 10/8/2019 RICHARD REASER
ZA Case Cleared 10/8/2019 RICHARD REASER
ZA Case Cleared 10/8/2019 RICHARD REASER
DAS Clearance Cleared 11/6/2019 SALVADOR QUINTANILLA
Green Code Cleared 12/13/2019 VIVIAN LAO
Food establishment approval Cleared 2/7/2020 LACDHS APPROVED
Eng Process Fee Ord 176,300 Cleared 2/24/2020 EMIL KYUPELYAN
Low Impact Development Cleared 5/4/2020 AMMAR ELTAWIL
Permit Cleared 8/28/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 8/28/2020 GUILLERMO PETRA
Sewer availability Cleared 8/28/2020 GUILLERMO PETRA
Driveway location Cleared 9/9/2020 DURRE SHAMSI
Comm Cor/Mini-Mall Cleared 9/10/2020 MIGUEL GAMBOA
Comm Cor/Mini-Mall Cleared 9/10/2020 MIGUEL GAMBOA
Miscellaneous Cleared 9/10/2020 MIGUEL GAMBOA
Prkng lot landscape/Water mgmt Cleared 9/10/2020 MIGUEL GAMBOA
ZA Case Cleared 9/10/2020 MIGUEL GAMBOA
Food Service Establishment Cleared 9/15/2020 RAMESHBHAIR PATEL
Highway dedication Cleared 9/16/2020 GUILLERMO PETRA

Contact Information

Contractor Cirks Construction Inc; Lic. No.: 763589-B 1442 E LINCOLN AVENUE #334      ORANGE, CA 92865
Engineer New,, Rod G; Lic. No.: S3419 1710 AURELIA DRIVE      CUMMING, GA 30041
Engineer Pirathiviraj,, Sivasubramaniam; Lic. No.: C71662 3 ALBANY      IRVINE, CA 92604

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 12/22/2020 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/22/2020 Partial Approval ROBERT DAVIS
Deputy Wood Construction 1/11/2021 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Corrections Issued ROBERT DAVIS
Interior/Exterior Lathing 2/16/2021 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 2/23/2021 Approved CAMERON CHABAN
Green Building Rough 3/1/2021 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 3/1/2021 Approved CAMERON CHABAN
Wood Frame 3/1/2021 Approved CAMERON CHABAN
Insulation 3/3/2021 Approved CAMERON CHABAN
Drywall Nailing 3/8/2021 Approved CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Approved CAMERON CHABAN
T-Bar Ceiling 3/19/2021 Partial Inspection CAMERON CHABAN
T-Bar Ceiling 4/20/2021 Approved CAMERON CHABAN
Green Building Final 4/29/2021 Partial Inspection CAMERON CHABAN
Final 5/10/2021 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/10/2021 Approved CAMERON CHABAN
Green Building Final 5/10/2021 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/10/2021 SGSOV Approved CAMERON CHABAN
Smoke Detectors 5/10/2021 Approved CAMERON CHABAN
Final 5/12/2021 Partial Inspection CAMERON CHABAN
Green Building Final 5/12/2021 Approved CAMERON CHABAN
Final 5/17/2021 Partial Inspection CAMERON CHABAN
Final 6/2/2021 Partial Inspection CAMERON CHABAN
Final 7/30/2021 OK to Issue CofO CAMERON CHABAN