7040 N SEPULVEDA BLVD 91405
Certificate Information: 7040 N SEPULVEDA BLVD 91405
- Application / Permit
- 19010-10000-03733
- Plan Check / Job No.
- B19LA17585
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- New Restaurant with Drive Thru and Outdoor Dining Area.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 1/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | SALVADOR QUINTANILLA |
| Corrections Issued | 9/16/2019 | SALVADOR QUINTANILLA |
| Quality Review Completed | 9/18/2019 | KEN GILL |
| Building Plans Picked Up | 9/26/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 9/26/2019 | APPLICANT |
| Green Plans Picked Up | 9/26/2019 | APPLICANT |
| Applicant returned to address corrections | 11/6/2019 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/19/2019 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 8/20/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 9/2/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 9/15/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 9/16/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 9/17/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 9/24/2020 | SALVADOR QUINTANILLA |
| Plan Check Approved | 9/28/2020 | SALVADOR QUINTANILLA |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 7/30/2021 | CAMERON CHABAN |
| Permit Finaled | 1/25/2022 | RICKEY JACKSON |
| CofO Issued | 1/25/2022 | RICKEY JACKSON |
| Permit Finaled | 1/25/2022 | RICKEY JACKSON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/8/2019 | JEREMY CARTER |
| Miscellaneous | Cleared | 10/8/2019 | RICHARD REASER |
| ZA Case | Cleared | 10/8/2019 | RICHARD REASER |
| ZA Case | Cleared | 10/8/2019 | RICHARD REASER |
| ZA Case | Cleared | 10/8/2019 | RICHARD REASER |
| ZA Case | Cleared | 10/8/2019 | RICHARD REASER |
| ZA Case | Cleared | 10/8/2019 | RICHARD REASER |
| DAS Clearance | Cleared | 11/6/2019 | SALVADOR QUINTANILLA |
| Green Code | Cleared | 12/13/2019 | VIVIAN LAO |
| Food establishment approval | Cleared | 2/7/2020 | LACDHS APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2020 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 5/4/2020 | AMMAR ELTAWIL |
| Permit | Cleared | 8/28/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 8/28/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/28/2020 | GUILLERMO PETRA |
| Driveway location | Cleared | 9/9/2020 | DURRE SHAMSI |
| Comm Cor/Mini-Mall | Cleared | 9/10/2020 | MIGUEL GAMBOA |
| Comm Cor/Mini-Mall | Cleared | 9/10/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 9/10/2020 | MIGUEL GAMBOA |
| Prkng lot landscape/Water mgmt | Cleared | 9/10/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 9/10/2020 | MIGUEL GAMBOA |
| Food Service Establishment | Cleared | 9/15/2020 | RAMESHBHAIR PATEL |
| Highway dedication | Cleared | 9/16/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Cirks Construction Inc; Lic. No.: 763589-B | 1442 E LINCOLN AVENUE #334 ORANGE, CA 92865 |
| Engineer | New,, Rod G; Lic. No.: S3419 | 1710 AURELIA DRIVE CUMMING, GA 30041 |
| Engineer | Pirathiviraj,, Sivasubramaniam; Lic. No.: C71662 | 3 ALBANY IRVINE, CA 92604 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 12/22/2020 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 12/22/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 1/11/2021 | Approved | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Corrections Issued | ROBERT DAVIS |
| Interior/Exterior Lathing | 2/16/2021 | Conditional Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 2/23/2021 | Approved | CAMERON CHABAN |
| Green Building Rough | 3/1/2021 | Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 3/1/2021 | Approved | CAMERON CHABAN |
| Wood Frame | 3/1/2021 | Approved | CAMERON CHABAN |
| Insulation | 3/3/2021 | Approved | CAMERON CHABAN |
| Drywall Nailing | 3/8/2021 | Approved | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Approved | CAMERON CHABAN |
| T-Bar Ceiling | 3/19/2021 | Partial Inspection | CAMERON CHABAN |
| T-Bar Ceiling | 4/20/2021 | Approved | CAMERON CHABAN |
| Green Building Final | 4/29/2021 | Partial Inspection | CAMERON CHABAN |
| Final | 5/10/2021 | Partial Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 5/10/2021 | Approved | CAMERON CHABAN |
| Green Building Final | 5/10/2021 | Partial Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2021 | SGSOV Approved | CAMERON CHABAN |
| Smoke Detectors | 5/10/2021 | Approved | CAMERON CHABAN |
| Final | 5/12/2021 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 5/12/2021 | Approved | CAMERON CHABAN |
| Final | 5/17/2021 | Partial Inspection | CAMERON CHABAN |
| Final | 6/2/2021 | Partial Inspection | CAMERON CHABAN |
| Final | 7/30/2021 | OK to Issue CofO | CAMERON CHABAN |