10200 S SUCCESS AVE 90002

Certificate Information: 10200 S SUCCESS AVE 90002

Application / Permit
19010-10000-03683
Plan Check / Job No.
B19LA17372
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(4) Community Center operated by philanthropic organization
Work Description
NEW 2-STORY COMMUNITY CENTER (OFFICES) BUILDING.
Permit Issued
Issued on 12/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 ALBERT SERVIN
Green Plans Picked Up 8/29/2019 APPLICANT
Corrections Issued 9/3/2019 ALBERT SERVIN
Quality Review Completed 9/6/2019 GARO TELMI
Building Plans Picked Up 9/10/2019 APPLICANT
Disabled Access Plans Picked Up 10/8/2019 APPLICANT
Applicant returned to address corrections 10/30/2019 ALBERT SERVIN
Applicant returned to address corrections 11/7/2019 ALBERT SERVIN
Applicant returned to address corrections 11/13/2019 ALBERT SERVIN
Plan Check Approved 12/20/2019 ALBERT SERVIN
Issued 12/20/2019 LADBS
TCO Issued (Expire Date: 06-07-2022) 12/9/2021 TED RIES
CofO in Progress 12/15/2021 SORIN CIRSTOIU
CofO Issued 12/17/2021 ERNESTO CORRAL
Permit Finaled 12/17/2021 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/20/2019 EMIL KYUPELYAN
Highway dedication Cleared 9/20/2019 EMIL KYUPELYAN
Permit Cleared 9/20/2019 EMIL KYUPELYAN
Address approval Cleared 10/7/2019 JEANETTE VONG
Sewer availability Cleared 10/28/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 11/7/2019 ROBERT DUFF
"D" conditions Cleared 11/8/2019 STEVE GARCIA
Community Plan Implem. Overlay Cleared 11/8/2019 STEVE GARCIA
Prkng lot landscape/Water mgmt Cleared 11/8/2019 STEVE GARCIA
Community Plan Implem. Overlay Cleared 11/19/2019 MOHAMMAD HASAN
Internal circulation Cleared 11/19/2019 MOHAMMAD HASAN
Miscellaneous Cleared 11/19/2019 MOHAMMAD HASAN
DAS Clearance Cleared 11/22/2019 SHINE LIN
Community Plan Implem. Overlay Cleared 12/10/2019 ELENA LOPEZ
Miscellaneous Cleared 12/10/2019 ANNA VAN
Miscellaneous Cleared 12/10/2019 ANNA VAN
Green Code Cleared 12/12/2019 SARAH ABOULHOSN
Low Impact Development Cleared 12/19/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/19/2019 JEANIE LAM

Contact Information

Architect Chait,, Michael Samuel; Lic. No.: C15381 7306 COLDWATER CYN AVENUE UNIT 12      NORTH HOLLYWOOD, CA 91605
Contractor Oltmans Construction Co; Lic. No.: 86393-B 10005 MISSION MILL RD      WHITTIER, CA 90601
Engineer Knur,, Reinard Thomas; Lic. No.: GE2755 1435 MONCADO DR      GLENDALE, CA 91207
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 12831 PANAMA STREET      LOS ANGELES, CA 90066

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/11/2020 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/17/2020 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 4/17/2020 Not Ready for Inspection JAMES POWERS
Pre-Inspection 4/17/2020 Approved JAMES POWERS
Reinforced Concrete Frame 4/17/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/22/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/22/2020 Partial Approval JAMES POWERS
Pre-Inspection 4/22/2020 Approved JAMES POWERS
Deputy Reinf. Concrete 4/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/28/2020 Partial Approval JAMES POWERS
Pre-Inspection 5/18/2020 Approved JAMES POWERS
Deputy Steel/Welding 6/15/2020 No Access for Inspection JAMES POWERS
Deputy Steel/Welding 6/16/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/17/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/18/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/19/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/23/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/24/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/26/2020 Conditional Approval NICK DANERI
Deputy Steel/Welding 6/26/2020 Conditional Approval NICK DANERI
Deputy Steel/Welding 6/29/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/30/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/1/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/2/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/7/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/9/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/14/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/14/2020 Not Ready for Inspection JAMES POWERS
Structural Steel Frame 7/14/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/15/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/16/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/17/2020 Partial Approval JAMES POWERS
Pre-Inspection 7/20/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/18/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/18/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/29/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/1/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/15/2020 Partial Approval JAMES POWERS
Insulation 10/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/4/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/4/2020 Partial Approval JAMES POWERS
Green Building Rough 11/17/2020 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 11/17/2020 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 11/17/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 11/17/2020 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 11/19/2020 Partial Approval NICK DANERI
Drywall Nailing 12/2/2020 Partial Approval JAMES POWERS
Green Building Rough 12/2/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/8/2020 Partial Approval JAMES POWERS
Green Building Rough 12/8/2020 Approved JAMES POWERS
Insulation 12/8/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/14/2020 Partial Approval JAMES POWERS
Insulation 12/14/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/14/2020 Approved JAMES POWERS
Deputy Reinf. Concrete 12/16/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/16/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/21/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/21/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 12/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/22/2020 Partial Approval JAMES POWERS
Drywall Nailing 1/12/2021 Approved JAMES POWERS
T-Bar Ceiling 4/29/2021 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Approved JOEY BUCHANAN
Final 11/18/2021 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 11/18/2021 Partial Inspection SORIN CIRSTOIU
Green Building Final 11/18/2021 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 11/18/2021 Partial Inspection SORIN CIRSTOIU
Smoke Detectors 11/18/2021 Approved SORIN CIRSTOIU
Structural Steel Frame 11/18/2021 Partial Inspection SORIN CIRSTOIU
Verify Sprinkler Sign Off 11/18/2021 Approved SORIN CIRSTOIU
Final 12/15/2021 OK to Issue CofO SORIN CIRSTOIU
Footing/Foundation/Slab 12/15/2021 Approved SORIN CIRSTOIU
Green Building Final 12/15/2021 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 12/15/2021 Approved SORIN CIRSTOIU
Structural Steel Frame 12/15/2021 Approved SORIN CIRSTOIU