9136-9138 S MENLO AVE 90044

Certificate Information: 9136-9138 S MENLO AVE 90044

Application / Permit
19010-10000-03651
Plan Check / Job No.
B19LA17232
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED DUPLEX WITH ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
CofO Issued on 10/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 SINA KHOSRAVI
Corrections Issued 9/10/2019 SINA KHOSRAVI
Green Plans Picked Up 9/16/2019 APPLICANT
Quality Review Completed 9/28/2019 YOUNG KIM
Building Plans Picked Up 10/8/2019 APPLICANT
Plan Check Approved 11/5/2019 SINA KHOSRAVI
Issued 4/5/2021 APPLICANT
CofO in Progress 9/30/2021 ALEJANDRO DE ARTOLA
CofO Issued 10/2/2021 DEROLD HAUFF
Permit Finaled 10/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/11/2019 JEREMY CARTER
Address approval Cleared 10/15/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/15/2019 ERIK BEASLEY
Sewer availability Cleared 10/15/2019 ERIK BEASLEY
Green Code Cleared 10/22/2019 VIVIAN LAO
Low Impact Development Cleared 10/22/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/22/2019 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/26/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/11/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 5/11/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Partial Approval EUGENE CASSIDY
Insulation 5/12/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/23/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 6/23/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 6/23/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 6/23/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/24/2021 Approved ALEJANDRO DE ARTOLA
Insulation 6/24/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/24/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Special/Order Compliance 7/7/2021 Corrections Issued JOAQUIN GREENOUGH
Drywall Nailing 7/13/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/13/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/29/2021 Approved ALEJANDRO DE ARTOLA
Final 9/29/2021 OK to Issue CofO ALEJANDRO DE ARTOLA
Gas Test 9/29/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 9/29/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 9/29/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 9/29/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 9/29/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 9/29/2021 Approved ALEJANDRO DE ARTOLA