528 N BELLAGIO TER 90049

Certificate Information: 528 N BELLAGIO TER 90049

Application / Permit
19010-10000-03642
Plan Check / Job No.
B19LA17191
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT AND ATTACHED GARAGE PER AB 494 and SB 229
Permit Issued
Issued on 7/2/2020
Issuing Office
Current Status
CofO Issued on 5/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 ARSALAN SHABESTARI
Corrections Issued 9/3/2019 ARSALAN SHABESTARI
Green Plans Picked Up 9/3/2019 APPLICANT
Quality Review Completed 9/14/2019 YOUNG KIM
Building Plans Picked Up 9/17/2019 APPLICANT
Applicant returned to address corrections 4/13/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 5/27/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 5/28/2020 ARSALAN SHABESTARI
Plan Check Approved 7/2/2020 ARSALAN SHABESTARI
Issued 7/2/2020 APPLICANT
CofO in Progress 3/24/2022 CARLOS MATAMOROS
Permit Finaled 5/7/2022 DANIEL ORRANTE
CofO Issued 5/7/2022 DANIEL ORRANTE
Permit Finaled 5/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 9/23/2019 OSCAR CASTRO
Construction within easement Cleared 9/23/2019 OSCAR CASTRO
Address approval Cleared 9/25/2019 DINAH GARIN
BHO/Hillside ordinance Cleared 9/25/2019 DINAH GARIN
BHO/Hillside ordinance Cleared 9/25/2019 DINAH GARIN
BHO/Hillside ordinance Cleared 9/25/2019 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/25/2019 DINAH GARIN
Sewer availability Cleared 9/25/2019 DINAH GARIN
ZA Case Cleared 10/31/2019 TREVOR MARTIN
ZA Case Cleared 10/31/2019 TREVOR MARTIN
ZA Case Cleared 10/31/2019 TREVOR MARTIN
Grading Pre-Inspection Cleared 11/13/2019 ARSALAN SHABESTARI
Hydrant and Access approval Cleared 12/11/2019 ROBERT DUFF
Green Code Cleared 12/18/2019 VIVIAN LAO
Low Impact Development Cleared 6/27/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/1/2020 DINAH GARIN

Contact Information

Architect Howell,, Ronald Edwards; Lic. No.: C21122 P O BOX 661007      LOS ANGELES, CA 90066
Contractor J D Group Inc; Lic. No.: 675485-B 1537 PONTIUS AVENUE SUITE B      LOS ANGELES, CA 90025

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/1/2020 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/18/2020 Partial Approval CARLOS MATAMOROS
Gas Test 9/18/2020 Approved CARLOS MATAMOROS
Green Building Rough 9/18/2020 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 9/18/2020 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 9/18/2020 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Conditional Approval CARLOS MATAMOROS
Green Building Rough 9/25/2020 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 9/25/2020 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/31/2020 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 4/7/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/1/2021 Not Ready for Inspection CARLOS MATAMOROS
Sewer 6/1/2021 Approved CARLOS MATAMOROS
Shower Pan 6/1/2021 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 6/2/2021 Approved CARLOS MATAMOROS
Service/Power Release 6/14/2021 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 6/14/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 6/17/2021 Approved CARLOS MATAMOROS
Special/Order Compliance 6/23/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/13/2021 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Partial Approval CARLOS MATAMOROS
Green Building Rough 8/13/2021 Approved CARLOS MATAMOROS
HVAC-Rough 8/13/2021 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 8/13/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/17/2021 Approved CARLOS MATAMOROS
Green Building Rough 8/17/2021 Approved CARLOS MATAMOROS
HVAC-Rough 8/17/2021 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 9/3/2021 Not Ready for Inspection CARLOS MATAMOROS
Insulation 9/17/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/17/2021 Partial Approval JAVIER RAMOS JR
Drywall Nailing 9/23/2021 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 10/12/2021 Approved DANIEL ORRANTE
Shower Pan 10/12/2021 Approved DANIEL ORRANTE
Gas Test 12/10/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 12/17/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 12/17/2021 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 12/17/2021 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 12/28/2021 Corrections Issued CARLOS MATAMOROS
HVAC-Final 12/28/2021 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 12/28/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 1/12/2022 Partial Approval CARLOS MATAMOROS
HVAC-Final 1/12/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 1/21/2022 Approved CARLOS MATAMOROS
HVAC-Final 1/21/2022 Approved CARLOS MATAMOROS
Service/Power Release 2/9/2022 Approved CARLOS MATAMOROS
Special/Order Compliance 2/9/2022 Not Ready for Inspection CARLOS MATAMOROS
Final 3/23/2022 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 3/23/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 3/23/2022 Approved CARLOS MATAMOROS