528 N BELLAGIO TER 90049
Certificate Information: 528 N BELLAGIO TER 90049
- Application / Permit
- 19010-10000-03642
- Plan Check / Job No.
- B19LA17191
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT AND ATTACHED GARAGE PER AB 494 and SB 229
- Permit Issued
- Issued on 7/2/2020
- Issuing Office
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 9/3/2019 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 9/3/2019 | APPLICANT |
| Quality Review Completed | 9/14/2019 | YOUNG KIM |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Applicant returned to address corrections | 4/13/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 5/27/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 5/28/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 7/2/2020 | ARSALAN SHABESTARI |
| Issued | 7/2/2020 | APPLICANT |
| CofO in Progress | 3/24/2022 | CARLOS MATAMOROS |
| Permit Finaled | 5/7/2022 | DANIEL ORRANTE |
| CofO Issued | 5/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/23/2019 | OSCAR CASTRO |
| Construction within easement | Cleared | 9/23/2019 | OSCAR CASTRO |
| Address approval | Cleared | 9/25/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/25/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/25/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/25/2019 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2019 | DINAH GARIN |
| Sewer availability | Cleared | 9/25/2019 | DINAH GARIN |
| ZA Case | Cleared | 10/31/2019 | TREVOR MARTIN |
| ZA Case | Cleared | 10/31/2019 | TREVOR MARTIN |
| ZA Case | Cleared | 10/31/2019 | TREVOR MARTIN |
| Grading Pre-Inspection | Cleared | 11/13/2019 | ARSALAN SHABESTARI |
| Hydrant and Access approval | Cleared | 12/11/2019 | ROBERT DUFF |
| Green Code | Cleared | 12/18/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 6/27/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/1/2020 | DINAH GARIN |
Contact Information
| Architect | Howell,, Ronald Edwards; Lic. No.: C21122 | P O BOX 661007 LOS ANGELES, CA 90066 |
| Contractor | J D Group Inc; Lic. No.: 675485-B | 1537 PONTIUS AVENUE SUITE B LOS ANGELES, CA 90025 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/1/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/18/2020 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 9/18/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/18/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/18/2020 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/18/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Rough | 9/25/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/25/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2021 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/7/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/1/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Sewer | 6/1/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 6/1/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 6/2/2021 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/14/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 6/14/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 6/17/2021 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 6/23/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/13/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 8/13/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 8/13/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 8/13/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/17/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/17/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 8/17/2021 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/3/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 9/17/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/17/2021 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 9/23/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 10/12/2021 | Approved | DANIEL ORRANTE |
| Shower Pan | 10/12/2021 | Approved | DANIEL ORRANTE |
| Gas Test | 12/10/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 12/17/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 12/17/2021 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 12/17/2021 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 12/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 12/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 12/28/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/12/2022 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Final | 1/12/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/21/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 1/21/2022 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 2/9/2022 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 2/9/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 3/23/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 3/23/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/23/2022 | Approved | CARLOS MATAMOROS |