5500 E BUCHANAN ST 90042

Certificate Information: 5500 E BUCHANAN ST 90042

Application / Permit
19010-10000-03603
Plan Check / Job No.
B19LA17100
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1 STORY ADDITION (18.5' x 28') TO REAR OF EXISTING SINGLE FAMILY DWELLING TO CREATE 2 NEW BEDROOMS AND 1 NEW BATHROOM. ALL WORK TO BE DONE PER EOR.
Permit Issued
Issued on 2/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 MICHAEL LOPEZ
Corrections Issued 9/9/2019 MICHAEL LOPEZ
Quality Review Completed 9/14/2019 STANLEY RAAP
Building Plans Picked Up 9/18/2019 APPLICANT
Green Plans Picked Up 9/27/2019 APPLICANT
Applicant returned to address corrections 1/13/2020 MICHAEL LOPEZ
Plan Check Approved 2/4/2020 MICHAEL LOPEZ
Issued 2/6/2020 LADBS
CofO in Progress 5/6/2024 CHARLES BOGHOSKHAN
Permit Finaled 5/6/2024 DEROLD HAUFF
CofO Issued 5/6/2024 DEROLD HAUFF
Permit Finaled 5/6/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/8/2019 ERIK BEASLEY
Grading Pre-Inspection Cleared 11/8/2019 PATRICK MISCHLICH
Sewer availability Cleared 11/8/2019 ERIK BEASLEY
Green Code Cleared 1/7/2020 NEGAR NEJAD
Roof/Waste drainage to street Cleared 1/7/2020 NGOC KIEM
Low Impact Development Cleared 1/13/2020 ANDRES COVARRUBIAS
GPI Written Notices Cleared 2/4/2020 MICHAEL LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Torres,, Efren Santos; Lic. No.: S2340 16003 S INDIAN CREEK RD      CERRITOS, CA 90701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/24/2020 Partial Approval CRAIG VAUGHAN
Pre-Inspection 3/24/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/27/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/3/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Partial Approval CRAIG VAUGHAN
Special/Order Compliance 5/29/2020 Approved CRAIG VAUGHAN
Underground Mechanical 5/29/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Partial Approval CRAIG VAUGHAN
Wood Frame 6/12/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 6/24/2020 Partial Approval CRAIG VAUGHAN
HVAC-Rough 6/24/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/24/2020 Approved CRAIG VAUGHAN
Sewer 6/24/2020 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 6/29/2020 Approved CRAIG VAUGHAN
Wood Frame 6/29/2020 Approved CRAIG VAUGHAN
Insulation 7/6/2020 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 7/13/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 7/21/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 7/29/2020 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 7/29/2020 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 8/7/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/6/2020 Approved CRAIG VAUGHAN
Final 10/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 10/6/2020 Approved CRAIG VAUGHAN
Green Building Rough 10/6/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 10/6/2020 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 10/21/2020 Approved CRAIG VAUGHAN
Final 10/21/2020 Conditional Approval CRAIG VAUGHAN
HVAC-Final 10/21/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 10/21/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/21/2020 Approved CRAIG VAUGHAN
Final 5/3/2024 OK to Issue CofO CHARLES BOGHOSKHAN