10901 W RIVERSIDE DR 91602
Certificate Information: 10901 W RIVERSIDE DR 91602
- Application / Permit
- 19010-10000-03602
- Plan Check / Job No.
- B19LA17064
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- New 2-story drive-through restaurant with fire sprinkler throughout the building.
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 8/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | HELEN NGUYEN |
| Corrections Issued | 9/6/2019 | HELEN NGUYEN |
| Disabled Access Plans Picked Up | 9/12/2019 | APPLICANT |
| Quality Review Completed | 9/21/2019 | YOUNG KIM |
| Building Plans Picked Up | 10/10/2019 | APPLICANT |
| Applicant returned to address corrections | 4/27/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/1/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/17/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/25/2021 | HELEN NGUYEN |
| Green Plans Picked Up | 4/5/2021 | APPLICANT |
| Plan Check Approved | 4/27/2021 | HELEN NGUYEN |
| Issued | 5/7/2021 | APPLICANT |
| TCO Issued (Expire Date: 10-16-2022) | 4/19/2022 | RICKEY JACKSON |
| CofO in Progress | 8/12/2022 | JOHN KITCKO |
| Permit Finaled | 8/12/2022 | DAVID TSAU |
| CofO Issued | 8/12/2022 | DAVID TSAU |
| Permit Finaled | 8/12/2022 | DAVID TSAU |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 10/10/2019 | JOE LUCKEY |
| ZA Case | Cleared | 10/10/2019 | JOE LUCKEY |
| Metro Rail approval | Cleared | 10/22/2019 | YOUNG KIM |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 1/29/2020 | GEORGE SUCHAND |
| ZI | Cleared | 2/6/2020 | JOSE ROMERO-NAVARRO |
| Sewer availability | Cleared | 2/20/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 3/3/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/5/2020 | ADRIAN CASTRO |
| Food Service Establishment | Cleared | 8/3/2020 | KENNETH BROWNE |
| DAS Clearance | Cleared | 12/16/2020 | SHINE LIN |
| Food establishment approval | Cleared | 1/6/2021 | LACDHS APPROVED |
| Highway dedication | Cleared | 1/29/2021 | ADRIAN CASTRO |
| Permit | Cleared | 1/29/2021 | ADRIAN CASTRO |
| Green Code | Cleared | 3/25/2021 | HELEN NGUYEN |
| Fire Marshall Fire Life Safety | Cleared | 4/1/2021 | WILLIAM JOHNS |
Contact Information
| Architect | Bickel,, James S; Lic. No.: C20925 | 3600 BIRCH STREET SUITE 120 NEWPORT BEACH, CA 92660 |
| Contractor | C C K Builders Inc; Lic. No.: 855822-B | 625 WEST KATELLA AVENUE #2 ORANGE, CA 92867 |
| Engineer | Bedolla,, Baltazar; Lic. No.: C89875 | 3360 HONEYBROOK WAY APT 20 ONTARIO, CA 91761 |
| Engineer | Lee,, Jin Soo; Lic. No.: C49326 | 4249 WILEY LANE GLENDALE, CA 91214 |
| Engineer | Thompson,, Douglas Sevier; Lic. No.: S2578 | 21084 BAKE PARKWAY SUITE 100 LAKE FOREST, CA 92630 |
| Engineer | Yogeswaran,, Pirathapan; Lic. No.: GE2834 | 915 CARTER ST FOLSOM, CA 95630 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Deputy Reinf. Concrete | 6/30/2021 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 7/2/2021 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 7/13/2021 | Partial Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/15/2021 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 7/20/2021 | Partial Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 7/29/2021 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 8/17/2021 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Concrete | 8/19/2021 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 8/19/2021 | Corrections Issued | JOHN KITCKO |
| Piling/Pier/Caisson | 8/19/2021 | Partial Approval | JOHN KITCKO |
| Reinforced Concrete Frame | 8/19/2021 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Concrete | 8/20/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/30/2021 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 9/10/2021 | Approved | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 9/22/2021 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 9/24/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/24/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 10/13/2021 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/13/2021 | Approved | JOHN KITCKO |
| Green Building Rough | 10/13/2021 | Partial Approval | JOHN KITCKO |
| Structural Steel Frame | 10/13/2021 | Conditional Approval | JOHN KITCKO |
| Verify Sprinkler Sign Off | 10/13/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 10/15/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 10/20/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Wood Construction | 10/22/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Wood Construction | 10/28/2021 | Conditional Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 11/3/2021 | Approved | JOHN KITCKO |
| Green Building Rough | 11/3/2021 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 11/3/2021 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 11/12/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Drilled-In Anchors | 11/16/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 11/16/2021 | Conditional Approval | JEFFREY DURAN |
| Green Building Rough | 11/17/2021 | Approved | JOHN KITCKO |
| Structural Steel Frame | 11/17/2021 | Approved | JOHN KITCKO |
| Wood Frame | 11/17/2021 | Conditional Approval | JOHN KITCKO |
| Insulation | 11/22/2021 | Approved | JOHN KITCKO |
| Drywall Nailing | 12/2/2021 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/7/2021 | Conditional Approval | JOHN KITCKO |
| T-Bar Ceiling | 2/9/2022 | Not Ready for Inspection | JOHN KITCKO |
| T-Bar Ceiling | 3/2/2022 | Approved | JOHN KITCKO |
| Green Building Final | 3/25/2022 | Approved | JOHN KITCKO |
| Verify Rec and Parks Fee Memo | 3/25/2022 | Partial Inspection | JOHN KITCKO |
| Final | 4/13/2022 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 4/13/2022 | Approved | JOHN KITCKO |
| Light Gage Steel Frame | 4/13/2022 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 4/13/2022 | Approved | JOHN KITCKO |
| Wood Frame | 4/13/2022 | Approved | JOHN KITCKO |
| Wall Anchors | 4/14/2022 | Not Ready for Inspection | JOHN KITCKO |
| Final | 4/18/2022 | Conditional Approval | JOHN KITCKO |
| Final | 8/12/2022 | OK to Issue CofO | JOHN KITCKO |