5902 E TIPTON WAY 90042

Certificate Information: 5902 E TIPTON WAY 90042

Application / Permit
19010-10000-03601
Plan Check / Job No.
B19LA17038
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY, TYPE V 21'8"x 27'11" ADU WITH ATTACHED 22'X7'5" UNCOVERED WALKING DECK (<30" ABOVE GRADE). INCLUDE COMBINED ELECT, HVAC, & PLUMBING. ALL WORK PER WFPP.
Permit Issued
Issued on 2/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 PARISA ZAHABI
Corrections Issued 9/6/2019 PARISA ZAHABI
Quality Review Completed 9/12/2019 JASON HEALEY
Building Plans Picked Up 10/11/2019 APPLICANT
Green Plans Picked Up 10/11/2019 APPLICANT
Applicant returned to address corrections 12/30/2019 PARISA ZAHABI
Plan Check Approved 1/28/2020 PARISA ZAHABI
Issued 2/24/2020 LADBS
CofO in Progress 12/7/2020 CRAIG VAUGHAN
Permit Finaled 12/17/2020 DEROLD HAUFF
CofO Issued 12/17/2020 DEROLD HAUFF
Permit Finaled 12/17/2020 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/28/2019 JASON HEALEY
Address approval Cleared 11/13/2019 CELINA MORENO
BHO/Hillside ordinance Cleared 11/13/2019 CELINA MORENO
BHO/Hillside ordinance Cleared 11/13/2019 CELINA MORENO
Drainage to Storm Drain Cleared 11/13/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/13/2019 CELINA MORENO
Hydrant and Access approval Cleared 11/15/2019 ROBERT DUFF
BHO/Hillside ordinance Cleared 12/9/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 12/9/2019 ERIK BEASLEY
Sewer availability Cleared 12/9/2019 ERIK BEASLEY
Low Impact Development Cleared 12/19/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 12/19/2019 EMIL KYUPELYAN
GPI Written Notices Cleared 12/30/2019 PARISA ZAHABI
Green Code Cleared 1/9/2020 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/13/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/14/2020 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/30/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 4/30/2020 Partial Approval COREY HUPP
Wood Frame 4/30/2020 Partial Approval COREY HUPP
BUILDING-Rough-Frame 6/15/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 6/15/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 6/15/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/15/2020 Corrections Issued CRAIG VAUGHAN
Verify Sprinkler Sign Off 6/15/2020 Approved CRAIG VAUGHAN
Wood Frame 6/15/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 6/25/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 7/10/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/10/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/10/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/10/2020 Approved CRAIG VAUGHAN
Wood Frame 7/10/2020 Approved CRAIG VAUGHAN
HVAC-Rough 7/22/2020 Approved CRAIG VAUGHAN
Insulation 7/22/2020 Approved CRAIG VAUGHAN
Drywall Nailing 7/29/2020 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 9/3/2020 Partial Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/30/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/30/2020 SGSOV Not Ready CRAIG VAUGHAN
Final 10/9/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/9/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/9/2020 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 10/9/2020 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 10/9/2020 Corrections Issued CRAIG VAUGHAN
Final 10/16/2020 Corrections Issued CRAIG VAUGHAN
Service/Power Release 10/16/2020 Approved CRAIG VAUGHAN
Smoke Detectors 10/16/2020 Approved CRAIG VAUGHAN
Final 12/4/2020 OK to Issue CofO CRAIG VAUGHAN