5902 E TIPTON WAY 90042
Certificate Information: 5902 E TIPTON WAY 90042
- Application / Permit
- 19010-10000-03601
- Plan Check / Job No.
- B19LA17038
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY, TYPE V 21'8"x 27'11" ADU WITH ATTACHED 22'X7'5" UNCOVERED WALKING DECK (<30" ABOVE GRADE). INCLUDE COMBINED ELECT, HVAC, & PLUMBING. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | PARISA ZAHABI |
| Corrections Issued | 9/6/2019 | PARISA ZAHABI |
| Quality Review Completed | 9/12/2019 | JASON HEALEY |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Green Plans Picked Up | 10/11/2019 | APPLICANT |
| Applicant returned to address corrections | 12/30/2019 | PARISA ZAHABI |
| Plan Check Approved | 1/28/2020 | PARISA ZAHABI |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 12/7/2020 | CRAIG VAUGHAN |
| Permit Finaled | 12/17/2020 | DEROLD HAUFF |
| CofO Issued | 12/17/2020 | DEROLD HAUFF |
| Permit Finaled | 12/17/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/28/2019 | JASON HEALEY |
| Address approval | Cleared | 11/13/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/13/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/13/2019 | CELINA MORENO |
| Drainage to Storm Drain | Cleared | 11/13/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 11/15/2019 | ROBERT DUFF |
| BHO/Hillside ordinance | Cleared | 12/9/2019 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 12/9/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/9/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 12/19/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | EMIL KYUPELYAN |
| GPI Written Notices | Cleared | 12/30/2019 | PARISA ZAHABI |
| Green Code | Cleared | 1/9/2020 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/27/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/13/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2020 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/30/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 4/30/2020 | Partial Approval | COREY HUPP |
| Wood Frame | 4/30/2020 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 6/15/2020 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/15/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 6/15/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/15/2020 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/15/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 6/15/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/25/2020 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/10/2020 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/10/2020 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/10/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/10/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 7/10/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/22/2020 | Approved | CRAIG VAUGHAN |
| Insulation | 7/22/2020 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 7/29/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 9/3/2020 | Partial Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/30/2020 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 10/9/2020 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 10/9/2020 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2020 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 10/9/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 10/9/2020 | Corrections Issued | CRAIG VAUGHAN |
| Final | 10/16/2020 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 10/16/2020 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 10/16/2020 | Approved | CRAIG VAUGHAN |
| Final | 12/4/2020 | OK to Issue CofO | CRAIG VAUGHAN |