18761 W SHERMAN WAY 91335
Certificate Information: 18761 W SHERMAN WAY 91335
- Application / Permit
- 19010-10000-03599
- Plan Check / Job No.
- B19LA17034
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- NEW ONE-STORY DRIVE THROUGH RESTAURANT PER ZA-2019-5577-ZV-CU-CDO
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/9/2019 | FARSHAD ALIMOHAMADI |
| Disabled Access Plans Picked Up | 9/19/2019 | APPLICANT |
| Quality Review Completed | 9/21/2019 | YOUNG KIM |
| Building Plans Picked Up | 9/27/2019 | APPLICANT |
| Green Plans Picked Up | 7/1/2020 | APPLICANT |
| Applicant returned to address corrections | 1/21/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/18/2022 | FARSHAD ALIMOHAMADI |
| Issued | 5/23/2022 | APPLICANT |
| TCO Issued (Expire Date: 09-25-2023) | 3/29/2023 | RICKEY JACKSON |
| TCO Issued (Expire Date: 03-24-2024) | 9/26/2023 | RICKEY JACKSON |
| CofO in Progress | 2/22/2024 | CAMERON CHABAN |
| CofO Issued | 4/23/2024 | RICKEY JACKSON |
| Permit Finaled | 4/23/2024 | RICKEY JACKSON |
Permit Application Clearance Information
| Hold | Cleared | 8/29/2019 | LOURDES RAMIRO |
| Driveway location | Cleared | 2/20/2020 | BRANDON WILSON |
| Driveway location | Cleared | 2/20/2020 | BRANDON WILSON |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/4/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 7/1/2020 | COLIN LOREDO |
| Food Service Establishment | Cleared | 8/3/2020 | KENNETH BROWNE |
| Low Impact Development | Cleared | 8/20/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 8/24/2020 | ADRIAN CASTRO |
| Highway dedication | Cleared | 4/8/2021 | GUILLERMO PETRA |
| Permit | Cleared | 4/8/2021 | GUILLERMO PETRA |
| DAS Clearance | Cleared | 10/4/2021 | ELIZABETH TOMS |
| Trees in Parkway | Cleared | 11/17/2021 | ADALBERTO VERA |
| "Q" conditions | Cleared | 1/19/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/19/2022 | ANACANY HURTADO |
| Supp. Use District POD/CDO/TDO | Cleared | 1/19/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/19/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/19/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/19/2022 | ANACANY HURTADO |
| Food establishment approval | Cleared | 1/20/2022 | LACDHS APPROVED |
| Hydrant and Access approval | Cleared | 2/19/2022 | KURT CORRAL |
| Fire Marshall Fire Life Safety | Cleared | 3/9/2022 | WILLIAM JOHNS |
Contact Information
| Architect | Bickel,, James S; Lic. No.: C20925 | 3600 BIRCH STREET SUITE 120 NEWPORT BEACH, CA 92660 |
| Contractor | C C K Builders Inc; Lic. No.: 855822-B | 625 WEST KATELLA AVENUE #2 ORANGE, CA 92867 |
| Engineer | Thompson,, Douglas Sevier; Lic. No.: S2578 | 21084 BAKE PARKWAY SUITE 100 LAKE FOREST, CA 92630 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/31/2022 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 8/31/2022 | Partial Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 9/2/2022 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 9/7/2022 | No Access for Inspection | EMIL OPFFER |
| Deputy Reinf. Concrete | 9/12/2022 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 9/12/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Deputy Reinf. Concrete | 9/14/2022 | Conditional Approval | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 9/15/2022 | Conditional Approval | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Wood Construction | 10/4/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Wood Construction | 10/6/2022 | Conditional Approval | CAMERON CHABAN |
| Green Building Rough | 10/6/2022 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 10/6/2022 | Not Ready for Inspection | ANDREW DORSO |
| Verify Sprinkler Sign Off | 10/6/2022 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 10/6/2022 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 10/12/2022 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 10/12/2022 | Conditional Approval | CAMERON CHABAN |
| Green Building Rough | 10/14/2022 | Partial Inspection | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 10/14/2022 | Partial Inspection | CAMERON CHABAN |
| Wood Frame | 10/14/2022 | Partial Inspection | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Partial Approval | DANIEL VARNUM |
| Green Building Rough | 10/19/2022 | Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 10/19/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Wood Frame | 10/19/2022 | Partial Approval | CAMERON CHABAN |
| Insulation | 10/21/2022 | Approved | CAMERON CHABAN |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 10/28/2022 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 11/7/2022 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 12/28/2022 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 1/12/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 1/13/2023 | Conditional Approval | CAMERON CHABAN |
| Special/Order Compliance | 1/18/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Verify Sprinkler Sign Off | 1/18/2023 | Partial Approval | CAMERON CHABAN |
| Wood Frame | 1/18/2023 | Conditional Approval | CAMERON CHABAN |
| T-Bar Ceiling | 1/20/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 1/25/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 2/16/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 2/16/2023 | Approved | CAMERON CHABAN |
| Green Building Final | 2/16/2023 | Not Ready for Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 2/16/2023 | Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 2/16/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Wood Frame | 2/16/2023 | Conditional Approval | CAMERON CHABAN |
| Final | 3/24/2023 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 3/24/2023 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Not Ready | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 3/24/2023 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 3/24/2023 | Partial Approval | DANIEL VARNUM |
| Special/Order Compliance | 8/29/2023 | Partial Inspection | CAMERON CHABAN |
| Final | 2/22/2024 | OK to Issue CofO | CAMERON CHABAN |
| Green Building Final | 2/22/2024 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 2/22/2024 | Approved | CAMERON CHABAN |
| Wood Frame | 2/22/2024 | Approved | CAMERON CHABAN |
| Special/Order Compliance | 2/28/2024 | Partial Inspection | ROBERT DAVIS |