6901 N HINDS AVE 91605
Certificate Information: 6901 N HINDS AVE 91605
- Application / Permit
- 19010-10000-03575
- Plan Check / Job No.
- B19LA16920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 9/11/2020
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2019 | APPLICANT |
| Green Plans Picked Up | 8/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 9/3/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 9/12/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Plan Check Approved | 1/24/2020 | SAMUEL GONZALEZ |
| Issued | 9/11/2020 | APPLICANT |
| CofO in Progress | 2/28/2022 | JACK KARGODORIAN |
| No Progress | 3/16/2022 | JOHN JANSON |
| CofO in Progress | 4/13/2022 | MATT KELLERMAN |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 12/4/2019 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 1/14/2020 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 1/17/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 1/17/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/17/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2020 | Conditional Approval | DANIEL DREW |
| BUILDING-Rough-Frame | 1/6/2021 | Partial Approval | DANIEL DREW |
| Green Building Rough | 1/6/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 1/6/2021 | Partial Inspection | DANIEL DREW |
| Verify Sprinkler Sign Off | 1/6/2021 | Not Ready for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 1/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2021 | Partial Approval | DANIEL DREW |
| Green Building Rough | 1/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Insulation | 1/12/2021 | Partial Approval | DANIEL DREW |
| Verify Sprinkler Sign Off | 1/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 2/10/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 4/23/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 4/23/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 4/26/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/26/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/26/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/26/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/26/2021 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 4/26/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/6/2021 | Partial Approval | MISAEL ESPARZA |
| Insulation | 5/11/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/28/2021 | Approved | DANIEL ORRANTE |
| Sewer | 7/29/2021 | Approved | JOHN HAYES |
| Underground Mechanical | 7/29/2021 | Approved | JOHN HAYES |
| Deck | 9/13/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 9/22/2021 | Approved | DANIEL DREW |
| Final | 9/22/2021 | Not Ready for Inspection | DANIEL DREW |
| Footing/Foundation/Slab | 9/22/2021 | Approved | DANIEL DREW |
| Green Building Final | 9/22/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Final | 9/22/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 9/22/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 9/22/2021 | SGSOV Approved | DANIEL DREW |
| Service/Power Release | 9/22/2021 | Not Ready for Inspection | DANIEL DREW |
| Smoke Detectors | 9/22/2021 | Approved | DANIEL DREW |
| Final | 1/25/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 1/25/2022 | Approved | RICHARD DOCKUS |
| Service/Power Release | 1/25/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 1/26/2022 | Corrections Issued | RICHARD DOCKUS |
| Service/Power Release | 1/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 2/24/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 2/24/2022 | Approved | JACK KARGODORIAN |
| Final | 2/28/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Special/Order Compliance | 3/17/2022 | Corrections Issued | JACK KARGODORIAN |