51 WORLD WAY 90045

Certificate Information: 51 WORLD WAY 90045

Application / Permit
19010-10000-03537
Plan Check / Job No.
B19LA16658
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(15) Electrical Distributing Substation
Work Description
New 1-story Concrete building to house the traction power substation system (TPSS #1).
Permit Issued
Issued on 4/9/2020
Issuing Office
Metro
Current Status
Issued on 4/9/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/9/2019 APPLICANT
Green Plans Picked Up 8/16/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 RODOLFO ARIAS
Corrections Issued 8/26/2019 RODOLFO ARIAS
Quality Review Completed 8/30/2019 MINYE PAK
Building Plans Picked Up 9/13/2019 APPLICANT
Disabled Access Plans Picked Up 9/13/2019 APPLICANT
Applicant returned to address corrections 11/4/2019 RODOLFO ARIAS
Applicant returned to address corrections 11/21/2019 RODOLFO ARIAS
Applicant returned to address corrections 12/2/2019 RODOLFO ARIAS
Applicant returned to address corrections 1/10/2020 RODOLFO ARIAS
Applicant returned to address corrections 2/10/2020 RODOLFO ARIAS
Plan Check Approved 4/3/2020 RODOLFO ARIAS
Issued 4/9/2020 LADBS
TCO Issued (Expire Date: 08-25-2026) 2/26/2026 NICK LAROCCA

Permit Application Clearance Information

CPC Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 8/27/2019 SOPHIE GABEL-SCHEINBAU
City owned building/parcel Cleared 8/28/2019 HAROOT AVANESIAN
Low Impact Development Cleared 9/13/2019 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 9/17/2019 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 9/17/2019 ANTHONY MAINEZ
Sewer availability Cleared 9/17/2019 ANTHONY MAINEZ
Project Permit Cleared 9/19/2019 LAX APPROVED
Miscellaneous Cleared 10/28/2019 PEDRO AYALA
Specific Plan Cleared 10/28/2019 PEDRO AYALA
Hydrant and Access approval Cleared 11/21/2019 JOHN CONNEALLY
DAS Clearance Cleared 11/26/2019 WAI LAU
Airport buildings Cleared 12/2/2019 ANDREW KO
Excavation more than 5-ft deep Cleared 1/10/2020 CALOSHA APPROVED
Green Code Cleared 2/7/2020 DONALD CRICHLOW

Contact Information

Architect Youn,, Heesik; Lic. No.: C32969 4770 ARBORS CIRCLE      MUKILTEO, WA 98275
Contractor Fluor Flatiron Balfour Beatty Dragados; Lic. No.: 1036344-B 5050 BUSINESS CENTER DRIVE   SUITE 250    FAIRFIELD, CA 94534
Engineer Kashighandi,, Pirooz; Lic. No.: GE3104 1417 S WESTGATE AVE 207      LOS ANGELES, CA 90025
Engineer Ng,, Eric Cheung Chun; Lic. No.: S3583 17785 PENNACOOK CT      SAN DIEGO, CA 92127
Engineer Shinmei,, Robert Masaji; Lic. No.: C88334 416 S SAN MARINO AVE      PASADENA, CA 91107

Inspector Information

NICK LAROCCA, (213) 473-2153 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/3/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 10/17/2020 Partial Approval JONATHAN ALLEN
Pre-Inspection 10/19/2020 Approved JONATHAN ALLEN
Pre-Inspection 10/20/2020 Approved JONATHAN ALLEN
Pre-Inspection 10/21/2020 Partial Approval JONATHAN ALLEN
Pre-Inspection 10/23/2020 Approved JONATHAN ALLEN
Pre-Inspection 10/27/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/2/2020 Conditional Approval ALBERT COMISARI
Pre-Inspection 11/4/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/5/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/6/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/12/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/13/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/16/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/17/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/18/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/19/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/20/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/23/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/24/2020 Approved JONATHAN ALLEN
Pre-Inspection 11/25/2020 Approved JONATHAN ALLEN
Piling/Pier/Caisson 12/1/2020 Partial Approval JONATHAN ALLEN
Pre-Inspection 12/1/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/4/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/5/2020 Partial Approval JONATHAN ALLEN
Footing/Foundation/Slab 12/7/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/8/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/9/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/10/2020 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 12/11/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/14/2020 Conditional Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/15/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/16/2020 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 12/17/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/18/2020 Not Ready for Inspection ALBERT COMISARI
Piling/Pier/Caisson 12/21/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/22/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/23/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/24/2020 Conditional Approval ALBERT COMISARI
Piling/Pier/Caisson 12/29/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 12/30/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 1/5/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 1/6/2021 Approved JONATHAN ALLEN
Piling/Pier/Caisson 1/7/2021 Partial Approval JONATHAN ALLEN
Green Building Rough 1/8/2021 Approved JONATHAN ALLEN
Reinforced Concrete Frame 1/8/2021 Partial Approval JONATHAN ALLEN
Verify Sprinkler Sign Off 1/8/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 1/12/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 1/13/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 1/14/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 1/15/2021 Not Ready for Inspection JONATHAN ALLEN
Footing/Foundation/Slab 1/19/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 1/20/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 1/21/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 1/22/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 1/25/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 1/26/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 1/27/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 1/29/2021 Partial Approval JONATHAN ALLEN
Reinforced Concrete Frame 1/29/2021 Partial Approval JONATHAN ALLEN
Verify Sprinkler Sign Off 1/29/2021 Approved JONATHAN ALLEN
Piling/Pier/Caisson 2/1/2021 Partial Approval JONATHAN ALLEN
Footing/Foundation/Slab 2/3/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/5/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/8/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/9/2021 Partial Approval JONATHAN ALLEN
Footing/Foundation/Slab 2/10/2021 Partial Approval JONATHAN ALLEN
Reinforced Concrete Frame 2/10/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/12/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/16/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/17/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 2/18/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/19/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/23/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 2/24/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 2/25/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 2/26/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/1/2021 Partial Approval JONATHAN ALLEN
Footing/Foundation/Slab 3/2/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/9/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 3/10/2021 Partial Approval JONATHAN ALLEN
Reinforced Concrete Frame 3/11/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 3/12/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/15/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 3/16/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/17/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/18/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/19/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 3/22/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 3/23/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/24/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/25/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 3/30/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 3/31/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 4/1/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/7/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/7/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 4/8/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 4/9/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/13/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 4/14/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/15/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 4/16/2021 Not Ready for Inspection JONATHAN ALLEN
Reinforced Concrete Frame 4/16/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/19/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 4/20/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/21/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 4/22/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/23/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 4/26/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 4/28/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/4/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/5/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/7/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/12/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/13/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/14/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/18/2021 Partial Inspection JONATHAN ALLEN
Reinforced Concrete Frame 5/19/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/20/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/21/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/24/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 5/25/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/26/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/27/2021 Partial Approval JONATHAN ALLEN
Deputy Grading 5/28/2021 Conditional Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/28/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 6/1/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/2/2021 Not Ready for Inspection JONATHAN ALLEN
Reinforced Concrete Frame 6/3/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/4/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/8/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 6/9/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 6/11/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 6/14/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/15/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/16/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/17/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/18/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 6/21/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/22/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 6/23/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 6/24/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/30/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 7/1/2021 Partial Approval JONATHAN ALLEN
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/7/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/8/2021 Not Ready for Inspection JONATHAN ALLEN
Reinforced Concrete Frame 7/8/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 7/9/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/12/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 7/13/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/14/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/15/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 7/16/2021 Partial Approval ALAN NOVAK
Piling/Pier/Caisson 7/19/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/20/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/21/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 7/22/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 7/23/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/26/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/27/2021 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 7/28/2021 Partial Inspection JONATHAN ALLEN
Piling/Pier/Caisson 7/30/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 8/3/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 8/4/2021 Not Ready for Inspection JONATHAN ALLEN
Piling/Pier/Caisson 8/10/2021 Partial Approval JONATHAN ALLEN
Reinforced Concrete Frame 9/17/2021 Partial Approval JONATHAN ALLEN
Reinforced Concrete Frame 11/15/2021 Not Ready for Inspection JONATHAN ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval JONATHAN ALLEN
Footing/Foundation/Slab 2/8/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 2/8/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 4/29/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 5/2/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 5/3/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 5/4/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 5/5/2022 Conditional Approval ALAN NOVAK
Footing/Foundation/Slab 5/13/2022 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 5/26/2022 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 5/31/2022 Approved NICK LAROCCA
Posting Pre-Inspection 6/3/2022 Approved NICK LAROCCA
Pre-Inspection 6/3/2022 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/10/2022 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 6/10/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 7/1/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 7/5/2022 Conditional Approval ALAN NOVAK
Deputy Drilled-In Anchors 7/6/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 7/7/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 7/8/2022 Approved NICK LAROCCA
Reinforced Masonry Frame 9/14/2022 Partial Approval NICK LAROCCA
Pre-Inspection 10/14/2022 Approved ALAN NOVAK
Special/Order Compliance 10/17/2022 Approved ALAN NOVAK
Drywall Nailing 12/18/2025 Approved NICK LAROCCA
Final 12/18/2025 Not Ready for Inspection NICK LAROCCA
Green Building Final 12/18/2025 Approved NICK LAROCCA
Reinforced Masonry Frame 12/18/2025 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Approved NICK LAROCCA
Smoke Detectors 12/18/2025 Approved NICK LAROCCA
Special/Order Compliance 12/23/2025 Partial Approval NICK LAROCCA