1600 E VENICE BLVD 1-77 90291
Certificate Information: 1600 E VENICE BLVD 1-77 90291
- Application / Permit
- 19010-10000-03473
- Plan Check / Job No.
- B19LA16235
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 77 Unit Apartment Bldg. 4-Stories over a Subterranean Garage ( TYPE : VA / 1A). Per TOC guidelines.
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | VU NGUYEN |
| Corrections Issued | 8/30/2019 | VU NGUYEN |
| Quality Review Completed | 9/13/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 2/11/2021 | VU NGUYEN |
| Plan Check Approved | 8/3/2022 | VU NGUYEN |
| Issued | 8/9/2022 | APPLICANT |
| Building Plans Picked Up | 8/10/2022 | APPLICANT |
| TCO Issued (Expire Date: 01-25-2026) | 7/29/2025 | HENRY BAGHDASSARIAN |
| CofO in Progress | 9/4/2025 | DERRICK SPENCER |
| Permit Finaled | 9/4/2025 | HENRY BAGHDASSARIAN |
| CofO Issued | 9/4/2025 | HENRY BAGHDASSARIAN |
| Permit Finaled | 9/4/2025 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | JUAN ASHTON |
| Trees in Parkway | Cleared | 2/19/2020 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 3/5/2020 | ROBERT DUFF |
| Density Bonus 12.22.A.31 | Cleared | 2/2/2021 | DORIS KWOK |
| Low Impact Development | Cleared | 6/22/2021 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 9/30/2021 | AARON COSTA |
| DAS Clearance | Cleared | 11/10/2021 | VU NGUYEN |
| Fire Marshall Fire Life Safety | Cleared | 11/23/2021 | OSCAR SALGADO JR |
| Sewer availability | Cleared | 1/25/2022 | DINAH GARIN |
| Highway dedication | Cleared | 2/7/2022 | RAYMOND MUGAMBWA |
| Housing rent stabilization | Cleared | 2/24/2022 | MICHAEL SOTO |
| "Q" conditions | Cleared | 4/4/2022 | RYAN LY |
| Miscellaneous | Cleared | 4/4/2022 | RYAN LY |
| Opn space landscape/Water mgmt | Cleared | 4/4/2022 | RYAN LY |
| Prkng lot landscape/Water mgmt | Cleared | 4/4/2022 | RYAN LY |
| Miscellaneous | Cleared | 4/6/2022 | RYAN LY |
| Internal circulation | Cleared | 6/3/2022 | PEDRO AYALA |
| Specific Plan | Cleared | 6/3/2022 | PEDRO AYALA |
| Specific Plan | Cleared | 6/7/2022 | PEDRO AYALA |
| Transportation Demand Ord. | Cleared | 6/7/2022 | PEDRO AYALA |
| Work Adjacent to Public Way | Cleared | 7/22/2022 | SAUL GARCIA |
| Permit | Cleared | 7/29/2022 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | VLADIMIR ARUTYUNYAN |
| Building over 3-story or 36-ft | Cleared | 8/3/2022 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 8/3/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Uriu,, Giovanni; Lic. No.: C7487 | 830 SO GLENDALE AVENUE GLENDALE, CA 91205 |
| Contractor | Owner-Builder | , |
| Engineer | Dejban,, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 120 W WILSON AVE 1550 GLENDALE, CA 91203 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/17/2022 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 11/15/2022 | Partial Approval | DERRICK SPENCER |
| Deputy Shotcrete | 12/5/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/6/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/7/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/8/2022 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 12/8/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/9/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/15/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/12/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 2/7/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/10/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/13/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/26/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/16/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/16/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 9/20/2023 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 9/20/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 9/20/2023 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 9/28/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 10/12/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 10/27/2023 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 10/31/2023 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 11/3/2023 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 11/8/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 11/9/2023 | No Access for Inspection | PAUL DAVIDSON |
| Insulation | 11/13/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 11/21/2023 | Partial Approval | DERRICK SPENCER |
| Insulation | 12/11/2023 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 12/15/2023 | Partial Inspection | DERRICK SPENCER |
| Drywall Nailing | 12/21/2023 | Partial Approval | NICK LAROCCA |
| Drywall Nailing | 12/27/2023 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 12/27/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 1/3/2024 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 10/8/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/27/2025 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/12/2025 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 2/12/2025 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Ready | DERRICK SPENCER |
| Wood Frame | 2/12/2025 | Approved | DERRICK SPENCER |
| Final | 7/25/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 7/25/2025 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 7/25/2025 | Approved | DERRICK SPENCER |
| Final | 7/28/2025 | OK to Issue CofO | DERRICK SPENCER |