127 W 105TH ST 90003
Certificate Information: 127 W 105TH ST 90003
- Application / Permit
- 19010-10000-03451
- Plan Check / Job No.
- B19LA16187
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 2-STORY (24'-8" X 24'-3") ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT AB 494 AND SB 229.
- Permit Issued
- Issued on 2/19/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | MICHAEL LOPEZ |
| Corrections Issued | 9/3/2019 | MICHAEL LOPEZ |
| Quality Review Completed | 9/7/2019 | STANLEY RAAP |
| Building Plans Picked Up | 9/12/2019 | APPLICANT |
| Applicant returned to address corrections | 2/14/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 2/19/2020 | MICHAEL LOPEZ |
| Issued | 2/19/2020 | LADBS |
| Green Plans Picked Up | 4/6/2020 | APPLICANT |
| CofO in Progress | 2/10/2021 | ANSON MAGLASANG |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
| CofO Issued | 2/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 8/9/2019 | CYNTHIA RYAN |
| Address approval | Cleared | 12/20/2019 | HOK CHI CHIU |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 1/28/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 1/28/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/28/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/28/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 2/4/2020 | SARAH ABOULHOSN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/27/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 3/3/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/21/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/27/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/2/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 6/2/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 6/2/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/4/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 6/4/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 6/4/2020 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 6/4/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2020 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2020 | Partial Approval | EUGENE CASSIDY |
| Sewer | 7/30/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/19/2020 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/19/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/19/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/19/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/27/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/27/2020 | Approved | EUGENE CASSIDY |
| Insulation | 10/7/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 10/7/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/15/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/16/2020 | Approved | EUGENE CASSIDY |
| Final | 12/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 12/16/2020 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/16/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 12/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/8/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/8/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 1/8/2021 | Approved | EUGENE CASSIDY |
| Final | 1/12/2021 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/12/2021 | SGSOV Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/25/2021 | Approved | EUGENE CASSIDY |
| Final | 1/25/2021 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 1/25/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/25/2021 | Approved | EUGENE CASSIDY |