6706 S MAIN ST 90003

Certificate Information: 6706 S MAIN ST 90003

Application / Permit
19010-10000-03444
Plan Check / Job No.
B19LA16167
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
FOR NEW MIXED USE 100%AFFORDABLE HOUSING 5-STORY BLDG
Permit Issued
Issued on 12/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 VU NGUYEN
Corrections Issued 9/16/2019 VU NGUYEN
Quality Review Completed 10/3/2019 JOSE RODRIGUEZ
Building Plans Picked Up 10/25/2019 APPLICANT
Applicant returned to address corrections 3/4/2020 VU NGUYEN
Applicant returned to address corrections 6/25/2020 VU NGUYEN
Applicant returned to address corrections 6/30/2020 VU NGUYEN
Applicant returned to address corrections 10/22/2020 VU NGUYEN
Applicant returned to address corrections 11/5/2020 VU NGUYEN
Applicant returned to address corrections 12/7/2020 VU NGUYEN
Green Plans Picked Up 12/15/2020 APPLICANT
Plan Check Approved 12/18/2020 VU NGUYEN
Issued 12/22/2020 APPLICANT
TCO Issued (Expire Date: 01-18-2025) 7/22/2024 ERNESTO CORRAL
CofO in Progress 1/8/2025 JAMES POWERS
CofO Issued 1/8/2025 ERNESTO CORRAL
Permit Finaled 1/8/2025 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 6/25/2020 RUBEN VASQUEZ
Community Plan Implem. Overlay Cleared 6/26/2020 HELEN JADALI
Address approval Cleared 7/16/2020 THOMAS LANG
Housing rent stabilization Cleared 7/16/2020 MICHAEL GREGERSON
Comm Cor/Mini-Mall Cleared 7/17/2020 RUBEN VASQUEZ
Comm Cor/Mini-Mall Cleared 7/17/2020 RUBEN VASQUEZ
Comm Cor/Mini-Mall Cleared 7/17/2020 RUBEN VASQUEZ
Site Plan review Cleared 7/17/2020 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 7/23/2020 THOMAS LANG
Prkng lot landscape/Water mgmt Cleared 7/23/2020 RUBEN VASQUEZ
Low Impact Development Cleared 7/31/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/6/2020 THOMAS LANG
Building over 3-story or 36-ft Cleared 8/20/2020 CALOSHA APPROVED
Highway dedication Cleared 9/16/2020 THOMAS LANG
Hydrant and Access approval Cleared 9/16/2020 MATTHEW CRAIG
Permit Cleared 9/16/2020 THOMAS LANG
Project located in CRA area Cleared 9/18/2020 GISELLE CORELLA
Sewer availability Cleared 9/23/2020 PAMELA TENEZA
Trees in Parkway Cleared 10/27/2020 JOHN KIM
Green Code Cleared 11/4/2020 VU NGUYEN
Density Bonus 12.22.A.31 Cleared 11/10/2020 MICHAEL ZIRBES
Public Housing Cleared 11/10/2020 GLEN OLIVER
Fire Marshall Fire Life Safety Cleared 12/2/2020 VIDAL GARCIA
DAS Clearance Cleared 12/17/2020 VU NGUYEN

Contact Information

Architect Molina,, Javier Martin; Lic. No.: C23685 625 SOUTH PROSPERO DRIVE      WEST COVINA, CA 91791
Engineer Eosakul,, Dissakorn; Lic. No.: S5226 8363 EDGE WOOD ST      CHINO, CA 91708
Geologist Kirkgard,, Susan Franzen; Lic. No.: EG1754 1481 STONEBROOK STREET      AZUSA, CA 91702

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/15/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/15/2021 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/18/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/22/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/30/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/5/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/22/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/26/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/1/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/7/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/15/2021 Partial Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 6/17/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 6/18/2021 Conditional Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 6/22/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 7/8/2021 Conditional Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/8/2021 Partial Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/13/2021 Partial Inspection LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/27/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/28/2021 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Wood Construction 8/20/2021 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 8/23/2021 Conditional Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 8/23/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 8/27/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 8/31/2021 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Corrections Issued LEOPOLDO MENDOZA
Deputy Wood Construction 9/3/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Wood Construction 9/17/2021 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Inspection LEOPOLDO MENDOZA
Pre-Inspection 9/17/2021 Partial Inspection LEOPOLDO MENDOZA
Wood Frame 9/17/2021 Partial Inspection LEOPOLDO MENDOZA
Deputy Steel/Welding 9/22/2021 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 9/23/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 9/24/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 9/27/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 9/28/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 9/29/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 9/30/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 10/1/2021 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Partial Approval LEOPOLDO MENDOZA
Light Gage Steel Frame 10/5/2021 Partial Inspection LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Partial Approval RUSSELL BONVOULOIR
Wood Frame 10/8/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Wood Construction 10/15/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Partial Approval JAMES POWERS
Wood Frame 10/15/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/18/2021 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 10/19/2021 Conditional Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 10/29/2021 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Inspection SORIN CIRSTOIU
Deputy Steel/Welding 11/1/2021 Conditional Approval SORIN CIRSTOIU
Drywall Nailing 11/3/2021 Partial Approval SORIN CIRSTOIU
Wood Frame 11/4/2021 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 11/5/2021 Approved SORIN CIRSTOIU
Drywall Nailing 11/5/2021 Partial Approval SORIN CIRSTOIU
Drywall Nailing 11/8/2021 Partial Approval TIMOTHY BUXTON
Wood Frame 11/10/2021 Corrections Issued SORIN CIRSTOIU
Drywall Nailing 11/17/2021 Partial Approval SORIN CIRSTOIU
Insulation 11/17/2021 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 11/17/2021 Partial Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 11/22/2021 Partial Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 11/23/2021 Partial Approval SORIN CIRSTOIU
Insulation 12/2/2021 Partial Approval SORIN CIRSTOIU
Insulation 12/6/2021 Partial Approval JAMES POWERS
Insulation 12/10/2021 Partial Approval SORIN CIRSTOIU
Insulation 12/16/2021 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 12/17/2021 Partial Approval SORIN CIRSTOIU
Insulation 12/27/2021 Partial Approval SORIN CIRSTOIU
Insulation 1/3/2022 Partial Approval SORIN CIRSTOIU
Insulation 1/11/2022 Partial Approval SORIN CIRSTOIU
Insulation 1/20/2022 Partial Approval JONATHAN QUACH
Insulation 1/25/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 2/4/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 2/17/2022 Partial Approval SORIN CIRSTOIU
Insulation 2/22/2022 Corrections Issued SORIN CIRSTOIU
Insulation 3/4/2022 Partial Approval JONATHAN QUACH
Pre-Inspection 3/10/2022 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 4/22/2022 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 5/9/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 5/13/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 5/13/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 6/27/2022 Partial Approval RUSSELL BONVOULOIR
Insulation 6/30/2022 Not Ready for Inspection GREGORY POMISH
Light Gage Steel Frame 7/5/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 7/8/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/21/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/25/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 8/9/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/26/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 9/1/2022 Conditional Approval WINSTON DUNNING
Wood Frame 10/4/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/17/2022 Approved DAVID BURKHEAD
T-Bar Ceiling 11/8/2022 Partial Approval JAMES POWERS
T-Bar Ceiling 11/17/2022 Not Ready for Inspection JAMES POWERS
T-Bar Ceiling 11/18/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/12/2022 Partial Approval JAMES POWERS
T-Bar Ceiling 12/12/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 1/3/2023 Partial Approval JAMES POWERS
T-Bar Ceiling 1/19/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/12/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/10/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/28/2023 Partial Approval JAMES POWERS
Final 11/9/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/9/2023 Approved JAMES POWERS
Green Building Final 11/9/2023 Approved JAMES POWERS
Green Building Rough 11/9/2023 Approved JAMES POWERS
Reinforced Concrete Frame 11/9/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/9/2023 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved JAMES POWERS
Smoke Detectors 11/9/2023 Approved JAMES POWERS
Structural Steel Frame 11/9/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/9/2023 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/15/2023 Partial Approval JAMES POWERS
Special/Order Compliance 12/4/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 1/7/2025 Approved JAMES POWERS
Final 1/8/2025 OK to Issue CofO JAMES POWERS
Reinforced Concrete Frame 1/8/2025 Approved JAMES POWERS
Reinforced Masonry Frame 1/8/2025 Approved JAMES POWERS
Structural Steel Frame 1/8/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 1/8/2025 Approved JAMES POWERS