5138 S BROADWAY 90037

Certificate Information: 5138 S BROADWAY 90037

Application / Permit
19010-10000-03307
Plan Check / Job No.
B19LA16012
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4-STORY APARTMENT BUILDING (3 STORIES TYPE IIB FACTORY BUILT HOUSING OVER 1 STORY TYPE IA), 49 STATE APPROVED MODULAR UNITS. TOC TIER 2 PROJECT (100 % AFFORDABLE, 48 PERMANENT SUPPORTIVE HOUSING UNITS) PAR 2019-1193 TOC. <<NO EXCAVATION NEXT ANY PROPERTY LINES UNTIL BOE APPROVAL AND 30-DAY NOTICE OF EXCAVATION PROVIDED>> << NO CERTIFICATE OF OCCUPANCY UNTIL ROOFTOP DECK MAINTENANCE OF BLDG SUPPORT AFFIDAVIT IS RECORDED>>
Permit Issued
Issued on 1/29/2021
Issuing Office
Current Status
CofO Issued on 1/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 ALBERT SERVIN
Corrections Issued 8/27/2019 ALBERT SERVIN
Disabled Access Plans Picked Up 8/30/2019 APPLICANT
Quality Review Completed 9/4/2019 GARO TELMI
Building Plans Picked Up 9/6/2019 APPLICANT
Applicant returned to address corrections 11/22/2019 ALBERT SERVIN
Applicant returned to address corrections 6/30/2020 ALBERT SERVIN
Applicant returned to address corrections 7/2/2020 ALBERT SERVIN
Applicant returned to address corrections 10/1/2020 ALBERT SERVIN
Applicant returned to address corrections 10/28/2020 ALBERT SERVIN
Applicant returned to address corrections 11/20/2020 ALBERT SERVIN
Green Plans Picked Up 11/25/2020 APPLICANT
Applicant returned to address corrections 1/13/2021 ALBERT SERVIN
Plan Check Approved 1/28/2021 ALBERT SERVIN
Issued 1/29/2021 APPLICANT
TCO Issued (Expire Date: 04-30-2023) 11/1/2022 TED RIES
CofO in Progress 1/17/2023 JAMES POWERS
CofO Issued 1/17/2023 ERNESTO CORRAL
Permit Finaled 1/17/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 12/23/2019 EMIL KYUPELYAN
Miscellaneous Cleared 12/23/2019 RICHARD REASER
ZA Case Cleared 12/23/2019 RICHARD REASER
Community Plan Implem. Overlay Cleared 1/15/2020 HELEN JADALI
Community Plan Implem. Overlay Cleared 2/13/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/28/2020 JUAN ASHTON
ZA Case Cleared 3/6/2020 ANACANY HURTADO
Density Bonus 12.22.A.31 Cleared 10/7/2020 DORIS KWOK
Encroachment in public way Cleared 10/16/2020 ELAINE LEI
Opn space landscape/Water mgmt Cleared 10/16/2020 RICHARD REASER
Project located in CRA area Cleared 10/27/2020 GRACIELA ACOSTA
Highway dedication Cleared 11/4/2020 JAMES MORALEZ
Community Plan Implem. Overlay Cleared 11/17/2020 JOHN KIM
Trees in Parkway Cleared 11/19/2020 JOHN KIM
Building over 3-story or 36-ft Cleared 11/20/2020 CALOSHA APPROVED
Community Plan Implem. Overlay Cleared 11/24/2020 PETE EYRE
Internal circulation Cleared 11/24/2020 PETE EYRE
Green Code Cleared 11/25/2020 ALBERT SERVIN
Permit Cleared 12/15/2020 JAMES MORALEZ
Community Plan Implem. Overlay Cleared 1/5/2021 WALTER RAMIREZ
Sewer availability Cleared 1/11/2021 RENZ SORIANO
Hydrant and Access approval Cleared 1/12/2021 JEREMY CARTER
Low Impact Development Cleared 1/19/2021 MARTIN FRAGOSO
Miscellaneous Cleared 1/22/2021 HELEN JADALI
Public Housing Cleared 1/25/2021 THOMAS ANTONIO
DAS Clearance Cleared 1/28/2021 ALBERT SERVIN
Fire Marshall Fire Life Safety Cleared 1/28/2021 WILLIAM JOHNS
Roof/Waste drainage to street Cleared 1/28/2021 ROSA SILVA

Contact Information

Architect Wong,, Wilbur; Lic. No.: C29795 9142 HYDE PARK DRIVE      HUNTINGTON BEACH, CA 92646
Contractor Hoffman Management & Construction Corporation; Lic. No.: 506092-A 984 MCGARRY ST STE 101      LOS ANGELES, CA 90021
Engineer Tavares,, Ralph Monteiro; Lic. No.: C60484 11777 BERNARDO PLAZA CT      SAN DIEGO, CA 92128

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/21/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 5/26/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/11/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/21/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/23/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/1/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/1/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/2/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/6/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/6/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/7/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/7/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/7/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/7/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 7/7/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/7/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/7/2021 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 7/8/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/8/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/8/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/8/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/9/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/9/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/12/2021 Conditional Approval DAVID TSAU
Deputy Shotcrete 7/12/2021 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 7/13/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/14/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/15/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/16/2021 Approved JOEY BUCHANAN
Deputy Shotcrete 7/16/2021 Approved JOEY BUCHANAN
Reinforced Concrete Frame 7/19/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/20/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/20/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/21/2021 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/21/2021 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 7/21/2021 Not Ready for Inspection ERNESTO CORRAL
Insulation 7/21/2021 Not Ready for Inspection ERNESTO CORRAL
Deputy Other (see comments) 7/22/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/22/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/22/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/23/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/23/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/26/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/11/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/12/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 8/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/12/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/13/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 8/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/13/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/31/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/1/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/2/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 9/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/14/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/29/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/29/2021 Partial Approval DAVID TSAU
Excavation/Setback/Form/Re-Bar 9/30/2021 Partial Approval JONATHAN QUACH
Deputy Other (see comments) 10/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/7/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/14/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/21/2021 Conditional Approval JONATHAN QUACH
Light Gage Steel Frame 11/1/2021 Partial Approval MARK FERRARI
Light Gage Steel Frame 12/1/2021 Partial Approval JAMES POWERS
Insulation 12/2/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/3/2021 Partial Approval JAMES POWERS
Green Building Rough 12/3/2021 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 2/2/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/3/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/8/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/9/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/18/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/22/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/23/2022 Partial Approval JAMES POWERS
Green Building Rough 2/23/2022 Approved JAMES POWERS
Structural Steel Frame 2/23/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/23/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 2/24/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 2/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/28/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/1/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/2/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/3/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/8/2022 Partial Approval JAMES POWERS
Structural Steel Frame 3/8/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/9/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/15/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/16/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/18/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/22/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/25/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/1/2022 Partial Approval TED RIES
Light Gage Steel Frame 4/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/15/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/19/2022 Partial Approval DAVID BURKHEAD
Special/Order Compliance 4/20/2022 Approved TED RIES
Drywall Nailing 4/26/2022 Partial Approval TED RIES
Drywall Nailing 5/2/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/9/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/17/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/22/2022 Partial Approval JAMES POWERS
T-Bar Ceiling 6/22/2022 Not Ready for Inspection JAMES POWERS
Deputy Other (see comments) 7/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/6/2022 Conditional Approval ERNESTO CORRAL
Insulation 7/12/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/14/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/14/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/26/2022 Approved JAMES POWERS
Drywall Nailing 9/22/2022 Approved JAMES POWERS
Final 9/22/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/22/2022 Approved JAMES POWERS
Green Building Final 9/22/2022 Approved JAMES POWERS
Reinforced Concrete Frame 9/22/2022 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/22/2022 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Not Ready JAMES POWERS
Smoke Detectors 9/22/2022 Approved JAMES POWERS
Structural Steel Frame 9/22/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/22/2022 Not Ready for Inspection JAMES POWERS
Final 12/16/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/16/2022 Approved JAMES POWERS
Reinforced Masonry Frame 12/16/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Approved JAMES POWERS
Structural Steel Frame 12/16/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 12/16/2022 Approved JAMES POWERS
Final 12/27/2022 Not Ready for Inspection JAMES POWERS
Final 1/9/2023 Partial Approval JAMES POWERS
Final 1/17/2023 OK to Issue CofO JAMES POWERS