2925 W WAVERLY DR 90039

Certificate Information: 2925 W WAVERLY DR 90039

Application / Permit
19010-10000-03272
Plan Check / Job No.
B19LA15867
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FOR NEW THREE STORY SFD/GAR PER VTT 72367-5L-IA (LOT 1), Comply with department order effective date 07/15/2019 CEIS case number is 868174.
Permit Issued
Issued on 6/12/2020
Issuing Office
Current Status
CofO Issued on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 TSE MING HUANG
Corrections Issued 8/26/2019 TSE MING HUANG
Green Plans Picked Up 9/4/2019 APPLICANT
Quality Review Completed 9/7/2019 STANLEY RAAP
Applicant returned to address corrections 11/18/2019 TSE MING HUANG
Applicant returned to address corrections 12/12/2019 TSE MING HUANG
Applicant returned to address corrections 1/10/2020 TSE MING HUANG
Applicant returned to address corrections 1/13/2020 TSE MING HUANG
Applicant returned to address corrections 2/14/2020 TSE MING HUANG
Plan Check Approved 6/4/2020 TSE MING HUANG
Issued 6/12/2020 APPLICANT
Building Plans Picked Up 6/12/2020 APPLICANT
CofO in Progress 6/6/2022 SCOTT FINNILA
Permit Finaled 6/7/2022 DEROLD HAUFF
CofO Issued 6/7/2022 DEROLD HAUFF
Permit Finaled 6/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 8/20/2019 CYNTHIA RYAN
Address approval Cleared 11/8/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 11/8/2019 ERIK BEASLEY
Highway dedication Cleared 11/8/2019 ERIK BEASLEY
Permit Cleared 11/8/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 11/12/2019 JEANIE LAM
BHO/Hillside ordinance Cleared 11/12/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/12/2019 JEANIE LAM
Miscellaneous Cleared 11/12/2019 LAMBERT GIESSINGER
ZA Case Cleared 11/12/2019 ANNA VAN
Hydrant and Access approval Cleared 11/18/2019 JEREMY CARTER
Sewer availability Cleared 11/18/2019 JEANIE LAM
ZI Cleared 11/21/2019 JOE LUCKEY
Green Code Cleared 11/22/2019 VIVIAN LAO
Low Impact Development Cleared 12/5/2019 ORVAL HERNANDEZ-MARCI
Grading Pre-Inspection Cleared 12/30/2019 TSE MING HUANG
Miscellaneous Cleared 1/7/2020 LINDA MARGARET
Roof/Waste drainage to street Cleared 1/7/2020 LINDA MARGARET
Miscellaneous Cleared 3/2/2020 JOE LUCKEY
Miscellaneous Cleared 3/2/2020 JOE LUCKEY
Tract Map conditions Cleared 3/2/2020 JOE LUCKEY

Contact Information

Architect Gibbs,, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Owner-Builder       ,
Engineer Levitas,, Felix; Lic. No.: C62311 6634 VALJEAN AVE      VAN NUYS, CA 91406
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/23/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 9/24/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 10/2/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 10/5/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 10/7/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 10/9/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 10/15/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 10/15/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 10/19/2020 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 Conditional Approval SCOTT FINNILA
Drywall Nailing 11/25/2020 Corrections Issued SCOTT FINNILA
Drywall Nailing 12/2/2020 Partial Inspection ALEJANDRO DE ARTOLA
Drywall Nailing 12/3/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 12/15/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 12/31/2020 Partial Approval SCOTT FINNILA
Green Building Rough 12/31/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/26/2021 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Conditional Approval SCOTT FINNILA
HVAC-Rough 3/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/8/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 4/8/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 4/16/2021 Not Ready for Inspection SCOTT FINNILA
HVAC-Rough 4/16/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 4/16/2021 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 4/16/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 4/22/2021 Approved SCOTT FINNILA
PLUMBING-Rough 4/22/2021 Approved SCOTT FINNILA
ELECTRICAL-Rough 4/29/2021 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 5/3/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 5/3/2021 Approved SCOTT FINNILA
MERV13>=Rough 5/3/2021 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 5/3/2021 Approved SCOTT FINNILA
Deputy Drilled-In Anchors 5/4/2021 Conditional Approval MICHAEL FAUNCE
ELECTRICAL-Rough 5/11/2021 Not Ready for Inspection SCOTT FINNILA
Wood Frame 5/11/2021 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Rough 5/17/2021 Approved SCOTT FINNILA
Wood Frame 5/17/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 5/20/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/20/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 6/9/2021 Approved SCOTT FINNILA
Insulation 6/9/2021 Approved SCOTT FINNILA
Drywall Nailing 6/16/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 6/22/2021 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 6/28/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 7/6/2021 Partial Approval SCOTT FINNILA
HVAC-Rough 10/18/2021 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 10/19/2021 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 10/20/2021 No Access for Inspection SCOTT FINNILA
PLUMBING-Rough 11/3/2021 Partial Approval SCOTT FINNILA
Underground Mechanical 11/3/2021 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 11/19/2021 Partial Approval SCOTT FINNILA
Deputy Reinf. Masonry 12/1/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 12/21/2021 Corrections Issued SCOTT FINNILA
Final 12/21/2021 Corrections Issued SCOTT FINNILA
Green Building Final 12/21/2021 Corrections Issued SCOTT FINNILA
HVAC-Final 12/21/2021 Corrections Issued SCOTT FINNILA
MERV13>=Final 12/21/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Final 12/21/2021 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 12/21/2021 Corrections Issued SCOTT FINNILA
Smoke Detectors 12/21/2021 Approved SCOTT FINNILA
HVAC-Rough 1/28/2022 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 1/28/2022 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Final 1/31/2022 Partial Inspection SCOTT FINNILA
Final 4/25/2022 Partial Inspection SCOTT FINNILA
Final 5/2/2022 Partial Inspection SCOTT FINNILA
Green Building Final 5/2/2022 Partial Inspection SCOTT FINNILA
MERV13>=Final 5/2/2022 Partial Inspection SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 5/2/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 5/11/2022 Corrections Issued STUART CHAPMAN
Final 5/11/2022 Corrections Issued STUART CHAPMAN
Green Building Final 5/11/2022 Corrections Issued STUART CHAPMAN
MERV13>=Final 5/11/2022 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 5/11/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 5/16/2022 Approved SCOTT FINNILA
Final 5/24/2022 Partial Approval SCOTT FINNILA
Green Building Final 5/24/2022 Approved SCOTT FINNILA
HVAC-Final 5/24/2022 Approved SCOTT FINNILA
MERV13>=Final 5/24/2022 Approved SCOTT FINNILA
PLUMBING-Final 5/24/2022 Approved SCOTT FINNILA
Service/Power Release 5/24/2022 Approved SCOTT FINNILA
Final 6/6/2022 OK to Issue CofO SCOTT FINNILA