10918 W CAMARILLO ST 91602

Certificate Information: 10918 W CAMARILLO ST 91602

Application / Permit
19010-10000-03254
Plan Check / Job No.
B19LA15763
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 5-STORY APARTMENT BLDG. WITH PARKING PER TOC (TIER 1) WITH TWO UNITS VERY LOW INCOME (UNITS 202 & 302) AND ONE UNIT EXTREMELY LOW INCOME (UNIT 102).
Permit Issued
Issued on 5/20/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 JOSE RODRIGUEZ
Disabled Access Plans Picked Up 8/23/2019 APPLICANT
Corrections Issued 10/3/2019 JOSE RODRIGUEZ
Quality Review Completed 11/6/2019 QUAN NGHIEM
Building Plans Picked Up 11/12/2019 APPLICANT
Applicant returned to address corrections 2/13/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/27/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/8/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/16/2021 LAWRENCE QUIRANTE
Green Plans Picked Up 6/2/2021 APPLICANT
Applicant returned to address corrections 6/15/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 6/23/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/26/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/22/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/23/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/18/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/7/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/9/2021 LAWRENCE QUIRANTE
Plan Check Approved 12/16/2021 LAWRENCE QUIRANTE
Issued 5/20/2022 APPLICANT
TCO Issued (Expire Date: 08-23-2025) 2/24/2025 RICKEY JACKSON
TCO Issued (Expire Date: 01-24-2026) 7/28/2025 JEFFREY DURAN
CofO in Progress 10/2/2025 JOHN KITCKO
Permit Finaled 10/30/2025 JEFFREY DURAN
CofO Issued 10/30/2025 JEFFREY DURAN
Permit Finaled 10/30/2025 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 11/20/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/20/2019 JEANIE LAM
Miscellaneous Cleared 2/3/2020 JASON CHAN
Miscellaneous Cleared 2/3/2020 JASON CHAN
DAS Clearance Cleared 3/5/2020 JOSE RODRIGUEZ
Permit Cleared 6/29/2020 LEE GUILBEAUX
Sewer availability Cleared 6/29/2020 LEE GUILBEAUX
Highway dedication Cleared 7/1/2020 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 7/9/2020 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 7/9/2020 RUBEN VASQUEZ
Trees in Parkway Cleared 7/21/2020 JOHN KIM
Construction near power lines Cleared 9/12/2020 RIDWAN HARDY
Density Bonus 12.22.A.31 Cleared 11/23/2020 MICHAEL ZIRBES
Density Bonus 12.22.A.31 Cleared 11/23/2020 MICHAEL ZIRBES
Hydrant and Access approval Cleared 1/12/2021 MATTHEW CRAIG
Driveway location Cleared 1/27/2021 COLLINS ALLAN
Building over 3-story or 36-ft Cleared 2/2/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 2/2/2021 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 4/29/2021 MENOA AGHAJANI
Low Impact Development Cleared 5/6/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/7/2021 ADRIAN CASTRO
Green Code Cleared 5/20/2021 AARON COSTA

Contact Information

Contractor Century West Associates Incorporated; Lic. No.: 523872-B 1415 JONESBORO DR      LOS ANGELES, CA 90049
Engineer Afsharhasani,, Rouzbeh; Lic. No.: C87032 1133 CAMELBACK ST 9038      NEWPORT BEACH, CA 92658
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024
Engineer Plouff,, Kacie Allison; Lic. No.: L9013 27821 FREMONT COURT 6      VALENCIA, CA 91355

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/8/2022 Partial Inspection JOHN KITCKO
Deputy Grading 7/27/2022 Conditional Approval JOHN KITCKO
Deputy Grading 7/28/2022 Conditional Approval JOHN KITCKO
Deputy Grading 7/29/2022 Conditional Approval JOHN KITCKO
Special/Order Compliance 8/22/2022 Partial Inspection JOHN KITCKO
Deputy Steel/Welding 10/11/2022 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 10/12/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 11/23/2022 Approved JOHN KITCKO
Footing/Foundation/Slab 11/23/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 12/6/2022 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 12/21/2022 Approved JOHN KITCKO
Green Building Rough 12/22/2022 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 12/22/2022 Corrections Issued JOHN KITCKO
Verify Sprinkler Sign Off 12/22/2022 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 12/27/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 12/28/2022 Approved JOHN KITCKO
Deputy Shotcrete 12/28/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/29/2022 Approved JOHN KITCKO
Deputy Shotcrete 12/29/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/31/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/1/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/2/2023 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 2/2/2023 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 3/13/2023 Corrections Issued JOHN KITCKO
Special/Order Compliance 3/13/2023 Partial Approval STEVEN LEVITT
Excavation/Setback/Form/Re-Bar 3/15/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/30/2023 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 4/7/2023 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 4/25/2023 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 5/19/2023 No Access for Inspection JOHN KITCKO
Footing/Foundation/Slab 5/25/2023 Corrections Issued JOHN KITCKO
Drywall Nailing 5/26/2023 Partial Approval JOHN KITCKO
Green Building Rough 5/26/2023 Not Ready for Inspection JOHN KITCKO
Deputy Wood Construction 6/21/2023 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 7/19/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Partial Approval JOHN KITCKO
Drywall Nailing 7/25/2023 Partial Inspection ANDREW DORSO
Green Building Rough 7/25/2023 Not Ready for Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 8/3/2023 Conditional Approval KENNETH ROBERTS
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 9/11/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 9/13/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Not Ready for Inspection JOHN KITCKO
Green Building Rough 9/13/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 9/13/2023 Approved JOHN KITCKO
Wood Frame 9/13/2023 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 9/19/2023 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Not Ready for Inspection JOHN KITCKO
Insulation 9/29/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Partial Approval JOHN KITCKO
Drywall Nailing 10/11/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Corrections Issued JOHN KITCKO
Green Building Rough 10/11/2023 Not Ready for Inspection JOHN KITCKO
Deputy Wood Construction 10/16/2023 Approved JOHN KITCKO
Drywall Nailing 10/17/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Partial Approval JOHN KITCKO
Green Building Rough 10/17/2023 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 10/20/2023 Not Ready for Inspection JOHN KITCKO
Green Building Rough 10/20/2023 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 10/25/2023 Partial Approval JOHN KITCKO
Green Building Rough 10/25/2023 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Partial Approval JOHN KITCKO
Insulation 11/14/2023 Partial Approval JOHN KITCKO
Deputy Steel/Welding 1/3/2024 Conditional Approval ANDREW DORSO
Interior/Exterior Lathing 1/5/2024 Partial Approval JOHN KITCKO
Green Building Rough 1/23/2024 Approved JOHN KITCKO
Wood Frame 1/23/2024 Approved JOHN KITCKO
Insulation 1/26/2024 Partial Approval JOHN KITCKO
Drywall Nailing 2/2/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 2/7/2024 Partial Approval JOHN KITCKO
Drywall Nailing 2/12/2024 Partial Approval JOHN KITCKO
Drywall Nailing 2/20/2024 Approved DEANDRE HOFFMAN
Special/Order Compliance 2/20/2024 No Access for Inspection MELVIN GIRTON
Special/Order Compliance 2/20/2024 Partial Inspection MELVIN GIRTON
Light Gage Steel Frame 3/4/2024 Conditional Approval JOHN KITCKO
Light Gage Steel Frame 3/14/2024 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 7/17/2024 Conditional Approval JOHN KITCKO
Final 12/31/2024 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 12/31/2024 Approved JOHN KITCKO
Green Building Final 12/31/2024 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 12/31/2024 Approved JOHN KITCKO
Reinforced Masonry Frame 12/31/2024 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Approved JOHN KITCKO
Smoke Detectors 12/31/2024 Approved JOHN KITCKO
Structural Steel Frame 12/31/2024 Approved JOHN KITCKO
Final 1/14/2025 Not Ready for Inspection JOHN KITCKO
Green Building Final 1/14/2025 Approved JOHN KITCKO
Final 1/22/2025 Conditional Approval JOHN KITCKO
Deputy Wood Construction 10/2/2025 Approved JOHN KITCKO
Final 10/2/2025 OK to Issue CofO JOHN KITCKO