1135 N AVENUE 64 90042
Certificate Information: 1135 N AVENUE 64 90042
- Application / Permit
- 19010-10000-03250
- Plan Check / Job No.
- B19LA15723
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 2 STORY GARAGE AND STORAGE
- Permit Issued
- Issued on 12/24/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 8/20/2019 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 8/22/2019 | APPLICANT |
| Quality Review Completed | 9/1/2019 | YOUNG KIM |
| Building Plans Picked Up | 9/12/2019 | APPLICANT |
| Plan Check Approved | 12/20/2019 | ARSALAN SHABESTARI |
| Issued | 12/24/2019 | LADBS |
| CofO in Progress | 5/29/2025 | DAVID WILLIAMS |
| No Progress | 6/3/2025 | DEROLD HAUFF |
| CofO in Progress | 6/3/2025 | DEROLD HAUFF |
| Permit Finaled | 6/12/2025 | DEROLD HAUFF |
| Permit Finaled | 6/12/2025 | DEROLD HAUFF |
| CofO Issued | 6/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 8/20/2019 | KATIE DEBIASE |
| Miscellaneous | Cleared | 8/20/2019 | KATIE DEBIASE |
| ZI | Cleared | 8/20/2019 | KATIE DEBIASE |
| BHO/Hillside ordinance | Cleared | 10/11/2019 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 10/11/2019 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 10/11/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2019 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 10/11/2019 | JEREMY CARTER |
| Permit | Cleared | 10/11/2019 | JAMES MORALEZ |
| Sewer availability | Cleared | 10/11/2019 | JAMES MORALEZ |
| ZA Case | Cleared | 10/11/2019 | TERRI OSBORNE |
| ZA Case | Cleared | 10/11/2019 | TERRI OSBORNE |
| ZA Case | Cleared | 10/11/2019 | TERRI OSBORNE |
| Grading Pre-Inspection | Cleared | 11/8/2019 | ARSALAN SHABESTARI |
| Green Code | Cleared | 11/8/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 11/22/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/25/2019 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2022 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 8/24/2023 | Partial Approval | AMY COLIN |
| Green Building Rough | 8/24/2023 | Not Ready for Inspection | AMY COLIN |
| Deputy Wood Construction | 10/16/2023 | Conditional Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 10/27/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 10/27/2023 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Approved | ROY SPAULDING |
| Pre-Inspection | 11/8/2023 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 12/20/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 2/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 2/22/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Insulation | 2/23/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/23/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/13/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/13/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/13/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/13/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/13/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/13/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/13/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/26/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 3/26/2025 | Partial Approval | DAVID WILLIAMS |
| Pre-Inspection | 3/26/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/26/2025 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 3/26/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 4/11/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 4/11/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 4/11/2025 | Approved | DAVID WILLIAMS |
| Final | 5/5/2025 | Corrections Issued | DAVID WILLIAMS |
| Final | 5/29/2025 | OK to Issue CofO | DAVID WILLIAMS |