800 S 3RD AVE 90005
Certificate Information: 800 S 3RD AVE 90005
- Application / Permit
- 19010-10000-03238
- Plan Check / Job No.
- B19LA15639
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 20' x 20' DETACHED 2 CAR GARAGE.
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2019 | APPLICANT |
| Green Plans Picked Up | 8/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 8/14/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/21/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 8/21/2019 | APPLICANT |
| Applicant returned to address corrections | 3/6/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/20/2020 | SERGIO GUTIERREZ |
| Issued | 8/26/2020 | APPLICANT |
| CofO in Progress | 5/2/2022 | STUART CHAPMAN |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
| CofO Issued | 5/7/2022 | DEROLD HAUFF |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 12/5/2019 | VIVIAN LAO |
| Permit | Cleared | 12/5/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/19/2020 | JOHN CONNEALLY |
| HPOZ | Cleared | 3/18/2020 | AMANDA KAINER |
| Miscellaneous | Cleared | 3/18/2020 | AMANDA KAINER |
| ZI | Cleared | 3/18/2020 | AMANDA KAINER |
| Sewer availability | Cleared | 7/7/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/19/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tagudar,, Fred; Lic. No.: C33612 | 850 E OCEAN BLVD 706 LONG BEACH, CA 90802 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Final | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/2/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Final | 3/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 3/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Green Building Final | 3/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Green Building Rough | 3/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 3/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Smoke Detectors | 3/21/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Final | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Green Building Final | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Green Building Rough | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| HVAC-Final | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| PLUMBING-Final | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Smoke Detectors | 3/30/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Final | 4/1/2022 | Partial Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 4/1/2022 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 4/4/2022 | Approved | CRAIG DAVIS |
| Green Building Final | 4/4/2022 | Approved | CRAIG DAVIS |
| Green Building Rough | 4/4/2022 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 4/4/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Smoke Detectors | 4/4/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 4/11/2022 | No Access for Inspection | ARTHUR SARGSYAN |
| Final | 4/14/2022 | Partial Approval | STUART CHAPMAN |
| Final | 4/18/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 4/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 5/2/2022 | OK to Issue CofO | STUART CHAPMAN |