1621-1623 E 46TH ST 90011
Certificate Information: 1621-1623 E 46TH ST 90011
- Application / Permit
- 19010-10000-03169
- Plan Check / Job No.
- B19LA15240
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE.
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2019 | APPLICANT |
| Green Plans Picked Up | 8/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/13/2019 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 8/31/2019 | YOUNG KIM |
| Building Plans Picked Up | 10/30/2019 | APPLICANT |
| Plan Check Approved | 11/13/2019 | FARSHAD ALIMOHAMADI |
| Issued | 1/10/2020 | LADBS |
| CofO in Progress | 7/25/2020 | ROBERT MCDOWELL |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
| CofO Issued | 9/3/2020 | DEROLD HAUFF |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 11/8/2019 | ADRIAN SANCHEZ |
| Address approval | Cleared | 11/12/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2019 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 11/12/2019 | ROBERT DUFF |
| Permit | Cleared | 11/12/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 11/12/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 11/13/2019 | COLIN LOREDO |
| Low Impact Development | Cleared | 11/13/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/13/2019 | CELINA MORENO |
| ZI | Cleared | 11/13/2019 | TERRI OSBORNE |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/31/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/4/2020 | Approved | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 2/7/2020 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/19/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 2/19/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 2/19/2020 | Conditional Approval | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 2/19/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 2/21/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 4/2/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/5/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/5/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/5/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 5/5/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/5/2020 | Approved | ROBERT MCDOWELL |
| Rough-Elec/Plmb/HVAC | 5/5/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/5/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 5/6/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/14/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/14/2020 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 7/24/2020 | Approved | ROBERT MCDOWELL |
| Final | 7/24/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 7/24/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 7/24/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 7/24/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 7/24/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 7/24/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 7/24/2020 | Approved | ROBERT MCDOWELL |