1621-1623 E 46TH ST 90011

Certificate Information: 1621-1623 E 46TH ST 90011

Application / Permit
19010-10000-03169
Plan Check / Job No.
B19LA15240
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE.
Permit Issued
Issued on 1/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2019 APPLICANT
Green Plans Picked Up 8/6/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 FARSHAD ALIMOHAMADI
Corrections Issued 8/13/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 8/31/2019 YOUNG KIM
Building Plans Picked Up 10/30/2019 APPLICANT
Plan Check Approved 11/13/2019 FARSHAD ALIMOHAMADI
Issued 1/10/2020 LADBS
CofO in Progress 7/25/2020 ROBERT MCDOWELL
Permit Finaled 9/3/2020 DEROLD HAUFF
CofO Issued 9/3/2020 DEROLD HAUFF
Permit Finaled 9/3/2020 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 11/8/2019 ADRIAN SANCHEZ
Address approval Cleared 11/12/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 11/12/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 11/12/2019 ROBERT DUFF
Permit Cleared 11/12/2019 EMIL KYUPELYAN
Sewer availability Cleared 11/12/2019 EMIL KYUPELYAN
Green Code Cleared 11/13/2019 COLIN LOREDO
Low Impact Development Cleared 11/13/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/13/2019 CELINA MORENO
ZI Cleared 11/13/2019 TERRI OSBORNE

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2020 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/4/2020 Approved JOAQUIN GREENOUGH
Deputy Reinf. Concrete 2/7/2020 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/19/2020 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 2/19/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 2/19/2020 Conditional Approval JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 2/19/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 2/21/2020 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/19/2020 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 4/2/2020 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/6/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/5/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 5/5/2020 Approved ROBERT MCDOWELL
Green Building Rough 5/5/2020 Approved ROBERT MCDOWELL
HVAC-Rough 5/5/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 5/5/2020 Approved ROBERT MCDOWELL
Rough-Elec/Plmb/HVAC 5/5/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 5/5/2020 Approved ROBERT MCDOWELL
Insulation 5/6/2020 Approved SABAS ALONSO
Drywall Nailing 5/14/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 5/14/2020 Approved SABAS ALONSO
ELECTRICAL-Final 7/24/2020 Approved ROBERT MCDOWELL
Final 7/24/2020 OK to Issue CofO ROBERT MCDOWELL
Green Building Final 7/24/2020 Approved ROBERT MCDOWELL
HVAC-Final 7/24/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 7/24/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 7/24/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 7/24/2020 Approved ROBERT MCDOWELL
Smoke Detectors 7/24/2020 Approved ROBERT MCDOWELL