9823 N SHADOW ISLAND DR 91040
Certificate Information: 9823 N SHADOW ISLAND DR 91040
- Application / Permit
- 19010-10000-03153
- Plan Check / Job No.
- B19LA15195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. NFPA-13D fire sprinkler is required per 12.21 C.10(h)(1).
- Permit Issued
- Issued on 3/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2019 | APPLICANT |
| Green Plans Picked Up | 8/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 8/30/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/5/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 9/6/2019 | APPLICANT |
| Applicant returned to address corrections | 2/11/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/9/2020 | SERGIO GUTIERREZ |
| Issued | 3/9/2020 | LADBS |
| CofO in Progress | 4/15/2021 | BEAU COLLINS |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/16/2019 | OSCAR CASTRO |
| Sewer availability | Cleared | 10/16/2019 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 10/25/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/25/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 10/25/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 10/25/2019 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 11/6/2019 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 11/6/2019 | SERGIO GUTIERREZ |
| Low Impact Development | Cleared | 11/6/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 11/6/2019 | ERIK BEASLEY |
| Stormwater Pollution Mitigatn | Cleared | 11/6/2019 | ORVAL HERNANDEZ-MARCIAL |
| Green Code | Cleared | 1/28/2020 | NEGAR NEJAD |
| Address approval | Cleared | 2/11/2020 | JEANETTE VONG |
| Specific Plan | Cleared | 2/25/2020 | PEGGY MALONE-BROWN |
Contact Information
| Architect | Powell,, Gregory M; Lic. No.: C28099 | 9821 SHADOW ISLAND DR. SHADOW HILLS, CA 91040 |
| Contractor | Owner-Builder | , |
| Engineer | Mina,, Ehab Iskander; Lic. No.: C62846 | 12940 EXCALIBUR DR CORONA, CA 92880 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Partial Inspection | BEAU COLLINS |
| Sewer | 4/1/2020 | Approved | BEAU COLLINS |
| ELECTRICAL-Rough | 4/8/2020 | Partial Approval | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 4/8/2020 | Not Ready for Inspection | BEAU COLLINS |
| PLUMBING-Rough | 4/8/2020 | Not Ready for Inspection | BEAU COLLINS |
| ELECTRICAL-Rough | 4/15/2020 | Partial Approval | BEAU COLLINS |
| PLUMBING-Rough | 4/15/2020 | Partial Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 4/21/2020 | Approved | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2020 | Partial Approval | BEAU COLLINS |
| Green Building Rough | 7/2/2020 | Not Ready for Inspection | BEAU COLLINS |
| Verify Sprinkler Sign Off | 7/2/2020 | Not Ready for Inspection | BEAU COLLINS |
| PLUMBING-Rough | 8/19/2020 | Partial Approval | BEAU COLLINS |
| PLUMBING-Rough | 8/20/2020 | Approved | BEAU COLLINS |
| ELECTRICAL-Rough | 9/16/2020 | Approved | BEAU COLLINS |
| Drywall Nailing | 9/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/24/2020 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/24/2020 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/14/2020 | Approved | BEAU COLLINS |
| Green Building Rough | 10/14/2020 | Approved | BEAU COLLINS |
| Insulation | 10/14/2020 | Approved | BEAU COLLINS |
| Verify Sprinkler Sign Off | 10/14/2020 | Approved | BEAU COLLINS |
| Green Building Final | 10/15/2020 | Not Ready for Inspection | BEAU COLLINS |
| Insulation | 10/15/2020 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 10/15/2020 | Not Ready for Inspection | BEAU COLLINS |
| Drywall Nailing | 10/21/2020 | Approved | BEAU COLLINS |
| ELECTRICAL-Final | 12/21/2020 | Not Ready for Inspection | BEAU COLLINS |
| HVAC-Final | 12/21/2020 | Not Ready for Inspection | BEAU COLLINS |
| PLUMBING-Final | 12/21/2020 | Corrections Issued | BEAU COLLINS |
| Final | 4/13/2021 | OK to Issue CofO | BEAU COLLINS |
| Green Building Final | 4/13/2021 | Approved | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | BEAU COLLINS |
| Service/Power Release | 4/13/2021 | Not Required | BEAU COLLINS |
| Smoke Detectors | 4/13/2021 | Approved | BEAU COLLINS |