1484 N AVENUE 57 90042
Certificate Information: 1484 N AVENUE 57 90042
- Application / Permit
- 19010-10000-03120
- Plan Check / Job No.
- B19LA15069
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING INCLUDING MEZZANINE AND ATTACHED GARAGE PER ZA-2018-3194-ZAA-ZAD.
- Permit Issued
- Issued on 1/31/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | KEVIN MORALES |
| Corrections Issued | 8/7/2019 | KEVIN MORALES |
| Quality Review Completed | 8/25/2019 | YOUNG KIM |
| Building Plans Picked Up | 8/27/2019 | APPLICANT |
| Green Plans Picked Up | 8/27/2019 | APPLICANT |
| Plan Check Approved | 1/27/2020 | KEVIN MORALES |
| Issued | 1/31/2020 | LADBS |
| CofO in Progress | 5/31/2022 | CRAIG VAUGHAN |
| CofO in Progress | 5/31/2022 | CRAIG VAUGHAN |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
| CofO Issued | 6/23/2022 | DEROLD HAUFF |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/25/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2019 | ERIK BEASLEY |
| Permit | Cleared | 10/25/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/25/2019 | ERIK BEASLEY |
| Green Code | Cleared | 12/20/2019 | COLIN LOREDO |
| Work Adjacent to Public Way | Cleared | 1/3/2020 | ROSA SILVA |
| BHO/Hillside ordinance | Cleared | 1/6/2020 | ARMEN MEHRABIAN |
| BHO/Hillside ordinance | Cleared | 1/6/2020 | ARMEN MEHRABIAN |
| Hydrant and Access approval | Cleared | 1/7/2020 | ROBERT DUFF |
| Low Impact Development | Cleared | 1/7/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/10/2020 | NGOC KIEM |
| ZA Case | Cleared | 1/13/2020 | TRACY WILLIAMS |
| GPI Written Notices | Cleared | 1/27/2020 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 1/27/2020 | KEVIN MORALES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 3/3/2020 | Approved | TODD MALAND |
| Deputy Grading | 3/4/2020 | No Access for Inspection | CRAIG VAUGHAN |
| Deputy Grading | 3/5/2020 | No Access for Inspection | CRAIG VAUGHAN |
| Deputy Grading | 3/6/2020 | No Access for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/1/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/1/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 4/1/2020 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/21/2020 | Partial Approval | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 5/21/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/19/2020 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2020 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 12/8/2020 | Partial Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/31/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2020 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 1/12/2021 | Partial Inspection | ROBERT VORHIS |
| Deputy Wood Construction | 1/15/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 1/28/2021 | Partial Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/23/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 2/23/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 2/23/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/23/2021 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 2/23/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Wood Construction | 3/2/2021 | No Access for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/2/2021 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 3/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/2/2021 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 3/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| Wood Frame | 3/8/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/12/2021 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 3/12/2021 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/16/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 3/18/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/18/2021 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 3/18/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 3/23/2021 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 3/26/2021 | Approved | CRAIG VAUGHAN |
| Special/Order Compliance | 6/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 8/19/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 9/22/2021 | Approved | ALAN MORELOS |
| Special/Order Compliance | 10/21/2021 | Approved | HECTOR ALIKHAN |
| ELECTRICAL-Final | 10/29/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 11/2/2021 | Not Ready for Inspection | COREY HUPP |
| Special/Order Compliance | 11/22/2021 | Partial Inspection | AMY COLIN |
| Special/Order Compliance | 11/30/2021 | Approved | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 12/6/2021 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 1/28/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | CRAIG VAUGHAN |
| Final | 2/22/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/22/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 2/22/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 2/22/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/22/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 2/22/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 2/22/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 2/22/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/18/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 3/18/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 3/24/2022 | Conditional Approval | CRAIG VAUGHAN |
| Final | 4/14/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 4/14/2022 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 4/14/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/15/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/15/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 4/15/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/15/2022 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 4/15/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/18/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 4/18/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/18/2022 | Approved | CRAIG VAUGHAN |