Pre-Inspection
|
6/2/2020
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
9/15/2020
|
Partial Approval
|
NICK DANERI
|
|
Piling/Pier/Caisson
|
9/15/2020
|
Approved
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
9/28/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
10/6/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
10/8/2020
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
10/8/2020
|
Partial Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
10/13/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Other (see comments)
|
10/14/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
10/22/2020
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
10/22/2020
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
10/23/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
10/28/2020
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
11/4/2020
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
11/5/2020
|
Partial Approval
|
NICK DANERI
|
|
Deputy Drilled-In Anchors
|
11/10/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
11/10/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
11/13/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/16/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/17/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/18/2020
|
Conditional Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
11/18/2020
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/19/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/20/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
11/23/2020
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
11/23/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
11/23/2020
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/23/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/24/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/25/2020
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
11/25/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
11/25/2020
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/25/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/30/2020
|
Conditional Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
12/3/2020
|
Conditional Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
12/30/2020
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
1/12/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
1/12/2021
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
1/12/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
1/28/2021
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
1/29/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
2/1/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
2/25/2021
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
3/4/2021
|
Partial Approval
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
3/4/2021
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
3/4/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/5/2021
|
Conditional Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
3/5/2021
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/9/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/10/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/11/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/12/2021
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
3/12/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
3/12/2021
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
3/12/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/15/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
3/15/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
3/15/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
3/16/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
3/16/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
3/16/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
3/17/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/17/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
3/17/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/18/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/18/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
3/18/2021
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
3/18/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
3/18/2021
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
3/18/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/19/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/19/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
3/19/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/14/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
4/15/2021
|
Conditional Approval
|
DANIEL COLLINS
|
|
Green Building Rough
|
4/15/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
4/15/2021
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
4/15/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Pre-Stress Concrete
|
4/16/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Pre-Stress Concrete
|
4/19/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/19/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/20/2021
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2021
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/14/2021
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
6/8/2021
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
6/10/2021
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
6/11/2021
|
Approved
|
DANIEL COLLINS
|
|
Reinforced Masonry Frame
|
6/11/2021
|
Partial Approval
|
DANIEL COLLINS
|
|
Verify Sprinkler Sign Off
|
6/11/2021
|
Not Ready for Inspection
|
DANIEL COLLINS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/18/2021
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
6/21/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/8/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
7/8/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/19/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/27/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/3/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/13/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/20/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/23/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/24/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/25/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/26/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/27/2021
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
8/27/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/30/2021
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
8/30/2021
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
9/15/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
9/24/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/29/2021
|
Not Ready for Inspection
|
DANIEL COLLINS
|
|
Drywall Nailing
|
10/4/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/4/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Wood Frame
|
10/13/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
10/19/2021
|
Partial Approval
|
DANIEL COLLINS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/19/2021
|
Partial Approval
|
DANIEL COLLINS
|
|
Wood Frame
|
10/21/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Wood Frame
|
10/22/2021
|
Partial Approval
|
DANIEL COLLINS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/25/2021
|
Not Ready for Inspection
|
MARK FERRARI
|
|
Light Gage Steel Frame
|
10/25/2021
|
Partial Approval
|
MARK FERRARI
|
|
Light Gage Steel Frame
|
10/28/2021
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
10/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
10/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/2/2021
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
11/4/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/5/2021
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/5/2021
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
11/5/2021
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
11/9/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
11/10/2021
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/12/2021
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
11/16/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/16/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
11/17/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
11/18/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
11/24/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
11/24/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/30/2021
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
12/3/2021
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
12/8/2021
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
12/15/2021
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
12/16/2021
|
Partial Approval
|
NICK DANERI
|
|
T-Bar Ceiling
|
12/20/2021
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
12/22/2021
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
12/23/2021
|
Partial Approval
|
NICK DANERI
|
|
T-Bar Ceiling
|
12/29/2021
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
1/5/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
1/10/2022
|
Conditional Approval
|
NICK DANERI
|
|
T-Bar Ceiling
|
1/11/2022
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
1/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
1/19/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
1/20/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
1/24/2022
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
1/26/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
2/1/2022
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
2/11/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
2/18/2022
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
2/23/2022
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
2/24/2022
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
3/7/2022
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
3/15/2022
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
3/25/2022
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
3/30/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
4/12/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
4/28/2022
|
SGSOV Not Ready
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
5/3/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
7/26/2022
|
Approved
|
NICK DANERI
|
|
Final
|
7/26/2022
|
Partial Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
7/26/2022
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
7/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
7/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
7/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
7/26/2022
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
7/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
7/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Pre-Inspection
|
7/27/2022
|
Partial Inspection
|
NICK DANERI
|
|
Pre-Inspection
|
7/29/2022
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
8/18/2022
|
Partial Inspection
|
NICK DANERI
|
|
Final
|
9/16/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Final
|
9/16/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
9/16/2022
|
Approved
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
9/16/2022
|
Approved
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
9/16/2022
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
9/16/2022
|
Approved
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
9/16/2022
|
Approved
|
NICK DANERI
|
|
Special/Order Compliance
|
9/22/2022
|
Partial Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
2/13/2023
|
SGSOV Not Ready
|
NICK DANERI
|
|
Special/Order Compliance
|
3/9/2023
|
Conditional Approval
|
NICK DANERI
|
|
Final
|
5/2/2023
|
OK to Issue CofO
|
NICK DANERI
|
|
Green Building Final
|
5/2/2023
|
Approved
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
5/2/2023
|
SGSOV Approved
|
NICK DANERI
|