19550 W CELTIC ST 91326
Certificate Information: 19550 W CELTIC ST 91326
- Application / Permit
- 19010-10000-03026
- Plan Check / Job No.
- B19LA14509
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- BUILD NEW 2-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 1/31/2020
- Issuing Office
- Valley
- Current Status
- Issued on 1/31/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 8/12/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/20/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 8/22/2019 | APPLICANT |
| Green Plans Picked Up | 8/27/2019 | APPLICANT |
| Plan Check Approved | 1/30/2020 | SERGIO GUTIERREZ |
| Issued | 1/31/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 11/8/2019 | ELENA LOPEZ |
| Hydrant and Access approval | Cleared | 12/3/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2019 | PAMELA TENEZA |
| Sewer availability | Cleared | 12/9/2019 | PAMELA TENEZA |
| Green Code | Cleared | 1/7/2020 | SERGIO GUTIERREZ |
| Low Impact Development | Cleared | 1/7/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/16/2020 | ELAINE LEI |
| Stormwater Pollution Mitigatn | Cleared | 1/16/2020 | ORVAL HERNANDEZ-MARCIAL |
| GPI Written Notices | Cleared | 1/30/2020 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 1/30/2020 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2020 | Partial Approval | DONALD SUNSERI |
| Footing/Foundation/Slab | 3/9/2020 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/18/2020 | Approved | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Partial Approval | DONALD SUNSERI |
| ELECTRICAL-Rough | 5/15/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2020 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 5/15/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/15/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/11/2020 | Corrections Issued | DONALD SUNSERI |
| Underground Mechanical | 6/11/2020 | Partial Approval | DONALD SUNSERI |
| Interior/Exterior Lathing | 6/29/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 6/29/2020 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 7/2/2020 | Approved | JEFFREY PARD |
| Green Building Rough | 7/2/2020 | Approved | JEFFREY PARD |
| MERV13>=Rough | 7/2/2020 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 7/2/2020 | Approved | JEFFREY PARD |
| Insulation | 7/8/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 7/13/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 11/4/2020 | Corrections Issued | JEFFREY PARD |
| HVAC-Final | 11/4/2020 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Final | 11/4/2020 | Corrections Issued | JEFFREY PARD |
| Final | 12/2/2020 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 12/2/2020 | Approved | JEFFREY PARD |
| MERV13>=Final | 12/2/2020 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 12/2/2020 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 12/2/2020 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 12/2/2020 | Approved | JEFFREY PARD |