19550 W CELTIC ST 91326

Certificate Information: 19550 W CELTIC ST 91326

Application / Permit
19010-10000-03026
Plan Check / Job No.
B19LA14509
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
BUILD NEW 2-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 1/31/2020
Issuing Office
Valley
Current Status
Issued on 1/31/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 SERGIO GUTIERREZ
Corrections Issued 8/12/2019 SERGIO GUTIERREZ
Quality Review Completed 8/20/2019 KESETE HAREGOT
Building Plans Picked Up 8/22/2019 APPLICANT
Green Plans Picked Up 8/27/2019 APPLICANT
Plan Check Approved 1/30/2020 SERGIO GUTIERREZ
Issued 1/31/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 11/8/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 12/3/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 12/9/2019 PAMELA TENEZA
Sewer availability Cleared 12/9/2019 PAMELA TENEZA
Green Code Cleared 1/7/2020 SERGIO GUTIERREZ
Low Impact Development Cleared 1/7/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/16/2020 ELAINE LEI
Stormwater Pollution Mitigatn Cleared 1/16/2020 ORVAL HERNANDEZ-MARCIAL
GPI Written Notices Cleared 1/30/2020 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 1/30/2020 SERGIO GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/4/2020 Partial Approval DONALD SUNSERI
Footing/Foundation/Slab 3/9/2020 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 3/18/2020 Approved MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval DONALD SUNSERI
ELECTRICAL-Rough 5/15/2020 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Corrections Issued HENRY KIM
HVAC-Rough 5/15/2020 Approved HENRY KIM
PLUMBING-Rough 5/15/2020 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 6/11/2020 Corrections Issued DONALD SUNSERI
Underground Mechanical 6/11/2020 Partial Approval DONALD SUNSERI
Interior/Exterior Lathing 6/29/2020 Approved JEFFREY PARD
PLUMBING-Rough 6/29/2020 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 7/2/2020 Approved JEFFREY PARD
Green Building Rough 7/2/2020 Approved JEFFREY PARD
MERV13>=Rough 7/2/2020 Approved JEFFREY PARD
Verify Sprinkler Sign Off 7/2/2020 Approved JEFFREY PARD
Insulation 7/8/2020 Approved DAVID STEPANYAN
Drywall Nailing 7/13/2020 Approved HENRY KIM
ELECTRICAL-Final 11/4/2020 Corrections Issued JEFFREY PARD
HVAC-Final 11/4/2020 Corrections Issued JEFFREY PARD
PLUMBING-Final 11/4/2020 Corrections Issued JEFFREY PARD
Final 12/2/2020 Not Ready for Inspection JEFFREY PARD
Green Building Final 12/2/2020 Approved JEFFREY PARD
MERV13>=Final 12/2/2020 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 12/2/2020 SGSOV Approved JEFFREY PARD
Service/Power Release 12/2/2020 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 12/2/2020 Approved JEFFREY PARD