21138 S WESTERN AVE A-C 90501
Certificate Information: 21138 S WESTERN AVE A-C 90501
- Application / Permit
- 19010-10000-02946
- Plan Check / Job No.
- B19LA14186
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail Store or Business
- Work Description
- NEW 2 STORY GAS STATION/CONVENIENT STORE AND CORE AND SHELL RETAIL STORE.
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 7/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | HERNAN ARREOLA |
| Corrections Issued | 7/28/2019 | HERNAN ARREOLA |
| Quality Review Completed | 8/5/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 8/6/2019 | APPLICANT |
| Green Plans Picked Up | 5/19/2020 | APPLICANT |
| Applicant returned to address corrections | 9/23/2020 | HERNAN ARREOLA |
| Plan Check Approved | 11/5/2020 | HERNAN ARREOLA |
| Issued | 12/7/2021 | APPLICANT |
| TCO Issued (Expire Date: 11-12-2025) | 5/16/2025 | JOEY BUCHANAN |
| CofO in Progress | 10/15/2025 | RICARDO ROBLES |
| Permit Finaled | 10/16/2025 | DAVID TSAU |
| CofO Issued | 10/16/2025 | DAVID TSAU |
| Permit Finaled | 10/16/2025 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 10/23/2019 | VIVIAN LAO |
| Sewer availability | Cleared | 1/23/2020 | ANTHONY MAINEZ |
| "Q" conditions | Cleared | 2/3/2020 | JOE LUCKEY |
| Comm Cor/Mini-Mall | Cleared | 2/3/2020 | JOE LUCKEY |
| Prkng lot landscape/Water mgmt | Cleared | 2/3/2020 | JOE LUCKEY |
| Trees in Parkway | Cleared | 2/3/2020 | STEPHEN DUPREY |
| Hydrant and Access approval | Cleared | 3/13/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 3/13/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/1/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2020 | CHINH DINH |
| Highway dedication | Cleared | 4/23/2020 | CHINH DINH |
| Driveway location | Cleared | 5/7/2020 | PEDRO AYALA |
| DAS Clearance | Cleared | 6/11/2020 | CHOI YAN |
| Comm Cor/Mini-Mall | Cleared | 7/27/2020 | JOE LUCKEY |
| Food Service Establishment | Cleared | 8/28/2020 | RAMESHBHAIR PATEL |
Contact Information
| Architect | Coffman,, Jeffrey Scott; Lic. No.: C25115 | 2000 E CHAPMAN AVE SUITE 202 FULLERTON, CA 92831 |
| Contractor | Menemsha Development Group Inc; Lic. No.: 647870-B | 20521 EARL ST TORRANCE, CA 90503 |
| Engineer | Yaghi,, Shucri Ibrahim; Lic. No.: C43205 | 112 E CHAPMAN AVE STE D ORANGE, CA 92866 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2022 | Corrections Issued | JOEY BUCHANAN |
| Pre-Inspection | 3/7/2022 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 5/17/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 6/23/2022 | Approved | JOEY BUCHANAN |
| Grading Pre-Inspection | 12/20/2022 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 11/13/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 12/18/2023 | Approved | AMANUEL BERHE |
| Footing/Foundation/Slab | 1/30/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 3/11/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 3/28/2024 | Not Ready for Inspection | DAVID TSAU |
| Excavation/Setback/Form/Re-Bar | 4/2/2024 | Partial Approval | RICARDO ROBLES |
| Excavation/Setback/Form/Re-Bar | 4/29/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/29/2024 | Corrections Issued | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 5/6/2024 | Conditional Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 5/6/2024 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 5/20/2024 | Partial Approval | JOEY BUCHANAN |
| Pre-Inspection | 5/20/2024 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Partial Approval | JOEY BUCHANAN |
| Green Building Rough | 6/13/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 6/13/2024 | Approved | JOEY BUCHANAN |
| Green Building Final | 6/17/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Light Gage Steel Frame | 6/17/2024 | Partial Approval | JOEY BUCHANAN |
| Insulation | 6/21/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Drywall Nailing | 6/25/2024 | Partial Approval | RICARDO ROBLES |
| Green Building Rough | 6/25/2024 | Approved | RICARDO ROBLES |
| Insulation | 6/25/2024 | Partial Approval | RICARDO ROBLES |
| Wood Frame | 6/25/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 6/28/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 7/3/2024 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 7/3/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 7/10/2024 | Partial Approval | JOEY BUCHANAN |
| Interior/Exterior Lathing | 7/26/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 7/31/2024 | Partial Inspection | AMANUEL BERHE |
| Excavation/Setback/Form/Re-Bar | 8/14/2024 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 10/3/2024 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 11/6/2024 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 11/12/2024 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/13/2024 | Conditional Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/15/2024 | Conditional Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/21/2024 | Conditional Approval | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 11/22/2024 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 11/25/2024 | Conditional Approval | JOEY BUCHANAN |
| Masonry Wall/Backfill | 11/25/2024 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 12/2/2024 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 12/6/2024 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 12/11/2024 | Partial Approval | JOEY BUCHANAN |
| Pre-Inspection | 1/24/2025 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/25/2025 | Approved | JOEY BUCHANAN |
| Green Building Final | 4/25/2025 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 4/25/2025 | Approved | JOEY BUCHANAN |
| Wood Frame | 4/25/2025 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 4/29/2025 | Corrections Issued | JOEY BUCHANAN |
| Final | 4/30/2025 | OK for TCO | JOEY BUCHANAN |
| Final | 5/1/2025 | Corrections Issued | JOEY BUCHANAN |
| Final | 5/5/2025 | No Access for Inspection | RICARDO ROBLES |
| Special/Order Compliance | 5/13/2025 | Corrections Issued | JOEY BUCHANAN |
| Pre-Inspection | 7/9/2025 | Partial Approval | RICARDO ROBLES |
| Special/Order Compliance | 10/15/2025 | Approved | RICARDO ROBLES |