936 S MARIPOSA AVE 90006

Certificate Information: 936 S MARIPOSA AVE 90006

Application / Permit
19010-10000-02908
Plan Check / Job No.
B19LA13903
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 23 UNIT with 3 extrmely low income units, 6-STORY APARTMENT BUILDING. 4 STORIES OF TYPE VA OVER 2 STORY OF TYPE IA PARKING. TOC TIER 3.
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
Issued on 8/29/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2019 APPLICANT
Green Plans Picked Up 8/14/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 QUAN NGHIEM
Corrections Issued 10/18/2019 QUAN NGHIEM
Quality Review Completed 10/24/2019 SIAVOSH POURSABAHIAN
Building Plans Picked Up 11/14/2019 APPLICANT
Disabled Access Plans Picked Up 11/14/2019 APPLICANT
Applicant returned to address corrections 7/30/2020 QUAN NGHIEM
Applicant returned to address corrections 3/4/2022 QUAN NGHIEM
Plan Check Approved 6/23/2022 QUAN NGHIEM
Issued 8/29/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/13/2020 ELAINE LEI
Hydrant and Access approval Cleared 10/13/2020 GILBERT URREA
Building over 3-story or 36-ft Cleared 12/18/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/18/2020 CALOSHA APPROVED
Trees in Parkway Cleared 12/22/2020 JOHN KIM
Address approval Cleared 8/17/2021 THOMAS LANG
Highway dedication Cleared 10/8/2021 THAN WIN
Sewer availability Cleared 10/15/2021 CELINA MORENO
Density Bonus 12.22.A.31 Cleared 11/4/2021 DORIS KWOK
Permit Cleared 11/8/2021 THAN WIN
Fire Marshall Fire Life Safety Cleared 11/23/2021 OSCAR SALGADO JR
Green Code Cleared 12/3/2021 KHEDER ALRAZAA
DAS Clearance Cleared 12/9/2021 WAI LAU
Low Impact Development Cleared 12/9/2021 IDA MEISAMI-FARD
Frnt yard landscape/Water mgmt Cleared 12/20/2021 LAUREN PADICK
Opn space landscape/Water mgmt Cleared 12/20/2021 LAUREN PADICK
Project located in CRA area Cleared 12/21/2021 DAVID URITA
Roof/Waste drainage to street Cleared 12/21/2021 CELINA MORENO
Work Adjacent to Public Way Cleared 2/17/2022 JOSE RODRIGUEZ

Contact Information

Contractor K N D D Inc; Lic. No.: 794816-B 132 S LA PEER DR      BEVERLY HILLS, CA 90211

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2022 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 3/7/2023 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/24/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/31/2023 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 4/3/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/3/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/12/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/12/2023 Partial Approval LARRY ARNICK
Deputy Shotcrete 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/16/2023 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/22/2023 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/26/2023 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 6/28/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 6/28/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 6/28/2023 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 6/28/2023 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/12/2023 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/8/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/11/2023 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/16/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/25/2023 Partial Approval ADAM BURGESS
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 9/8/2023 Conditional Approval GREGORY POMISH
Green Building Rough 9/8/2023 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 9/8/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 9/8/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 9/18/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Not Ready for Inspection GREGORY POMISH
Green Building Rough 9/19/2023 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 9/19/2023 Partial Inspection GREGORY POMISH
Wood Frame 9/19/2023 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 9/21/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/21/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Partial Approval GREGORY POMISH
Green Building Rough 10/17/2023 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/17/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 10/17/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 10/26/2023 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval NICK DANERI
Deputy Wood Construction 11/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Partial Approval NICK DANERI
Deputy Wood Construction 12/4/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Partial Approval NICK DANERI
Drywall Nailing 1/9/2024 Partial Approval GREGORY POMISH
Green Building Rough 1/9/2024 Partial Inspection GREGORY POMISH
Interior/Exterior Lathing 1/9/2024 Partial Inspection GREGORY POMISH
Drywall Nailing 3/1/2024 Partial Approval NICK DANERI
Deputy Wood Construction 3/26/2024 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 4/8/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 4/8/2024 Not Ready for Inspection NICK DANERI
Wood Frame 4/8/2024 Partial Approval NICK DANERI
Insulation 4/23/2024 Partial Approval NICK DANERI
Insulation 4/30/2024 Partial Approval NICK DANERI
Insulation 5/21/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 7/1/2024 Partial Approval NICK DANERI
Drywall Nailing 7/18/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 7/18/2024 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 8/21/2024 Partial Inspection JEROME BLACKWOOD
Green Building Rough 8/27/2024 Not Ready for Inspection JEROME BLACKWOOD
Interior/Exterior Lathing 8/27/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 8/30/2024 Partial Approval JEROME BLACKWOOD
Green Building Rough 8/30/2024 Partial Inspection JEROME BLACKWOOD
Interior/Exterior Lathing 9/11/2024 Partial Approval NICK DANERI
Insulation 10/8/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/10/2024 Partial Approval NICK DANERI
Drywall Nailing 10/21/2024 Not Ready for Inspection LARRY ARNICK
Green Building Rough 10/21/2024 Not Ready for Inspection LARRY ARNICK
Insulation 10/23/2024 Partial Approval LARRY ARNICK
Drywall Nailing 10/28/2024 Partial Approval NICK DANERI
Green Building Rough 10/28/2024 Partial Inspection NICK DANERI
Drywall Nailing 11/15/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 11/15/2024 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 11/15/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/2/2024 Partial Approval LARRY ARNICK
Green Building Rough 12/2/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 6/12/2025 Conditional Approval JOEY BUCHANAN
Masonry Wall/Backfill 6/16/2025 No Access for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 6/18/2025 Approved JOEY BUCHANAN
Interior/Exterior Lathing 10/27/2025 Approved JOEY BUCHANAN
Deputy Steel/Welding 1/26/2026 Approved JOEY BUCHANAN
Drywall Nailing 1/26/2026 Approved JOEY BUCHANAN
Final 1/26/2026 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 1/26/2026 Approved JOEY BUCHANAN
Green Building Final 1/26/2026 Approved JOEY BUCHANAN
Green Building Rough 1/26/2026 Approved JOEY BUCHANAN
Reinforced Concrete Frame 1/26/2026 Approved JOEY BUCHANAN
Reinforced Masonry Frame 1/26/2026 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 1/26/2026 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 1/26/2026 Approved JOEY BUCHANAN
Wood Frame 1/26/2026 Approved JOEY BUCHANAN