5660 E ASH ST 90042

Certificate Information: 5660 E ASH ST 90042

Application / Permit
19010-10000-02887
Plan Check / Job No.
B19LA13876
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
New detached, irregular-shaped patio cover (52' x 29'-11", 1488 SF) with foundation for rain tank. All work per engineered design. "COMPLY WITH DEPARTMENT ORDER effective date 03/23/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/6/2020
Issuing Office
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 FARSHAD ALIMOHAMADI
Corrections Issued 7/11/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 10/1/2020 CHRISTOPHER KOMANCHECK
Issued 10/6/2020 APPLICANT
Building Plans Picked Up 10/14/2020 APPLICANT
CofO in Progress 4/13/2022 SCOTT FINNILA
Permit Finaled 8/11/2022 DEROLD HAUFF
CofO Issued 8/11/2022 DEROLD HAUFF
Permit Finaled 8/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/11/2019 JEANETTE VONG
HPOZ Cleared 12/6/2019 MELISSA JONES
Low Impact Development Cleared 8/26/2020 SARAH YOUSSEF
GPI Written Notices Cleared 9/11/2020 FARSHAD ALIMOHAMADI
Grading Pre-Inspection Cleared 9/11/2020 FARSHAD ALIMOHAMADI
Roof/Waste drainage to street Cleared 9/23/2020 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,
Engineer Gilsanz,, Ramon Emilio; Lic. No.: S4161 2 FIFTH AVE APT 7F      NEW YORK, NY 10011

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/20/2020 Corrections Issued CRAIG VAUGHAN
Deputy Steel/Welding 11/30/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 12/9/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 12/9/2020 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 12/11/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 12/11/2020 Partial Approval CRAIG VAUGHAN
Reinforced Concrete Frame 2/23/2021 Partial Approval COREY HUPP
Deputy Steel/Welding 4/5/2021 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/9/2021 Approved COREY HUPP
BUILDING-Rough-Frame 4/7/2022 Approved CRAIG VAUGHAN
Final 4/7/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 4/7/2022 Approved CRAIG VAUGHAN
Smoke Detectors 4/7/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/7/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/12/2022 Approved SCOTT FINNILA
Final 4/12/2022 OK to Issue CofO SCOTT FINNILA
HVAC-Final 4/12/2022 Approved SCOTT FINNILA
PLUMBING-Final 4/12/2022 Approved SCOTT FINNILA
Smoke Detectors 4/12/2022 Approved SCOTT FINNILA