11401 N PORTER VALLEY DR 91326
Certificate Information: 11401 N PORTER VALLEY DR 91326
- Application / Permit
- 19010-10000-02833
- Plan Check / Job No.
- B19LA13632
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (7) Garage - Private
- Work Description
- (N) DETACHED (MAINTENANCE) GARAGE & STORAGE FOR MULTI-FAMILY DWELLINGS.
- Permit Issued
- Issued on 8/28/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 7/11/2019 | APPLICANT |
| Green Plans Picked Up | 7/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | ERWIN PASCUA |
| Corrections Issued | 7/22/2019 | ERWIN PASCUA |
| Quality Review Completed | 7/24/2019 | CHARLES CHANG |
| Building Plans Picked Up | 7/29/2019 | APPLICANT |
| Plan Check Approved | 8/27/2019 | ERWIN PASCUA |
| Issued | 8/28/2019 | LADBS |
| CofO in Progress | 10/6/2021 | DANNY RODRIGUEZ |
| CofO Issued | 10/12/2021 | RICKEY JACKSON |
| Permit Finaled | 10/12/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2019 | ADRIAN SANCHEZ |
| Permit | Cleared | 8/8/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/8/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/8/2019 | ADRIAN SANCHEZ |
| Specific Plan | Cleared | 8/8/2019 | COLLINS ALLAN |
| "T" removal | Cleared | 8/14/2019 | NOAH MCCOY |
| CPC | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/14/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 8/14/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 8/14/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 8/14/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 8/14/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 8/14/2019 | NOAH MCCOY |
| ZA Case | Cleared | 8/14/2019 | NOAH MCCOY |
| ZA Case | Cleared | 8/14/2019 | NOAH MCCOY |
| ZA Case | Cleared | 8/14/2019 | NOAH MCCOY |
| DAS Clearance | Cleared | 8/15/2019 | EDDIE GARIN |
| Green Code | Cleared | 8/19/2019 | VIVIAN LAO |
| GPI Written Notices | Cleared | 8/27/2019 | ERWIN PASCUA |
| Grading Pre-Inspection | Cleared | 8/27/2019 | ERWIN PASCUA |
Contact Information
| Architect | Alley,, Rembert Caven; Lic. No.: C22598 | 144 N ORANGE STREET ORANGE, CA 92692 |
| Contractor | R C I Builders Inc; Lic. No.: 835114-B | 2985 E HILLCREST DR #107 THOUSAND OAKS, CA 91362 |
| Engineer | Patel,, Sharad T; Lic. No.: S4488 | 104 LATTICE IRVINE, CA 92603 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/10/2020 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 2/13/2020 | Not Ready for Inspection | ROBERT COLE |
| Interior/Exterior Lathing | 10/1/2020 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 10/6/2020 | Partial Approval | DANNY RODRIGUEZ |
| Wood Frame | 10/6/2020 | Corrections Issued | DANNY RODRIGUEZ |
| Green Building Rough | 12/9/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 12/9/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 1/11/2021 | Partial Approval | HAMID PISHEHVAR |
| Green Building Rough | 1/11/2021 | Approved | HAMID PISHEHVAR |
| Drywall Nailing | 3/25/2021 | Approved | DANNY RODRIGUEZ |
| Final | 3/25/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/25/2021 | Approved | DANNY RODRIGUEZ |
| Green Building Final | 3/25/2021 | Approved | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/25/2021 | SGSOV Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 3/25/2021 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 3/25/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 3/30/2021 | OK to Issue CofO | DANNY RODRIGUEZ |
| Wood Frame | 3/30/2021 | Approved | DANNY RODRIGUEZ |