616-618 E 80TH ST 90001
Certificate Information: 616-618 E 80TH ST 90001
- Application / Permit
- 19010-10000-02831
- Plan Check / Job No.
- B19LA13615
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE. TYPE VB. SPRINKLERED.
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | VARAND SARKISIAN |
| Green Plans Picked Up | 7/19/2019 | APPLICANT |
| Corrections Issued | 7/22/2019 | VARAND SARKISIAN |
| Quality Review Completed | 7/31/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 8/1/2019 | APPLICANT |
| Plan Check Approved | 9/11/2019 | VARAND SARKISIAN |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 7/25/2020 | JOSEPH MCGARRY |
| Permit Finaled | 8/15/2020 | DEROLD HAUFF |
| Permit Finaled | 8/15/2020 | DEROLD HAUFF |
| CofO Issued | 8/15/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 8/8/2019 | VIVIAN LAO |
| Address approval | Cleared | 8/9/2019 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 8/9/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 8/9/2019 | JOHN CONNEALLY |
| Permit | Cleared | 8/9/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 8/9/2019 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 8/16/2019 | KIT AWAKUNI |
| Community Plan Implem. Overlay | Cleared | 8/16/2019 | KIT AWAKUNI |
| Low Impact Development | Cleared | 8/16/2019 | JORGE MEJIA LEMUS |
| Trees in Parkway | Cleared | 8/31/2019 | ADRIAN SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 9/3/2019 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 9/3/2019 | JEANIE LAM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/24/2020 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 1/30/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 2/3/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/3/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/3/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/3/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/3/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/3/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/3/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/6/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/6/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/9/2020 | Partial Inspection | ROBERT VORHIS |
| Green Building Rough | 4/9/2020 | Not Ready for Inspection | ROBERT VORHIS |
| HVAC-Rough | 4/9/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 4/9/2020 | Approved | ROBERT VORHIS |
| Pre-Inspection | 4/9/2020 | Partial Inspection | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 4/9/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 4/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 4/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 4/13/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/16/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/16/2020 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 4/16/2020 | Approved | EUGENE CASSIDY |
| Insulation | 4/20/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 5/1/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 5/1/2020 | Approved | BRIAN CHRISTIAN |
| Sewer | 5/1/2020 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/8/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/24/2020 | OK to Issue CofO | JOSEPH MCGARRY |