137-139 W 70TH ST 90003
Certificate Information: 137-139 W 70TH ST 90003
- Application / Permit
- 19010-10000-02830
- Plan Check / Job No.
- B19LA13613
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 10/24/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/20/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | DANIEL SANJUAN |
| Green Plans Picked Up | 7/19/2019 | APPLICANT |
| Corrections Issued | 7/22/2019 | DANIEL SANJUAN |
| Quality Review Completed | 8/1/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 8/1/2019 | APPLICANT |
| Plan Check Approved | 9/11/2019 | DANIEL SANJUAN |
| Issued | 10/24/2019 | LADBS |
| CofO in Progress | 3/25/2020 | EUGENE CASSIDY |
| Permit Finaled | 5/20/2020 | BOB DUNN |
| CofO Issued | 5/20/2020 | BOB DUNN |
| Permit Finaled | 5/20/2020 | BOB DUNN |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2019 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 8/9/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 8/9/2019 | JOHN CONNEALLY |
| Sewer availability | Cleared | 8/9/2019 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 9/3/2019 | JOE LUCKEY |
| Low Impact Development | Cleared | 9/4/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/4/2019 | JEANETTE VONG |
| Green Code | Cleared | 9/10/2019 | KHEDER ALRAZAA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/16/2019 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 11/16/2019 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 11/19/2019 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2019 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2019 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/26/2019 | Conditional Approval | WILLIAM ROSE |
| ELECTRICAL-Rough | 12/26/2019 | Corrections Issued | WILLIAM ROSE |
| Green Building Rough | 12/26/2019 | Not Ready for Inspection | WILLIAM ROSE |
| HVAC-Rough | 12/26/2019 | Corrections Issued | WILLIAM ROSE |
| PLUMBING-Rough | 12/26/2019 | Approved | WILLIAM ROSE |
| Sewer | 12/26/2019 | Approved | WILLIAM ROSE |
| Verify Sprinkler Sign Off | 12/26/2019 | Approved | WILLIAM ROSE |
| BUILDING-Rough-Frame | 12/30/2019 | Conditional Approval | WILLIAM ROSE |
| ELECTRICAL-Rough | 12/30/2019 | Corrections Issued | WILLIAM ROSE |
| Green Building Rough | 12/30/2019 | Approved | WILLIAM ROSE |
| HVAC-Rough | 12/30/2019 | Approved | WILLIAM ROSE |
| Wood Frame | 12/30/2019 | Approved | WILLIAM ROSE |
| ELECTRICAL-Rough | 1/16/2020 | Approved | EUGENE CASSIDY |
| Insulation | 1/21/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 1/28/2020 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/28/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/29/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/29/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/20/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/20/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 3/20/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/20/2020 | Approved | EUGENE CASSIDY |
| Gas Test | 3/20/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 3/20/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 3/20/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/20/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 3/20/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 3/20/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/24/2020 | Approved | EUGENE CASSIDY |
| Final | 3/24/2020 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 3/24/2020 | Approved | EUGENE CASSIDY |