6501 S CRENSHAW BLVD 90043

Certificate Information: 6501 S CRENSHAW BLVD 90043

Application / Permit
19010-10000-02774
Plan Check / Job No.
B19LA13364
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 5-STORY APARTMENT BUILDING WITH 98 MODULAR UNITS (97 LOW INCOME UNITS AND 1 MANAGERS UNIT) . APARTMENT/RETAIL/SUPPORTIVE OFFICE . 100% AFFORDABLE SUPPORTIVE HOUSING
Permit Issued
Issued on 1/29/2021
Issuing Office
Metro
Current Status
CofO Issued on 10/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 JOE VO
Corrections Issued 7/23/2019 JOE VO
Quality Review Completed 7/24/2019 GARO TELMI
Disabled Access Plans Picked Up 7/24/2019 APPLICANT
Building Plans Picked Up 7/25/2019 APPLICANT
Applicant returned to address corrections 7/20/2020 JOE VO
Applicant returned to address corrections 7/31/2020 JOE VO
Applicant returned to address corrections 9/30/2020 JOE VO
Green Plans Picked Up 11/18/2020 APPLICANT
Applicant returned to address corrections 12/10/2020 JOE VO
Applicant returned to address corrections 12/14/2020 JOE VO
Applicant returned to address corrections 1/7/2021 JOE VO
Applicant returned to address corrections 1/11/2021 JOE VO
Plan Check Approved 1/28/2021 JOE VO
Issued 1/29/2021 APPLICANT
TCO Issued (Expire Date: 01-03-2024) 7/7/2023 ERNESTO CORRAL
CofO in Progress 10/20/2023 JAMES POWERS
Permit Finaled 10/20/2023 ERNESTO CORRAL
CofO Issued 10/20/2023 ERNESTO CORRAL
Permit Finaled 10/20/2023 ERNESTO CORRAL

Permit Application Clearance Information

Historic monument Cleared 12/27/2019 LAMBERT GIESSINGER
Address approval Cleared 2/7/2020 CELINA MORENO
Metro Rail approval Cleared 2/25/2020 JOE VO
Eng Process Fee Ord 176,300 Cleared 2/28/2020 JUAN ASHTON
DCP conditions approval Cleared 10/7/2020 JAMES MCCARTHY
Density Bonus 12.22.A.31 Cleared 10/7/2020 JAMES MCCARTHY
DCP conditions approval Cleared 10/21/2020 JAMES MCCARTHY
Permit Cleared 10/22/2020 WALLIE JONG
"D" conditions Cleared 11/13/2020 MARITZA PRZEKOP
Frnt yard landscape/Water mgmt Cleared 11/13/2020 MARITZA PRZEKOP
Miscellaneous Cleared 11/13/2020 MARITZA PRZEKOP
Miscellaneous Cleared 11/13/2020 MARITZA PRZEKOP
Opn space landscape/Water mgmt Cleared 11/13/2020 MARITZA PRZEKOP
Site Plan review Cleared 11/13/2020 MARITZA PRZEKOP
Site Plan review Cleared 11/13/2020 MARITZA PRZEKOP
Specific Plan Cleared 11/13/2020 MARITZA PRZEKOP
ZA Case Cleared 11/13/2020 MARITZA PRZEKOP
ZI Cleared 11/13/2020 MARITZA PRZEKOP
Sewer availability Cleared 11/16/2020 WALLIE JONG
ZI Cleared 11/16/2020 GRACIELA ACOSTA
Green Code Cleared 11/17/2020 JOE VO
Hydrant and Access approval Cleared 11/17/2020 MATTHEW CRAIG
Building over 3-story or 36-ft Cleared 11/19/2020 CALOSHA APPROVED
DAS Clearance Cleared 12/3/2020 JOE VO
Driveway location Cleared 12/3/2020 PETE EYRE
Highway dedication Cleared 1/14/2021 WALLIE JONG
Low Impact Development Cleared 1/14/2021 MARTIN FRAGOSO
Fire Marshall Fire Life Safety Cleared 1/20/2021 ANDREW KO
Roof/Waste drainage to street Cleared 1/20/2021 WALLIE JONG
Public Housing Cleared 1/25/2021 LUIS ALVAREZ

Contact Information

Architect Wong,, Wilbur; Lic. No.: C29795 9142 HYDE PARK DRIVE      HUNTINGTON BEACH, CA 92646
Contractor C W Driver Llc; Lic. No.: 1009002-B 468 NORTH ROSEMEAD BLVD      PASADENA, CA 91107
Engineer Tavares,, Ralph Monteiro; Lic. No.: C60484 11777 BERNARDO PLAZA CT      SAN DIEGO, CA 92128

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/2/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/4/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/10/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/10/2021 Partial Approval JAMES POWERS
Piling/Pier/Caisson 6/10/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/11/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/15/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/23/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/23/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/28/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/1/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/16/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/16/2021 Partial Approval JOEY BUCHANAN
Piling/Pier/Caisson 7/16/2021 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/21/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/11/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/13/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/19/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/3/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/3/2021 Partial Approval JAMES POWERS
Green Building Rough 9/3/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/3/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/3/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/21/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/29/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/1/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 10/7/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/12/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/19/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/19/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 10/20/2021 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 10/20/2021 Conditional Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 10/21/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 10/21/2021 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 10/22/2021 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/22/2021 Conditional Approval ERNESTO CORRAL
Drywall Nailing 10/27/2021 Partial Approval JAMES POWERS
Green Building Rough 10/27/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/27/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/1/2021 Partial Approval JONATHAN QUACH
Green Building Rough 11/1/2021 Partial Approval JONATHAN QUACH
Deputy Drilled-In Anchors 11/2/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/2/2021 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 11/3/2021 Partial Approval JAMES POWERS
Pre-Inspection 11/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2021 Partial Approval JAMES POWERS
Green Building Rough 11/4/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 11/15/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 11/15/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/22/2021 Approved TED RIES
Deputy Drilled-In Anchors 11/23/2021 Conditional Approval TED RIES
Deputy Drilled-In Anchors 11/24/2021 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 12/8/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/9/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/10/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/10/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/13/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/14/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/15/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/16/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/16/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/17/2021 Partial Approval JAMES POWERS
Wall Anchors 12/20/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/22/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/23/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/28/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/29/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/30/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/3/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/3/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/4/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/5/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/6/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/6/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/7/2022 Approved TED RIES
Deputy Steel/Welding 1/7/2022 Approved TED RIES
Deputy Reinf. Concrete 1/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/10/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/12/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/12/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/13/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/13/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/18/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/19/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/19/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/20/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/20/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/21/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/21/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/26/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/27/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/27/2022 Partial Approval JAMES POWERS
Drywall Nailing 1/27/2022 Partial Approval JAMES POWERS
Green Building Rough 1/27/2022 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 1/28/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/28/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/31/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/2/2022 Partial Approval JAMES POWERS
Insulation 2/3/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/8/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/9/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/11/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/14/2022 Approved JAMES POWERS
Deputy Steel/Welding 2/15/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/16/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/17/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 2/18/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/22/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/24/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/24/2022 Partial Approval JAMES POWERS
Green Building Rough 2/24/2022 Approved JAMES POWERS
Deputy Steel/Welding 2/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/28/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/28/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/1/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/2/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/3/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/8/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/9/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/15/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/16/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/18/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/21/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/22/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/24/2022 Partial Approval JAMES POWERS
Drywall Nailing 3/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/25/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/29/2022 Conditional Approval TED RIES
Deputy Steel/Welding 3/30/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/31/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/1/2022 Conditional Approval TED RIES
Deputy Steel/Welding 4/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/6/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/8/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/11/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/12/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/12/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/13/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/15/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/18/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 4/22/2022 Conditional Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 5/31/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/13/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/16/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/24/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/30/2022 Partial Approval GREGORY POMISH
Drywall Nailing 7/12/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/19/2022 Partial Approval JAMES POWERS
Drywall Nailing 8/31/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/2/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 9/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 10/20/2022 Partial Approval JAMES POWERS
Insulation 11/17/2022 Partial Approval JAMES POWERS
Drywall Nailing 11/23/2022 Partial Approval JAMES POWERS
Pre-Inspection 12/12/2022 Partial Approval JAMES POWERS
T-Bar Ceiling 1/27/2023 Partial Approval GREGORY POMISH
T-Bar Ceiling 2/6/2023 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Not Ready JAMES POWERS
T-Bar Ceiling 2/9/2023 Partial Approval JAMES POWERS
Green Building Final 3/28/2023 Approved JAMES POWERS
Final 3/29/2023 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Not Ready JAMES POWERS
Drywall Nailing 3/30/2023 Approved JAMES POWERS
Final 3/30/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 3/30/2023 Approved JAMES POWERS
Grading Pre-Inspection 3/30/2023 Approved JAMES POWERS
Reinforced Concrete Frame 3/30/2023 Approved JAMES POWERS
Reinforced Masonry Frame 3/30/2023 Approved JAMES POWERS
Smoke Detectors 3/30/2023 Approved JAMES POWERS
Structural Steel Frame 3/30/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 3/30/2023 Approved JAMES POWERS
Final 10/20/2023 OK to Issue CofO JAMES POWERS
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved JAMES POWERS