5215 E BARKER DR 90042
Certificate Information: 5215 E BARKER DR 90042
- Application / Permit
- 19010-10000-02732
- Plan Check / Job No.
- B19LA13155
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW THREE STORY SFD WITH ROOFTOP DECK
- Permit Issued
- Issued on 11/20/2023
- Issuing Office
- Metro
- Current Status
- Issued on 11/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/25/2019 | APPLICANT |
| Green Plans Picked Up | 7/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | ZAW HAN |
| Corrections Issued | 7/24/2019 | ZAW HAN |
| Quality Review Completed | 7/31/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 8/5/2019 | APPLICANT |
| Applicant returned to address corrections | 2/20/2020 | ZAW HAN |
| Applicant returned to address corrections | 3/16/2020 | ZAW HAN |
| Applicant returned to address corrections | 10/1/2020 | ZAW HAN |
| Plan Check Approved | 6/30/2021 | ZAW HAN |
| Issued | 11/20/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2019 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 12/20/2019 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 12/20/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2019 | ERIK BEASLEY |
| Permit | Cleared | 12/20/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/20/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 1/3/2020 | JEREMY CARTER |
| Frnt yard landscape/Water mgmt | Cleared | 1/15/2020 | SOPHIE GABEL-SCHEINBAU |
| Green Code | Cleared | 1/15/2020 | COLIN LOREDO |
| Low Impact Development | Cleared | 1/21/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/25/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 11/12/2020 | ELAINE LEI |
| Building over 3-story or 36-ft | Cleared | 5/13/2021 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/13/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/13/2021 | TODD ROBERTSON |
| Grading Pre-Inspection | Cleared | 5/13/2021 | TODD ROBERTSON |
| Trees in Parkway | Cleared | 6/8/2021 | JOHN KIM |
| Disturb/Remove Protected Trees | Cleared | 6/10/2021 | STEPHEN DUPREY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Amoroso,, Gregory Michael; Lic. No.: L8771 | 24269 PALO VERDE DR VALENCIA, CA 91354 |
| Engineer | Navidpour,, Nasir; Lic. No.: S5563 | 2115 LA CANADA CRESR DR 107 LA CANADA, CA 91011 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Carnegie,, Vincent John; Lic. No.: EG1608 | P.O. BOX 5444 GLENDALE, CA 912012036 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Piling/Pier/Caisson | 8/28/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Piling/Pier/Caisson | 8/29/2025 | Corrections Issued | DAVID WILLIAMS |
| Piling/Pier/Caisson | 9/2/2025 | Corrections Issued | DAVID WILLIAMS |
| Footing/Foundation/Slab | 12/3/2025 | Partial Approval | RONNIE MEDINA |