4745 W FRANKLIN AVE 90027

Certificate Information: 4745 W FRANKLIN AVE 90027

Application / Permit
19010-10000-02692
Plan Check / Job No.
B19LA12942
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACEESSORY DWELLING UNIT PER AB 494 and SB 229.
Permit Issued
Issued on 12/3/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2019 APPLICANT
Green Plans Picked Up 7/3/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 MONICA RAMIREZ
Corrections Issued 7/15/2019 MONICA RAMIREZ
Quality Review Completed 7/31/2019 HERNAN ARREOLA
Building Plans Picked Up 8/5/2019 APPLICANT
Plan Check Approved 11/1/2019 MONICA RAMIREZ
Issued 12/3/2019 LADBS
CofO in Progress 2/11/2021 JOSEPH MCGARRY
Permit Finaled 2/13/2021 DEROLD HAUFF
CofO Issued 2/13/2021 DEROLD HAUFF
Permit Finaled 2/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/6/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/6/2019 JEANETTE VONG
Hydrant and Access approval Cleared 8/6/2019 GILBERT URREA
Permit Cleared 8/6/2019 JEANETTE VONG
Project located in CRA area Cleared 8/6/2019 JIM URQUHART
Sewer availability Cleared 8/6/2019 JEANETTE VONG
Specific Plan Cleared 8/7/2019 JASON HERNANDEZ
Trees in Parkway Cleared 8/8/2019 JOHN KIM
Construction near power lines Cleared 8/22/2019 RIDWAN HARDY
Green Code Cleared 9/3/2019 KHEDER ALRAZAA
Low Impact Development Cleared 9/3/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/3/2019 ELENA LOPEZ
Disturb/Remove Protected Trees Cleared 9/5/2019 JOHN KIM

Contact Information

Contractor Cornerstone Construction And Design; Lic. No.: 775449-B 4910 MT ROYAL DRIVE      LOS ANGELES, CA 90041
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/18/2019 Not Ready for Inspection LUIS BARRALES
Underground Mechanical 1/31/2020 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 2/3/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 2/7/2020 No Access for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 2/13/2020 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 5/28/2020 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 5/28/2020 Not Ready for Inspection JOSEPH MCGARRY
Deputy Other (see comments) 6/16/2020 Approved ENRIQUE MIRELES
Structural Steel Frame 6/16/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/13/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 8/13/2020 Approved ARTHUR SARGSYAN
Green Building Rough 8/13/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 8/13/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 8/13/2020 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 8/13/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 8/28/2020 Partial Approval JOSEPH MCGARRY
Sewer 8/28/2020 Approved JOSEPH MCGARRY
Underground Mechanical 8/28/2020 Approved JOSEPH MCGARRY
Insulation 9/21/2020 Corrections Issued JOSEPH MCGARRY
Shower Pan 9/21/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 9/25/2020 Approved JOSEPH MCGARRY
Insulation 9/25/2020 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 9/25/2020 Approved JOSEPH MCGARRY
Drywall Nailing 10/7/2020 Conditional Approval JOSEPH MCGARRY
Final 1/11/2021 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 1/11/2021 Approved JOSEPH MCGARRY
Gas Test 1/11/2021 Approved JOSEPH MCGARRY
Green Building Final 1/11/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Not Ready JOSEPH MCGARRY
Service/Power Release 1/11/2021 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 1/11/2021 Approved JOSEPH MCGARRY
Final 1/21/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/21/2021 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 2/8/2021 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 2/8/2021 Approved JOSEPH MCGARRY