445 W COTTAGE HOME ST 90012

Certificate Information: 445 W COTTAGE HOME ST 90012

Application / Permit
19010-10000-02684
Plan Check / Job No.
B19LA12861
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(4) Community Center operated by private agency
Work Description
FOR NEW 3-STORY COMMUNITY CENTER W/ PARKING PODIUM PER ZA-2017-4431-ZV-ZAA
Permit Issued
Issued on 2/26/2021
Issuing Office
Metro
Current Status
CofO Issued on 9/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2019 APPLICANT
Assigned to Plan Check Engineer 7/25/2019 JOE VO
Corrections Issued 8/2/2019 JOE VO
Quality Review Completed 8/5/2019 GARO TELMI
Disabled Access Plans Picked Up 8/7/2019 APPLICANT
Building Plans Picked Up 8/8/2019 APPLICANT
Green Plans Picked Up 4/30/2020 APPLICANT
Plan Check Approved 2/8/2021 JOE VO
Issued 2/26/2021 APPLICANT
CofO in Progress 9/21/2023 RAFAEL ESPINOZA
CofO Issued 9/22/2023 ERNESTO CORRAL
Permit Finaled 9/22/2023 ERNESTO CORRAL

Permit Application Clearance Information

Highway dedication Cleared 8/29/2019 ERIK BEASLEY
Driveway location Cleared 9/3/2019 COLLINS ALLAN
Miscellaneous Cleared 9/3/2019 COLLINS ALLAN
Miscellaneous Cleared 9/3/2019 COLLINS ALLAN
Hydrant and Access approval Cleared 1/27/2020 GILBERT URREA
Fire Marshall Fire Life Safety Cleared 2/7/2020 MENOA AGHAJANI
Food Service Establishment Cleared 2/10/2020 RAMESHBHAIR PATEL
CPC Cleared 2/26/2020 RICHARD REASER
DAS Clearance Cleared 2/27/2020 WAI LAU
Green Code Cleared 3/27/2020 NEGAR NEJAD
Abandoned oil well Cleared 4/15/2020 GEORGE SUCHAND
Abandoned oil well approval Cleared 4/15/2020 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 5/19/2020 WALLIE JONG
Sewer availability Cleared 5/19/2020 WALLIE JONG
Low Impact Development Cleared 5/27/2020 ANDRES COVARRUBIAS
Project located in CRA area Cleared 7/8/2020 GISELLE CORELLA
ZA Case Cleared 7/8/2020 RICHARD REASER
ZI Cleared 7/8/2020 GISELLE CORELLA
Roof/Waste drainage to street Cleared 7/9/2020 THOMAS LANG
Grading Pre-Inspection Cleared 2/1/2021 JOE VO
Building over 3-story or 36-ft Cleared 2/4/2021 CALOSHA APPROVED
Food establishment approval Cleared 2/4/2021 LACDHS APPROVED

Contact Information

Architect Kogachi,, Ryan H; Lic. No.: C27777 4488 VISTA SUPERBA STREET      LOS ANGELES, CA 90065
Contractor Vancrest Construction Corp; Lic. No.: 393800-B 7171 NORTH FIGUEROA STREET      LOS ANGELES, CA 90042
Engineer Lee,, Jack C; Lic. No.: C40870 576 E LAMBERT RD      BREA, CA 92821
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781
Geologist Minas,, Shant; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 8/4/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 8/5/2021 Conditional Approval RAFAEL ESPINOZA
Pre-Inspection 8/6/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/19/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 8/19/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 8/19/2021 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/31/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/3/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/7/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/9/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 9/10/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/10/2021 Conditional Approval RAFAEL ESPINOZA
Pre-Inspection 9/10/2021 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 9/20/2021 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 9/24/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 9/28/2021 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 9/28/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 9/28/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/1/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 10/1/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/4/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/5/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/6/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 10/6/2021 Partial Approval RAFAEL ESPINOZA
Deputy Methane Barrier 10/18/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 11/19/2021 Conditional Approval RAFAEL ESPINOZA
METHANE-Barrier 11/24/2021 Approved RAFAEL ESPINOZA
Deputy Drilled-In Anchors 12/1/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 12/3/2021 Approved RAFAEL ESPINOZA
METHANE-Subgrade 12/3/2021 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/14/2022 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 2/14/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/16/2022 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 2/28/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 3/7/2022 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 3/7/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/14/2022 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 3/14/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval RAFAEL ESPINOZA
Green Building Rough 4/26/2022 Approved RAFAEL ESPINOZA
METHANE-Rough 4/26/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/26/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/26/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/28/2022 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 5/12/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/16/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/20/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 6/2/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/15/2022 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 6/27/2022 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/27/2022 Partial Inspection RAFAEL ESPINOZA
Wood Frame 6/27/2022 Partial Approval RAFAEL ESPINOZA
Insulation 6/30/2022 Approved RAFAEL ESPINOZA
Interior/Exterior Lathing 7/1/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/7/2022 Approved RAFAEL ESPINOZA
Light Gage Steel Frame 7/14/2022 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 7/27/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/29/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/15/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/15/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/18/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/23/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/6/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/6/2022 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 9/29/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/11/2022 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 10/11/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/24/2022 Partial Approval RAFAEL ESPINOZA
T-Bar Ceiling 10/24/2022 Approved RAFAEL ESPINOZA
Masonry Wall/Backfill 11/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 11/18/2022 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 12/7/2022 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 12/13/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 12/14/2022 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 12/19/2022 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 12/19/2022 Partial Approval RAFAEL ESPINOZA
Final 3/9/2023 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 3/9/2023 Approved RAFAEL ESPINOZA
Green Building Final 3/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 3/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 3/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 7/11/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Final 7/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 7/11/2023 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 7/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 7/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/11/2023 Approved RAFAEL ESPINOZA
Wood Frame 7/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 9/21/2023 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 9/21/2023 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 9/21/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 9/21/2023 Approved RAFAEL ESPINOZA
Wood Frame 9/21/2023 Approved RAFAEL ESPINOZA