15322 W DE PAUW ST 90272

Certificate Information: 15322 W DE PAUW ST 90272

Application / Permit
19010-10000-02681
Plan Check / Job No.
B19LA12840
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
FOR NEW 1196 SF 2-STORY ACCESSORY DWELLING UNIT LOCATED AT REAR OF PROPERTY PER AB494 AND SB229. SEE COMMENTS
Permit Issued
Issued on 9/8/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2019 APPLICANT
Green Plans Picked Up 7/10/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 SAM CHANG
Corrections Issued 7/16/2019 SERGIO GUTIERREZ
Quality Review Completed 8/5/2019 KESETE HAREGOT
Building Plans Picked Up 8/6/2019 APPLICANT
Applicant returned to address corrections 10/8/2019 SERGIO GUTIERREZ
Plan Check Approved 10/18/2019 SERGIO GUTIERREZ
Issued 9/8/2020 APPLICANT
CofO in Progress 11/23/2021 ANDREW NAVE
Permit Finaled 12/2/2021 DANIEL ORRANTE
CofO Issued 12/2/2021 DANIEL ORRANTE
Permit Finaled 12/2/2021 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/16/2019 PATRICK MISCHLICH
Address approval Cleared 8/23/2019 KAREN LE
Eng Process Fee Ord 176,300 Cleared 8/23/2019 KAREN LE
Hydrant and Access approval Cleared 8/23/2019 JOHN CONNEALLY
Sewer availability Cleared 8/23/2019 KAREN LE
Green Code Cleared 9/11/2019 SERGIO GUTIERREZ
Low Impact Development Cleared 10/2/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/2/2019 JEANETTE VONG
Stormwater Pollution Mitigatn Cleared 10/2/2019 ANDRES COVARRUBIAS
Coastal Zone Cleared 10/7/2019 NOAH MCCOY
Miscellaneous Cleared 10/7/2019 NOAH MCCOY
ZI Cleared 10/7/2019 NOAH MCCOY
GPI Written Notices Cleared 10/18/2019 SERGIO GUTIERREZ

Contact Information

Contractor Janczak Roman Inc; Lic. No.: 964366-B 12137 VIEWCREST ROAD      STUDIO CITY, CA 91604
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/24/2020 Not Ready for Inspection ANDREW NAVE
Pre-Inspection 11/20/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 12/3/2020 Partial Approval ANDREW NAVE
Masonry Wall/Backfill 12/10/2020 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/11/2020 Partial Approval ANDREW NAVE
Underground Mechanical 12/11/2020 Approved ANDREW NAVE
Masonry Wall/Backfill 12/14/2020 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 12/17/2020 Approved CHRIS CHRISTENSEN
Special/Order Compliance 1/6/2021 Approved ANDREW NAVE
Deputy Wood Construction 2/9/2021 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Approved ANDREW NAVE
HVAC-Rough 5/28/2021 Corrections Issued ANDREW NAVE
PLUMBING-Rough 5/28/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 6/4/2021 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 6/4/2021 Approved ANDREW NAVE
Green Building Rough 6/4/2021 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 6/4/2021 Approved ANDREW NAVE
Verify Sprinkler Sign Off 6/4/2021 Approved ANDREW NAVE
Green Building Rough 7/1/2021 Conditional Approval ADAM ESCOTO
Insulation 7/1/2021 Conditional Approval ADAM ESCOTO
Interior/Exterior Lathing 7/1/2021 Partial Approval ADAM ESCOTO
Drywall Nailing 7/12/2021 Approved ANDREW NAVE
Insulation 7/12/2021 Approved ANDREW NAVE
Shower Pan 7/27/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 8/2/2021 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 10/5/2021 Approved ANDREW NAVE
Gas Test 10/5/2021 Partial Approval ANDREW NAVE
Green Building Final 10/5/2021 Corrections Issued ANDREW NAVE
Green Building Rough 10/5/2021 Approved ANDREW NAVE
PLUMBING-Final 10/5/2021 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 10/5/2021 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 10/22/2021 Corrections Issued ANDREW NAVE
Final 10/22/2021 Corrections Issued ANDREW NAVE
Gas Test 10/22/2021 Approved ANDREW NAVE
Green Building Final 10/22/2021 Not Ready for Inspection ANDREW NAVE
HVAC-Final 10/22/2021 Corrections Issued ANDREW NAVE
PLUMBING-Final 10/22/2021 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 10/22/2021 SGSOV Approved ANDREW NAVE
Service/Power Release 10/22/2021 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 10/22/2021 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 11/12/2021 Approved ANDREW NAVE
Final 11/12/2021 Corrections Issued ANDREW NAVE
Green Building Final 11/12/2021 Approved ANDREW NAVE
HVAC-Final 11/12/2021 Approved ANDREW NAVE
Service/Power Release 11/12/2021 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 11/12/2021 Approved ANDREW NAVE
Final 11/23/2021 OK to Issue CofO ANDREW NAVE
SUSMP-Std. Urban Storm Water 11/23/2021 Approved ANDREW NAVE
Service/Power Release 11/23/2021 Approved ANDREW NAVE