1457 N NORTH MAIN ST 90012

Certificate Information: 1457 N NORTH MAIN ST 90012

Application / Permit
19010-10000-02657
Plan Check / Job No.
B19LA12757
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(27) Joint Living and Working Quarters
Work Description
New 5 story III-A mixed use, 376 state approved modular units apartment building over ground floor type 1-A retail & UNITS. (total 6 story) ( core & shell only) over 1 level subterranean parking garage ( 42 extremely low income units)
Permit Issued
Issued on 1/3/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 7/29/2019 GARO TELMI
Corrections Issued 8/12/2019 GARO TELMI
Quality Review Completed 8/16/2019 CHAD DOI
Building Plans Picked Up 8/27/2019 APPLICANT
Applicant returned to address corrections 2/23/2022 GARO TELMI
Plan Check Approved 5/13/2022 GARO TELMI
No Progress 12/11/2023 GARO TELMI
Plan Check Approved 12/11/2023 GARO TELMI
Issued 1/3/2024 APPLICANT
TCO Issued (Expire Date: 07-27-2026) 1/28/2026 ERNESTO CORRAL
Permit Finaled 4/16/2026 ERNESTO CORRAL
CofO Issued 4/16/2026 ERNESTO CORRAL
Permit Finaled 4/16/2026 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/30/2020 ERIK BEASLEY
Address approval Cleared 1/31/2020 JEANETTE VONG
Permit Cleared 8/4/2020 JAMES MORALEZ
Certificate of Compliance Cleared 8/31/2021 DANIEL CORONADO
Driveway location Cleared 10/27/2021 PETE EYRE
Internal circulation Cleared 10/27/2021 PETE EYRE
Bicycle Parking Cleared 11/15/2021 JEREMY CHOK
Food Service Establishment Cleared 12/6/2021 KENNETH BROWNE
Trees in Parkway Cleared 12/15/2021 ADALBERTO VERA
Work Adjacent to Public Way Cleared 1/12/2022 ARMEN SARKISIAN
Low Impact Development Cleared 2/1/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/2/2022 CHRISTOPHER ROCHA
Encroachment in public way Cleared 2/3/2022 JEREMY CHOK
Green Code Cleared 3/3/2022 GARO TELMI
Hydrant and Access approval Cleared 3/7/2022 KURT CORRAL
Fire Marshall Fire Life Safety Cleared 3/8/2022 MENOA AGHAJANI
DAS Clearance Cleared 3/15/2022 GARO TELMI
DCP conditions approval Cleared 4/13/2022 RICHARD TRUONG
Density Bonus 12.22.A.31 Cleared 4/13/2022 RICHARD TRUONG
Specific Plan Cleared 4/26/2022 OSVALDO GARCIA
Miscellaneous Cleared 5/3/2022 DANIEL CORONADO
Opn space landscape/Water mgmt Cleared 5/3/2022 DANIEL CORONADO
Site Plan review Cleared 5/3/2022 DANIEL CORONADO
APC Cleared 5/4/2022 DANIEL CORONADO
Sewer availability Cleared 5/9/2022 CHRISTOPHER ROCHA
Building over 3-story or 36-ft Cleared 5/13/2022 CALOSHA APPROVED
Construction within easement Cleared 5/13/2022 RIDWAN HARDY
Excavation more than 5-ft deep Cleared 5/13/2022 CALOSHA APPROVED
DCP conditions approval Cleared 9/7/2023 NICHOLAS KAWAZOE
Density Bonus Cleared 9/7/2023 NICHOLAS KAWAZOE
Highway dedication Cleared 12/12/2023 WALLIE JONG

Contact Information

Contractor Built By Thrive Llc; Lic. No.: 1108114-B 131 CHARLES STREET      NEW YORK, NY 10014
Engineer Atry,, Andrew James; Lic. No.: C84728 215 N WOODS AVE      FULLERTON, CA 92832
Engineer Krief,, Dan D; Lic. No.: C76041 6420 WILSHIRE BLVD STE 1000      LOS ANGELES, CA 90048
Engineer Marcus,, Matthew Werner; Lic. No.: GE3156 2154 TORRANCE BLVD      TORRANCE, CA 90501

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/12/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 1/12/2024 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 1/12/2024 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 1/16/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/23/2024 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 1/23/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/24/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/30/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/30/2024 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 1/31/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/1/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/7/2024 Corrections Issued LARRY ARNICK
Footing/Foundation/Slab 2/7/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/8/2024 Partial Approval LARRY ARNICK
Deputy Shotcrete 2/9/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/9/2024 Partial Approval LARRY ARNICK
Deputy Shotcrete 2/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/13/2024 Conditional Approval LARRY ARNICK
Deputy Shotcrete 2/13/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/13/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/14/2024 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 2/15/2024 Conditional Approval LARRY ARNICK
Deputy Shotcrete 2/15/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/15/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 2/16/2024 Conditional Approval NICK DANERI
Deputy Shotcrete 2/16/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/16/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/22/2024 Conditional Approval NICK DANERI
Deputy Shotcrete 2/22/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/22/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/27/2024 Conditional Approval LARRY ARNICK
Deputy Shotcrete 2/27/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/27/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 2/28/2024 Conditional Approval LARRY ARNICK
Deputy Shotcrete 2/28/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/28/2024 Partial Approval LARRY ARNICK
Green Building Rough 2/28/2024 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 2/28/2024 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 2/28/2024 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 3/4/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/4/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 3/6/2024 Conditional Approval LARRY ARNICK
Deputy Shotcrete 3/6/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/7/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/8/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 3/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 3/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/13/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/13/2024 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 3/14/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/14/2024 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 3/15/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/15/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 3/18/2024 No Access for Inspection MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 4/15/2024 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 4/16/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/16/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 4/30/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 4/30/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 5/9/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/9/2024 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Masonry 5/10/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/10/2024 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 5/29/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/29/2024 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 5/29/2024 Not Ready for Inspection LARRY ARNICK
Deputy Pre-Stress Concrete 5/30/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 5/30/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/30/2024 Partial Approval LARRY ARNICK
Deputy Pre-Stress Concrete 6/3/2024 Conditional Approval LARRY ARNICK
Deputy Pre-Stress Concrete 6/4/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/4/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/5/2024 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 6/5/2024 Partial Approval LARRY ARNICK
Deputy Pre-Stress Concrete 6/6/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 6/6/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/6/2024 Partial Approval LARRY ARNICK
Deputy Pre-Stress Concrete 6/11/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 6/11/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/11/2024 Partial Approval LARRY ARNICK
Deputy Pre-Stress Concrete 6/12/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 6/12/2024 Conditional Approval LARRY ARNICK
Green Building Rough 6/12/2024 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 6/12/2024 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 6/12/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/13/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/18/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/20/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/21/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/25/2024 Partial Approval LARRY ARNICK
Green Building Rough 7/3/2024 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 7/3/2024 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 7/3/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 7/9/2024 Partial Approval LARRY ARNICK
Deputy Pre-Stress Concrete 7/17/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 7/17/2024 Conditional Approval LARRY ARNICK
Deputy Pre-Stress Concrete 7/18/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 7/18/2024 Conditional Approval LARRY ARNICK
Deputy Pre-Stress Concrete 7/25/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 7/25/2024 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 7/25/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 7/25/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/2/2024 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 8/2/2024 Partial Approval LARRY ARNICK
Deputy Pre-Stress Concrete 8/5/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 8/5/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/5/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 8/13/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/20/2024 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 8/20/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/26/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/10/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/19/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/20/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/24/2024 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 10/4/2024 Conditional Approval LARRY ARNICK
Pre-Inspection 10/4/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 10/15/2024 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 10/22/2024 Conditional Approval LARRY ARNICK
Deputy Wood Construction 10/22/2024 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 10/24/2024 Conditional Approval LARRY ARNICK
Wood Frame 10/24/2024 Conditional Approval LARRY ARNICK
Wood Frame 11/7/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 11/19/2024 Partial Approval LARRY ARNICK
Deputy Steel/Welding 12/2/2024 Conditional Approval LARRY ARNICK
Insulation 12/6/2024 Partial Approval LARRY ARNICK
Insulation 12/9/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 12/9/2024 Partial Approval LARRY ARNICK
Deputy Steel/Welding 12/17/2024 Conditional Approval LARRY ARNICK
Insulation 12/23/2024 Partial Approval LARRY ARNICK
Wood Frame 12/23/2024 Corrections Issued LARRY ARNICK
Wood Frame 1/15/2025 Corrections Issued LARRY ARNICK
Drywall Nailing 1/27/2025 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval LARRY ARNICK
Pre-Inspection 2/19/2025 Approved LARRY ARNICK
Wood Frame 2/19/2025 Partial Approval LARRY ARNICK
Drywall Nailing 2/27/2025 Not Ready for Inspection LARRY ARNICK
Insulation 2/27/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 2/27/2025 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 3/3/2025 Not Ready for Inspection LARRY ARNICK
Insulation 3/10/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 3/10/2025 Not Ready for Inspection LARRY ARNICK
Wood Frame 3/10/2025 Not Ready for Inspection LARRY ARNICK
Insulation 3/12/2025 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 4/10/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 4/14/2025 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 4/14/2025 Partial Inspection LARRY ARNICK
Interior/Exterior Lathing 4/16/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 4/18/2025 Partial Approval LARRY ARNICK
Pre-Inspection 4/18/2025 Partial Inspection LARRY ARNICK
Interior/Exterior Lathing 4/23/2025 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 4/25/2025 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 4/28/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/7/2025 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 5/8/2025 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 5/9/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/12/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 5/12/2025 Partial Approval LARRY ARNICK
Insulation 5/13/2025 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 5/13/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 5/15/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/21/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/27/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/28/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/29/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 6/2/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 6/9/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 6/9/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 6/13/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 6/16/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/23/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/24/2025 Partial Inspection LARRY ARNICK
Interior/Exterior Lathing 6/27/2025 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 7/1/2025 Partial Inspection LARRY ARNICK
Drywall Nailing 7/3/2025 Partial Approval LARRY ARNICK
Drywall Nailing 7/8/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 7/9/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 7/9/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 7/14/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/14/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 7/15/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 7/18/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 7/18/2025 Partial Approval LARRY ARNICK
Drywall Nailing 7/22/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 7/24/2025 Partial Approval LARRY ARNICK
Drywall Nailing 7/28/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 7/31/2025 Partial Approval LARRY ARNICK
Drywall Nailing 8/4/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 8/5/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 8/11/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 8/14/2025 Partial Approval LARRY ARNICK
Drywall Nailing 8/15/2025 Partial Approval RONALD JIMENEZ
Drywall Nailing 8/19/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/22/2025 Partial Approval RONALD JIMENEZ
Drywall Nailing 8/29/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 9/8/2025 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 9/10/2025 Conditional Approval LARRY ARNICK
Pre-Inspection 9/12/2025 Conditional Approval LARRY ARNICK
Pre-Inspection 9/18/2025 Conditional Approval LARRY ARNICK
Pre-Inspection 9/19/2025 Corrections Issued LARRY ARNICK
Light Gage Steel Frame 9/23/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 9/25/2025 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 9/25/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 9/26/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 9/29/2025 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 9/29/2025 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 9/29/2025 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 9/29/2025 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 10/2/2025 Partial Approval LARRY ARNICK
Special/Order Compliance 10/7/2025 Partial Inspection LARRY ARNICK
Pre-Inspection 10/15/2025 Conditional Approval LARRY ARNICK
Final 10/27/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 10/27/2025 Not Ready for Inspection LARRY ARNICK
Green Building Final 10/27/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 10/27/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 10/27/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 10/27/2025 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 10/27/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 10/27/2025 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 10/29/2025 Not Ready for Inspection LARRY ARNICK
Wood Frame 10/31/2025 Approved LARRY ARNICK
Light Gage Steel Frame 11/4/2025 Partial Approval LARRY ARNICK
Wood Frame 11/4/2025 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 11/5/2025 Conditional Approval LARRY ARNICK
Structural Steel Frame 11/5/2025 Approved LARRY ARNICK
Interior/Exterior Lathing 11/7/2025 Approved SCOTT SOBEL
Pre-Inspection 11/7/2025 Partial Approval LARRY ARNICK
Pre-Inspection 11/21/2025 Conditional Approval LARRY ARNICK
Final 12/3/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/3/2025 Not Ready for Inspection LARRY ARNICK
Green Building Final 12/3/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 12/3/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/3/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 12/3/2025 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 12/3/2025 SGSOV Approved LARRY ARNICK
Smoke Detectors 12/3/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 12/3/2025 Not Ready for Inspection LARRY ARNICK
Final 12/8/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/8/2025 Not Ready for Inspection LARRY ARNICK
Green Building Final 12/8/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 12/8/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/8/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 12/8/2025 Not Ready for Inspection LARRY ARNICK
Smoke Detectors 12/8/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 12/8/2025 Not Ready for Inspection LARRY ARNICK
Final 12/16/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/16/2025 Not Ready for Inspection LARRY ARNICK
Green Building Final 12/16/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 12/16/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/16/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 12/16/2025 Not Ready for Inspection LARRY ARNICK
Smoke Detectors 12/16/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 12/16/2025 Not Ready for Inspection LARRY ARNICK
Final 12/19/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/19/2025 Not Ready for Inspection LARRY ARNICK
Green Building Final 12/19/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 12/19/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/19/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 12/19/2025 Not Ready for Inspection LARRY ARNICK
Smoke Detectors 12/19/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 12/19/2025 Not Ready for Inspection LARRY ARNICK
Final 12/30/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/30/2025 Conditional Approval LARRY ARNICK
Green Building Final 12/30/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 12/30/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/30/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 12/30/2025 Not Ready for Inspection LARRY ARNICK
Smoke Detectors 12/30/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 12/30/2025 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 1/6/2026 Partial Approval LARRY ARNICK
Final 1/21/2026 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/21/2026 Approved LARRY ARNICK
Green Building Final 1/21/2026 Not Ready for Inspection LARRY ARNICK
Green Building Rough 1/21/2026 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 1/21/2026 Partial Inspection LARRY ARNICK
Reinforced Concrete Frame 1/21/2026 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 1/21/2026 Not Ready for Inspection LARRY ARNICK
Smoke Detectors 1/21/2026 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/21/2026 Not Ready for Inspection LARRY ARNICK
Final 1/27/2026 OK for TCO LARRY ARNICK
Green Building Final 1/27/2026 Not Ready for Inspection LARRY ARNICK
Green Building Rough 1/27/2026 Approved LARRY ARNICK
Reinforced Concrete Frame 1/27/2026 Approved LARRY ARNICK
Reinforced Masonry Frame 1/27/2026 Approved LARRY ARNICK
Smoke Detectors 1/27/2026 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/27/2026 Approved LARRY ARNICK
Pre-Inspection 2/2/2026 Partial Inspection LARRY ARNICK
Pre-Inspection 2/5/2026 Partial Inspection LARRY ARNICK
Pre-Inspection 2/24/2026 Approved RONALD JIMENEZ
Final 2/26/2026 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 2/26/2026 Not Ready for Inspection RONALD JIMENEZ
Smoke Detectors 2/26/2026 Approved RONALD JIMENEZ
Green Building Final 3/10/2026 Approved RONALD JIMENEZ
Pre-Inspection 3/10/2026 Approved RONALD JIMENEZ
Special/Order Compliance 3/11/2026 Approved RONALD JIMENEZ
Special/Order Compliance 3/12/2026 Corrections Issued RONALD JIMENEZ
Final 3/16/2026 Partial Inspection RONALD JIMENEZ
Final 3/19/2026 Partial Approval ERNESTO CORRAL
Pre-Inspection 3/24/2026 Approved RONALD JIMENEZ
Final 3/25/2026 Conditional Approval RONALD JIMENEZ