1345 1/2 W 74TH ST 90044
Certificate Information: 1345 1/2 W 74TH ST 90044
- Application / Permit
- 19010-10000-02651
- Plan Check / Job No.
- B19LA12700
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONSTRUCT A NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 AT REAR OF PROPERTY
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- Issued on 3/6/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | VU NGUYEN |
| Corrections Issued | 8/1/2019 | VU NGUYEN |
| Quality Review Completed | 8/12/2019 | JOSE RODRIGUEZ |
| Green Plans Picked Up | 8/16/2019 | APPLICANT |
| Building Plans Picked Up | 8/19/2019 | APPLICANT |
| Plan Check Approved | 2/18/2020 | VU NGUYEN |
| Issued | 3/6/2020 | LADBS |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 1/28/2020 | JOE LUCKEY |
| Low Impact Development | Cleared | 1/28/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/28/2020 | THOMAS LANG |
| Address approval | Cleared | 1/29/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2020 | CELINA MORENO |
| Sewer availability | Cleared | 1/29/2020 | CELINA MORENO |
| Green Code | Cleared | 2/18/2020 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/11/2021 | Approved | FREDDIE RIVERA |
| Sewer | 4/14/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 4/14/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 4/23/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/12/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/13/2021 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 8/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 9/7/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 9/10/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 9/10/2021 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 9/10/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 9/10/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 11/24/2021 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 3/14/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/14/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 3/16/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 3/16/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/16/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 3/16/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 3/16/2022 | Approved | LILIANA PORTILLO |
| Insulation | 3/21/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/21/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/30/2022 | Approved | LILIANA PORTILLO |