Pre-Inspection
|
7/8/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
10/1/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Other (see comments)
|
10/5/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/5/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
10/27/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
10/28/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
10/29/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/1/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/4/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
11/8/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/10/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Other (see comments)
|
11/12/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
11/12/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/15/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/19/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/22/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
12/7/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
12/7/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
12/20/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
1/12/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
1/31/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
2/1/2022
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/1/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
2/2/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Other (see comments)
|
3/4/2022
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/7/2022
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/10/2022
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/10/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/14/2022
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/21/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
3/24/2022
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/29/2022
|
Partial Approval
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
4/1/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
4/13/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/14/2022
|
Conditional Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
4/18/2022
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
5/16/2022
|
Not Ready for Inspection
|
DARRYL ARNOLD
|
|
Excavation/Setback/Form/Re-Bar
|
5/17/2022
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/18/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/18/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
5/18/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
5/18/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
5/23/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/23/2022
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
5/24/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
5/26/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/26/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
5/27/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/10/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/26/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/21/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/1/2022
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/6/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
2/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Insulation
|
3/9/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
3/16/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/30/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
4/10/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
4/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/10/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/12/2023
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
5/12/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/15/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/15/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/16/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Wood Frame
|
5/16/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/17/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Insulation
|
5/17/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
5/18/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/21/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/30/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/7/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
7/26/2023
|
Corrections Issued
|
GREGORY POMISH
|
|
Drywall Nailing
|
8/23/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/7/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
9/15/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
10/6/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
11/9/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
11/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
11/15/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
11/17/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
11/27/2023
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
11/28/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
12/5/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/7/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/12/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
12/12/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
1/4/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/9/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
1/9/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/23/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
1/23/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
1/24/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/2/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
3/4/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
4/10/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Special/Order Compliance
|
4/10/2024
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Light Gage Steel Frame
|
4/12/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
4/19/2024
|
Partial Approval
|
NICK DANERI
|
|
T-Bar Ceiling
|
4/19/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
4/29/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
5/3/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
6/3/2024
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
6/3/2024
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
6/10/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
6/27/2024
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
9/18/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
10/10/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
10/22/2024
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
11/18/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
11/21/2024
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
11/22/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/14/2025
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
1/14/2025
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
2/5/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
2/20/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
3/25/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
4/1/2025
|
Approved
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
9/26/2025
|
Approved
|
JOEY BUCHANAN
|
|
Special/Order Compliance
|
10/21/2025
|
Approved
|
JOEY BUCHANAN
|
|
Light Gage Steel Frame
|
11/5/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
11/14/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
12/8/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Light Gage Steel Frame
|
1/30/2026
|
Approved
|