10966 S SPRING ST 90061

Certificate Information: 10966 S SPRING ST 90061

Application / Permit
19010-10000-02633
Plan Check / Job No.
B19LA12650
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW TWO STORY DUPLEX WITH ATTACHED GARAGE
Permit Issued
Issued on 10/7/2019
Issuing Office
Metro
Current Status
CofO Corrected on 6/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2019 APPLICANT
Green Plans Picked Up 7/2/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 MANUEL MONTUFAR
Corrections Issued 7/15/2019 MANUEL MONTUFAR
Quality Review Completed 7/31/2019 KESETE HAREGOT
Building Plans Picked Up 8/1/2019 APPLICANT
Plan Check Approved 9/18/2019 MANUEL MONTUFAR
Issued 10/7/2019 LADBS
CofO in Progress 4/24/2020 EUGENE CASSIDY
CofO Issued-Status Void 5/21/2020 BOB DUNN
Permit Finaled-Status Void 5/21/2020 BOB DUNN
Re-Activate Permit 6/19/2020 DEROLD HAUFF
Permit Finaled 6/19/2020 BOB DUNN
CofO Corrected 6/19/2020 BOB DUNN
Permit Finaled 6/19/2020 BOB DUNN

Permit Application Clearance Information

Address approval Cleared 8/16/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/16/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 8/16/2019 JEREMY CARTER
Permit Cleared 8/16/2019 ADRIAN SANCHEZ
Sewer availability Cleared 8/16/2019 ADRIAN SANCHEZ
Community Plan Implem. Overlay Cleared 9/3/2019 JOE LUCKEY
Low Impact Development Cleared 9/4/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/4/2019 JEANETTE VONG
Trees in Parkway Cleared 9/4/2019 ADRIAN SANCHEZ
Green Code Cleared 9/10/2019 KHEDER ALRAZAA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/31/2019 Not Ready for Inspection WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 11/1/2019 Partial Approval WILLIAM ROSE
Special/Order Compliance 11/1/2019 Approved WILLIAM ROSE
Footing/Foundation/Slab 11/4/2019 Approved JOHN KLARIN
Deputy Reinf. Concrete 11/5/2019 No Result Entered MARK HATFIELD
Underground Mechanical 11/12/2019 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Partial Approval EUGENE CASSIDY
Insulation 11/13/2019 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/14/2019 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/21/2019 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/16/2019 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/18/2019 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/30/2020 Approved WILLIAM ROSE
ELECTRICAL-Rough 1/30/2020 Approved WILLIAM ROSE
Green Building Rough 1/30/2020 Approved WILLIAM ROSE
HVAC-Rough 1/30/2020 Approved WILLIAM ROSE
PLUMBING-Rough 1/30/2020 Approved WILLIAM ROSE
Verify Sprinkler Sign Off 1/30/2020 Approved WILLIAM ROSE
Insulation 1/31/2020 Approved WILLIAM ROSE
Drywall Nailing 2/12/2020 Approved WILLIAM ROSE
Interior/Exterior Lathing 2/12/2020 Approved WILLIAM ROSE
ELECTRICAL-Final 4/23/2020 Approved EUGENE CASSIDY
Final 4/23/2020 OK to Issue CofO EUGENE CASSIDY
Green Building Final 4/23/2020 Approved EUGENE CASSIDY
HVAC-Final 4/23/2020 Approved EUGENE CASSIDY
PLUMBING-Final 4/23/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/23/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/23/2020 Approved EUGENE CASSIDY
Smoke Detectors 4/23/2020 Approved EUGENE CASSIDY