2153 W 21ST ST 90018
Certificate Information: 2153 W 21ST ST 90018
- Application / Permit
- 19010-10000-02629
- Plan Check / Job No.
- B19LA12633
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TO CONSTRUCT A NEW ACCESSORY DWELLING UNIT AND ATTACHED 2-CAR GARAGE PER AB 494 AND SB229
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2019 | ALBERT SERVIN |
| Green Plans Picked Up | 8/1/2019 | APPLICANT |
| Corrections Issued | 8/2/2019 | ALBERT SERVIN |
| Quality Review Completed | 8/7/2019 | GARO TELMI |
| Building Plans Picked Up | 8/13/2019 | APPLICANT |
| Plan Check Approved | 11/27/2019 | ALBERT SERVIN |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 2/8/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
| CofO Issued | 2/14/2022 | DEROLD HAUFF |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2019 | JEANETTE VONG |
| Certificate of Compliance | Cleared | 8/22/2019 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 8/22/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 8/22/2019 | JEANETTE VONG |
| Street width determination | Cleared | 8/22/2019 | JEANETTE VONG |
| Green Code | Cleared | 8/29/2019 | VIVIAN LAO |
| Construction near power lines | Cleared | 10/24/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/24/2019 | RIDWAN HARDY |
| HPOZ | Cleared | 11/5/2019 | AMANDA KAINER |
| Hist. Property Cntrct Mgr Appr | Cleared | 11/5/2019 | AMANDA KAINER |
| Low Impact Development | Cleared | 11/5/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | THOMAS LANG |
Contact Information
| Contractor | New Home Design & Construction; Lic. No.: 954350-B | 1111 CAMINO DEL SUR SAN DIMAS, CA 91773 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 3/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 3/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Barrier | 3/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 3/27/2020 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 4/3/2020 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 4/3/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/3/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/1/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/9/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/9/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/9/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 7/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Rough | 7/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/9/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 7/9/2020 | Approved | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 7/13/2020 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/11/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 8/11/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 8/11/2020 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 8/11/2020 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 8/11/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/11/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/13/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 8/13/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 8/24/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/25/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 8/25/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/25/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 9/2/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 11/17/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 11/24/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 3/26/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 3/26/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 3/26/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 3/26/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 3/26/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 9/3/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 9/3/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 9/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 9/3/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 12/2/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 12/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 12/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 2/4/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Service/Power Release | 2/4/2022 | Approved | KATHRYN BUTTERWORTH |