2153 W 21ST ST 90018

Certificate Information: 2153 W 21ST ST 90018

Application / Permit
19010-10000-02629
Plan Check / Job No.
B19LA12633
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TO CONSTRUCT A NEW ACCESSORY DWELLING UNIT AND ATTACHED 2-CAR GARAGE PER AB 494 AND SB229
Permit Issued
Issued on 2/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2019 APPLICANT
Assigned to Plan Check Engineer 7/26/2019 ALBERT SERVIN
Green Plans Picked Up 8/1/2019 APPLICANT
Corrections Issued 8/2/2019 ALBERT SERVIN
Quality Review Completed 8/7/2019 GARO TELMI
Building Plans Picked Up 8/13/2019 APPLICANT
Plan Check Approved 11/27/2019 ALBERT SERVIN
Issued 2/24/2020 LADBS
CofO in Progress 2/8/2022 KATHRYN BUTTERWORTH
Permit Finaled 2/14/2022 DEROLD HAUFF
CofO Issued 2/14/2022 DEROLD HAUFF
Permit Finaled 2/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2019 JEANETTE VONG
Certificate of Compliance Cleared 8/22/2019 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 8/22/2019 JEANETTE VONG
Hydrant and Access approval Cleared 8/22/2019 GEORGE SUCHAND
Sewer availability Cleared 8/22/2019 JEANETTE VONG
Street width determination Cleared 8/22/2019 JEANETTE VONG
Green Code Cleared 8/29/2019 VIVIAN LAO
Construction near power lines Cleared 10/24/2019 RIDWAN HARDY
Construction within easement Cleared 10/24/2019 RIDWAN HARDY
HPOZ Cleared 11/5/2019 AMANDA KAINER
Hist. Property Cntrct Mgr Appr Cleared 11/5/2019 AMANDA KAINER
Low Impact Development Cleared 11/5/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 11/5/2019 THOMAS LANG

Contact Information

Contractor New Home Design & Construction; Lic. No.: 954350-B 1111 CAMINO DEL SUR      SAN DIMAS, CA 91773
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 3/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Subgrade 3/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/27/2020 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Barrier 3/27/2020 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 3/27/2020 Corrections Issued ENRIQUE MIRELES
METHANE-Barrier 4/3/2020 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 4/3/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 4/3/2020 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/1/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/9/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/9/2020 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 7/9/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 7/9/2020 Corrections Issued KATHRYN BUTTERWORTH
MERV13>=Rough 7/9/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 7/9/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 7/9/2020 Corrections Issued KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 7/9/2020 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 7/13/2020 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 8/11/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 8/11/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 8/11/2020 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 8/11/2020 Approved KATHRYN BUTTERWORTH
METHANE-Rough 8/11/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 8/11/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/13/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/13/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 8/24/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/25/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 8/25/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/25/2020 Partial Approval KATHRYN BUTTERWORTH
Insulation 9/2/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 9/14/2020 Approved KATHRYN BUTTERWORTH
Green Building Final 11/17/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 11/24/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 3/26/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 3/26/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Final 3/26/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/26/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 3/26/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 3/26/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 9/3/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 9/3/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 9/3/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 9/3/2021 Approved KATHRYN BUTTERWORTH
Final 12/2/2021 Corrections Issued KATHRYN BUTTERWORTH
Final 12/14/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Service/Power Release 12/14/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 2/4/2022 Partial Approval KATHRYN BUTTERWORTH
Service/Power Release 2/4/2022 Approved KATHRYN BUTTERWORTH