9515 S COMPTON AVE 90002

Certificate Information: 9515 S COMPTON AVE 90002

Application / Permit
19010-10000-02628
Plan Check / Job No.
B19LA12615
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 3-story, Type VA, 21 unit, apartment building TOC Tier 2, 100% affordable
Permit Issued
Issued on 1/7/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2019 APPLICANT
Disabled Access Plans Picked Up 7/1/2019 APPLICANT
Green Plans Picked Up 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 VU NGUYEN
Corrections Issued 7/22/2019 VU NGUYEN
Quality Review Completed 8/2/2019 JOSE RODRIGUEZ
Building Plans Picked Up 8/8/2019 APPLICANT
Applicant returned to address corrections 10/9/2019 VU NGUYEN
Applicant returned to address corrections 10/10/2019 VU NGUYEN
Plan Check Approved 1/3/2020 VU NGUYEN
Issued 1/7/2020 LADBS
TCO Issued (Expire Date: 10-02-2022) 4/5/2022 TED RIES
CofO in Progress 7/21/2022 JAMES POWERS
CofO Issued 7/25/2022 ERNESTO CORRAL
Permit Finaled 7/25/2022 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/15/2019 JEANIE LAM
Community Plan Implem. Overlay Cleared 8/15/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 8/15/2019 JEANIE LAM
Sewer availability Cleared 8/23/2019 JEANETTE VONG
Highway dedication Cleared 9/11/2019 JEANETTE VONG
Hydrant and Access approval Cleared 9/18/2019 ROBERT DUFF
Green Code Cleared 10/1/2019 KHEDER ALRAZAA
DAS Clearance Cleared 10/17/2019 VU NGUYEN
Fire Marshall Fire Life Safety Cleared 11/5/2019 VIDAL GARCIA
Low Impact Development Cleared 11/13/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/13/2019 ERIK BEASLEY
Density Bonus 12.22.A.31 Cleared 12/24/2019 RICHARD TRUONG

Contact Information

Architect Poindexter,, John Roger; Lic. No.: C9744 1059 ONEONTA DR      LOS ANGELES, CA 90065
Contractor Ap Contractors & Developers; Lic. No.: 643672-B PO BOX 4577      LA PUENTE, CA 91747
Engineer Kardjian,, Vahe Matios; Lic. No.: C40821 1648 W GLENOAKS BLVD STE 102      GLENDALE, CA 91201
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/24/2020 Approved JOEY BUCHANAN
Footing/Foundation/Slab 1/24/2020 Corrections Issued JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 1/29/2020 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 2/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/13/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/13/2020 Partial Approval JAMES POWERS
Deputy Other (see comments) 2/14/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 Partial Approval JAMES POWERS
Green Building Rough 3/10/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/10/2020 Not Ready for Inspection JAMES POWERS
Green Building Rough 4/24/2020 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/24/2020 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 4/24/2020 Partial Approval DAVID BURKHEAD
Green Building Rough 5/18/2020 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 5/18/2020 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 5/18/2020 Partial Approval JOEY BUCHANAN
Wood Frame 5/22/2020 Partial Approval JAMES POWERS
Wood Frame 5/28/2020 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 6/10/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 6/15/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/16/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 6/16/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/19/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/24/2020 Approved JOEY BUCHANAN
Wood Frame 6/24/2020 Partial Approval JOEY BUCHANAN
Wood Frame 6/25/2020 Conditional Approval JOEY BUCHANAN
Interior/Exterior Lathing 9/10/2020 Approved RAFAEL ESPINOZA
Wood Frame 9/23/2020 Partial Approval JAMES POWERS
Insulation 10/27/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/17/2020 Partial Approval NICK DANERI
Drywall Nailing 3/9/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/9/2021 Approved JOEY BUCHANAN
Final 12/22/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 12/22/2021 Approved JAMES POWERS
Green Building Final 12/22/2021 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Not Ready JAMES POWERS
Smoke Detectors 12/22/2021 Approved JAMES POWERS
Special/Order Compliance 12/22/2021 Approved JAMES POWERS
Wood Frame 12/22/2021 Approved JAMES POWERS
Final 3/14/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Approved JAMES POWERS
Final 4/4/2022 Not Ready for Inspection JAMES POWERS
Final 4/5/2022 OK for TCO JAMES POWERS
Final 7/1/2022 Not Ready for Inspection JAMES POWERS
Final 7/5/2022 Not Ready for Inspection JAMES POWERS
Final 7/20/2022 OK to Issue CofO JAMES POWERS