388 N HOMEWOOD ROAD 90049
Certificate Information: 388 N HOMEWOOD ROAD 90049
- Application / Permit
- 19010-10000-02574
- Plan Check / Job No.
- B19LA12350
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY AND BASEMENT SFD W/ ATTACHED GARAGE.
- Permit Issued
- Issued on 11/15/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | JOE VO |
| Corrections Issued | 7/8/2019 | JOE VO |
| Green Plans Picked Up | 7/15/2019 | APPLICANT |
| Quality Review Completed | 7/16/2019 | GARO TELMI |
| Building Plans Picked Up | 7/19/2019 | APPLICANT |
| Plan Check Approved | 11/6/2019 | JOE VO |
| Issued | 11/15/2019 | LADBS |
| CofO in Progress | 6/26/2023 | KENNETH NAGLE |
| Permit Finaled | 6/26/2023 | DANIEL ORRANTE |
| CofO Issued | 6/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 7/25/2019 | CHRISTOPHER LAW |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | JOSE CRUZ RODRIGUEZ |
| Flood clearance | Cleared | 7/29/2019 | TUYEN LE |
| Sewer availability | Cleared | 7/29/2019 | JOSE CRUZ RODRIGUEZ |
| Hydrant and Access approval | Cleared | 9/27/2019 | JOHN CONNEALLY |
| Green Code | Cleared | 10/2/2019 | COLIN LOREDO |
| Low Impact Development | Cleared | 10/16/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/16/2019 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 11/6/2019 | JOE VO |
| Miscellaneous | Cleared | 11/6/2019 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2019 | Corrections Issued | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 1/14/2020 | Partial Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 1/28/2020 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 2/26/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 2/27/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 3/19/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 3/26/2020 | Conditional Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 4/28/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Wood Construction | 7/6/2020 | Approved | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Conditional Approval | TIM CHRISTENSEN |
| Green Building Rough | 8/11/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Verify Sprinkler Sign Off | 8/11/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Deputy Wood Construction | 8/12/2020 | Conditional Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Partial Approval | TIM CHRISTENSEN |
| Green Building Rough | 9/25/2020 | No Access for Inspection | TIM CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/25/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 11/2/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 11/5/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 11/5/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/21/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/7/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Rough | 1/7/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 1/7/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Deputy Wood Construction | 1/11/2021 | Approved | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2021 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 1/15/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 1/15/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Partial Inspection | JUAN VALENZUELA |
| Green Building Rough | 2/3/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 2/3/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Underground Mechanical | 2/4/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/25/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 2/25/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/25/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 3/17/2021 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 4/5/2021 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 4/5/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 4/6/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 4/9/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 4/13/2021 | Conditional Approval | JUAN VALENZUELA |
| Green Building Rough | 4/13/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 4/13/2021 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 4/13/2021 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 4/13/2021 | Approved | JUAN VALENZUELA |
| Insulation | 4/22/2021 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 4/29/2021 | Partial Approval | PIERRE VEGA |
| Drywall Nailing | 5/4/2021 | Approved | JUAN VALENZUELA |
| Deputy Steel/Welding | 6/1/2021 | No Access for Inspection | AMY COLIN |
| Shower Pan | 6/8/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Structural Steel Frame | 6/8/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 6/18/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/28/2021 | Approved | JUAN VALENZUELA |
| Sewer | 10/27/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 10/28/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 11/3/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 11/8/2021 | Partial Approval | DEANDRE HOFFMAN |
| Sewer | 11/10/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/1/2022 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 6/7/2022 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 11/7/2022 | Partial Inspection | JUAN VALENZUELA |
| Service/Power Release | 2/15/2023 | Approved | KENNETH NAGLE |
| HVAC-Final | 3/1/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/30/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 4/5/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 4/7/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 4/10/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 4/13/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/26/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/27/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | KEVIN SARGSYAN |
| Final | 5/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/17/2023 | Approved | KEVIN SARGSYAN |
| Green Building Final | 5/17/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 5/17/2023 | Approved | KEVIN SARGSYAN |
| Pre-Inspection | 5/18/2023 | Partial Inspection | KEVIN SARGSYAN |
| Special/Order Compliance | 5/18/2023 | Partial Inspection | DANIEL ORRANTE |
| Final | 6/22/2023 | Conditional Approval | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | KENNETH NAGLE |