615 N NORTH FARING ROAD 90077

Certificate Information: 615 N NORTH FARING ROAD 90077

Application / Permit
19010-10000-02525
Plan Check / Job No.
B19LA12236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH HABITABLE BASEMENT AND ATTACHED 5-CAR GARAGE.
Permit Issued
Issued on 11/25/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 KEVIN MORALES
Corrections Issued 7/1/2019 KEVIN MORALES
Green Plans Picked Up 7/1/2019 APPLICANT
Quality Review Completed 7/20/2019 YOUNG KIM
Building Plans Picked Up 7/26/2019 APPLICANT
Plan Check Approved 11/20/2019 KEVIN MORALES
Issued 11/25/2019 LADBS
CofO in Progress 9/1/2023 CHRISTOPHER WILSON
CofO in Progress 9/6/2023 CHRISTOPHER WILSON
Permit Finaled 9/12/2023 DANIEL ORRANTE
CofO Issued 9/12/2023 DANIEL ORRANTE
Permit Finaled 9/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/29/2019 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 7/29/2019 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 7/29/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 7/29/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 7/31/2019 GEORGE SUCHAND
Sewer availability Cleared 8/7/2019 MARKOS PEREZ-BRAN
Trees in Parkway Cleared 8/22/2019 JOHN KIM
GPI Written Notices Cleared 8/23/2019 KEVIN MORALES
Grading Pre-Inspection Cleared 8/23/2019 KEVIN MORALES
Permit Cleared 8/23/2019 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 8/29/2019 CALOSHA APPROVED
Green Code Cleared 9/16/2019 KEVIN MORALES
Low Impact Development Cleared 11/12/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 11/12/2019 THOMAS LANG
BHO/Hillside ordinance Cleared 11/15/2019 TAO YANG

Contact Information

Architect Harouni,, Faradj-Ollah; Lic. No.: C13577 6334 WILSHIRE BLVD      LOS ANGELES, CA 90048
Contractor Pacific Source Construction Co Inc; Lic. No.: 829721-B 18067 LAKE ENCINO DRIVE      ENCINO, CA 91316

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/6/2019 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/27/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/9/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/8/2020 Partial Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/9/2020 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 4/10/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/14/2020 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 4/16/2020 Conditional Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 4/27/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 4/30/2020 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/30/2020 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Rough 5/4/2020 Partial Inspection CHRISTOPHER WILSON
Sewer 5/4/2020 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 5/6/2020 Partial Approval ANTHONY MCDOWALL
Sewer 5/6/2020 Not Ready for Inspection ANTHONY MCDOWALL
Deputy Drilled-In Anchors 5/20/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/21/2020 Corrections Issued MATT KELLERMAN
Deputy Reinf. Concrete 5/26/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/26/2020 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 5/29/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 6/6/2020 Partial Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/1/2020 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 7/1/2020 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 7/20/2020 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/24/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 8/19/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/19/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 8/31/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/9/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/11/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/18/2020 Corrections Issued MATT KELLERMAN
Deputy Reinf. Concrete 9/22/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/22/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 9/28/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 9/29/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 9/30/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 10/1/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 10/2/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/7/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/27/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/28/2020 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/17/2020 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 12/17/2020 Partial Approval THOMAS FINNILA
HVAC-Rough 12/17/2020 Partial Approval THOMAS FINNILA
PLUMBING-Rough 12/17/2020 Partial Approval THOMAS FINNILA
Wood Frame 12/17/2020 Partial Approval THOMAS FINNILA
Deputy Wood Construction 12/21/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/24/2020 Corrections Issued MATT KELLERMAN
Deputy Wood Construction 1/6/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/21/2021 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 2/8/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 3/27/2021 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 4/6/2021 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 4/16/2021 Partial Approval CHRISTOPHER WILSON
Sewer 5/28/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Partial Approval ANTHONY MCDOWALL
Deputy Wood Construction 6/30/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 7/13/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 7/27/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/29/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 7/30/2021 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Rough 8/5/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 8/13/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 8/13/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 8/17/2021 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 8/17/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 8/19/2021 Approved CHRISTOPHER WILSON
HVAC-Rough 8/19/2021 Approved CHRISTOPHER WILSON
Shower Pan 8/19/2021 Partial Approval CHRISTOPHER WILSON
Insulation 8/26/2021 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 8/31/2021 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 9/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/29/2021 Partial Approval CHRISTOPHER WILSON
Insulation 9/29/2021 Partial Approval CHRISTOPHER WILSON
Shower Pan 10/1/2021 Corrections Issued CHRISTOPHER WILSON
Shower Pan 10/7/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/13/2021 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Approval CHRISTOPHER WILSON
Green Building Rough 10/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/1/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 12/1/2021 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 12/1/2021 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/14/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 12/14/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 12/14/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 12/14/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 1/5/2022 Approved CHRISTOPHER WILSON
Green Building Rough 1/5/2022 Approved CHRISTOPHER WILSON
Insulation 1/5/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 1/21/2022 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 2/4/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 2/22/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/27/2022 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 9/27/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/4/2022 Partial Inspection CHRISTOPHER WILSON
Enclosure/Fence 11/21/2022 Not Ready for Inspection CARLOS MATAMOROS
Masonry Wall/Backfill 11/21/2022 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 12/1/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 12/20/2022 Partial Approval CLAYTON GRAHAM
Gas Test 12/21/2022 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved CHRISTOPHER WILSON
Gas Test 2/10/2023 Approved MICHAEL PELHAM
Underground Mechanical 2/10/2023 Partial Approval MICHAEL PELHAM
Drywall Nailing 5/17/2023 Approved CHRISTOPHER WILSON
Final 5/17/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/17/2023 Approved CHRISTOPHER WILSON
Green Building Final 5/17/2023 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/17/2023 Approved CHRISTOPHER WILSON
Service/Power Release 5/17/2023 Not Ready for Inspection CHRISTOPHER WILSON
Smoke Detectors 5/17/2023 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 5/17/2023 Approved CHRISTOPHER WILSON
Pre-Inspection 5/22/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Final 5/30/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 6/15/2023 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 6/16/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 6/20/2023 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 6/22/2023 Approved CHRISTOPHER WILSON
HVAC-Final 6/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 6/29/2023 Approved BRENDAN LOONEY
HVAC-Final 7/5/2023 Approved CHRISTOPHER WILSON
Final 8/10/2023 Corrections Issued CHRISTOPHER WILSON
Green Building Final 8/10/2023 Approved CHRISTOPHER WILSON
Smoke Detectors 8/10/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 8/17/2023 No Access for Inspection CHRISTOPHER WILSON
Smoke Detectors 8/17/2023 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 8/21/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 8/23/2023 Approved CHRISTOPHER WILSON
Final 8/28/2023 Corrections Issued CHRISTOPHER WILSON
Smoke Detectors 8/28/2023 Approved CHRISTOPHER WILSON
Final 8/30/2023 OK to Issue CofO CHRISTOPHER WILSON
Gas Test 8/30/2023 Approved CHRISTOPHER WILSON
Pre-Inspection 8/30/2023 Approved CHRISTOPHER WILSON