15585 W AQUA VERDE DR 90077

Certificate Information: 15585 W AQUA VERDE DR 90077

Application / Permit
19010-10000-02518
Plan Check / Job No.
B19LA12211
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (49'-6" x 63'-6"- IRREGULAR) 2-STORY SINGLE FAMILY DWELLING OVER BASEMENT. FIRE SPRINKLERED REQUIRED PER NFPA 13 D. 1 OF 3
Permit Issued
Issued on 12/16/2019
Issuing Office
West Los Angeles
Current Status
Issued on 12/16/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 MICHAEL LOPEZ
Corrections Issued 7/1/2019 MICHAEL LOPEZ
Quality Review Completed 7/13/2019 STANLEY RAAP
Building Plans Picked Up 7/19/2019 APPLICANT
Green Plans Picked Up 8/2/2019 APPLICANT
Applicant returned to address corrections 11/6/2019 MICHAEL LOPEZ
Applicant returned to address corrections 11/18/2019 MICHAEL LOPEZ
Applicant returned to address corrections 12/11/2019 MICHAEL LOPEZ
Plan Check Approved 12/13/2019 MICHAEL LOPEZ
Issued 12/16/2019 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/25/2019 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 7/25/2019 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 7/25/2019 CHRISTOPHER LAW
Permit Cleared 7/25/2019 CHRISTOPHER LAW
Eng Process Fee Ord 176,300 Cleared 7/29/2019 JOSE CRUZ RODRIGUEZ
Sewer availability Cleared 7/29/2019 JOSE CRUZ RODRIGUEZ
Green Code Cleared 10/18/2019 COLIN LOREDO
Hydrant and Access approval Cleared 10/25/2019 JOHN CONNEALLY
ZA Case Cleared 10/25/2019 DIANA JIMENEZ
ZA Case Cleared 10/25/2019 DIANA JIMENEZ
ZI Cleared 10/25/2019 DIANA JIMENEZ
Excavation more than 5-ft deep Cleared 11/18/2019 CALOSHA APPROVED
Green Code Cleared 11/25/2019 MICHAEL LOPEZ
Low Impact Development Cleared 11/26/2019 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/26/2019 ANTHONY MAINEZ
Miscellaneous Cleared 12/6/2019 DOMINICK ORTIZ
Specific Plan Cleared 12/6/2019 DOMINICK ORTIZ
GPI Written Notices Cleared 12/11/2019 BRIAN OLSON
Grading Pre-Inspection Cleared 12/11/2019 BRIAN OLSON

Contact Information

Contractor Owner-Builder       ,
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/23/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 5/30/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/12/2020 Conditional Approval CARLOS MATAMOROS
PLUMBING-Rough 9/30/2020 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 10/2/2020 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/7/2020 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/19/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 10/20/2020 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/21/2020 Partial Approval CARLOS MATAMOROS
Green Building Rough 10/21/2020 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/21/2020 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Masonry 10/29/2020 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/29/2020 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Masonry 10/30/2020 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/4/2020 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Masonry 11/9/2020 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/9/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/12/2020 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 11/12/2020 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 11/12/2020 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 11/13/2020 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/17/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/23/2020 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 11/23/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 11/30/2020 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/1/2020 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 12/2/2020 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 12/8/2020 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/9/2020 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 12/9/2020 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 12/9/2020 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 12/17/2020 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 1/12/2021 Conditional Approval CARLOS MATAMOROS
Deputy Wood Construction 2/22/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Partial Approval CARLOS MATAMOROS
Green Building Rough 2/22/2021 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 2/22/2021 Not Ready for Inspection CARLOS MATAMOROS
Structural Steel Frame 2/23/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/24/2021 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 2/24/2021 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 2/24/2021 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 3/9/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 8/11/2021 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 10/12/2021 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/12/2021 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Approved CARLOS MATAMOROS
Green Building Rough 11/8/2021 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 11/8/2021 Not Ready for Inspection CARLOS MATAMOROS
Deputy Wood Construction 11/12/2021 Conditional Approval STEPHANIE SWANSON
HVAC-Rough 11/18/2021 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 11/19/2021 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 11/19/2021 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 11/19/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/16/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 7/28/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 8/19/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 10/27/2022 Approved CARLOS MATAMOROS
HVAC-Rough 12/12/2022 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 3/9/2023 Conditional Approval MICHAEL PELHAM
Insulation 6/2/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 6/2/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/9/2023 Partial Approval BRENDAN LOONEY
Drywall Nailing 10/13/2023 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 10/26/2023 Corrections Issued CARLOS MATAMOROS
Green Building Rough 10/26/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 11/28/2023 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 11/28/2023 Approved CARLOS MATAMOROS
HVAC-Rough 11/28/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/12/2024 Approved CARLOS MATAMOROS
Insulation 1/23/2024 Approved CARLOS MATAMOROS
Shower Pan 5/7/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/19/2024 Partial Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 9/18/2024 Partial Approval CARLOS MATAMOROS
Sewer 10/11/2024 Approved CARLOS MATAMOROS
Drywall Nailing 11/14/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 11/14/2024 Approved CARLOS MATAMOROS
Drywall Nailing 2/7/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/7/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/9/2026 Approved CARLOS MATAMOROS
Structural Steel Frame 3/23/2026 Approved CARLOS MATAMOROS
Underground Mechanical 3/23/2026 Approved CARLOS MATAMOROS