Work Description
NEW 2-STORY SINGLE FAMILY DWELLING OVER BASEMENT, WITH ATTACHED TRELLIS.
Permit Issued
Issued on 1/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/25/2019 JOHNNY WU
Corrections Issued 8/2/2019 JOHNNY WU
Quality Review Completed 8/13/2019 JOSE RODRIGUEZ
Building Plans Picked Up 8/14/2019 APPLICANT
Green Plans Picked Up 8/14/2019 APPLICANT
Applicant returned to address corrections 12/4/2019 JOHNNY WU
Plan Check Approved 12/10/2019 JOHNNY WU
Issued 1/7/2020 LADBS
CofO in Progress 1/18/2022 ARTHUR SARGSYAN
CofO in Progress 1/18/2022 ARTHUR SARGSYAN
CofO in Progress 10/20/2022 JEFFREY MEAD
Permit Finaled 12/13/2022 DEROLD HAUFF
CofO Issued 12/13/2022 DEROLD HAUFF
Permit Finaled 12/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Disturb/Remove Protected Trees Cleared 8/31/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 8/31/2019 ADRIAN SANCHEZ
Abandoned oil well Cleared 10/16/2019 GEORGE SUCHAND
Hydrant and Access approval Cleared 10/16/2019 GEORGE SUCHAND
Address approval Cleared 11/8/2019 THOMAS LANG
Address approval Cleared 11/8/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/8/2019 THOMAS LANG
Permit Cleared 11/8/2019 THOMAS LANG
Green Code Cleared 11/18/2019 NEGAR NEJAD
Sewer availability Cleared 11/19/2019 THOMAS LANG
Low Impact Development Cleared 11/22/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/3/2019 THOMAS LANG
Excavation more than 5-ft deep Cleared 12/4/2019 CALOSHA APPROVED
Miscellaneous Cleared 12/4/2019 JOHNNY WU

Contact Information

Contractor David Elliot Builders Inc; Lic. No.: 1021000-B 5967 W 3RD ST #360      LOS ANGELES, CA 90036
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2020 Partial Approval ARTHUR SARGSYAN
Underground Mechanical 3/17/2020 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 3/26/2020 Partial Approval ROBERT CORNELL
METHANE-Barrier 3/26/2020 Approved ROBERT CORNELL
METHANE-Subgrade 3/26/2020 Approved ROBERT CORNELL
Deputy Reinf. Concrete 4/2/2020 Approved ARTHUR SARGSYAN
Shower Pan 4/2/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 5/1/2020 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Partial Approval CHRIS CHRISTENSEN
Deputy Methane Barrier 5/21/2020 Approved ARTHUR SARGSYAN
Deputy Methane Barrier 5/26/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 8/26/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/31/2020 Corrections Issued ARTHUR SARGSYAN
ELECTRICAL-Rough 8/31/2020 Partial Approval ARTHUR SARGSYAN
METHANE-Rough 8/31/2020 Not Ready for Inspection ARTHUR SARGSYAN
Verify Sprinkler Sign Off 8/31/2020 Corrections Issued ARTHUR SARGSYAN
BUILDING-Rough-Frame 9/1/2020 Partial Inspection ARTHUR SARGSYAN
Verify Sprinkler Sign Off 9/1/2020 Corrections Issued ARTHUR SARGSYAN
BUILDING-Rough-Frame 9/11/2020 Approved ARTHUR SARGSYAN
Green Building Rough 9/11/2020 Approved ARTHUR SARGSYAN
METHANE-Rough 9/11/2020 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 9/11/2020 Approved ARTHUR SARGSYAN
Shower Pan 9/25/2020 Approved ARTHUR SARGSYAN
Insulation 10/16/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 10/19/2020 Approved JOSEPH MCGARRY
Drywall Nailing 10/27/2020 Approved ARTHUR SARGSYAN
Service/Power Release 9/15/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 12/23/2021 Approved ARTHUR SARGSYAN
Gas Test 12/23/2021 Approved ARTHUR SARGSYAN
Green Building Final 12/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
HVAC-Final 12/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Final 12/23/2021 Approved ARTHUR SARGSYAN
Service/Power Release 12/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
Smoke Detectors 12/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
Verify Rec and Parks Fee Memo 12/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 12/30/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 12/30/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 12/30/2021 Approved CHRIS CHRISTENSEN
Smoke Detectors 12/30/2021 Approved CHRIS CHRISTENSEN
Final 1/14/2022 OK to Issue CofO ARTHUR SARGSYAN
Footing/Foundation/Slab 1/14/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Approved ARTHUR SARGSYAN
Pre-Inspection 8/12/2022 Partial Approval JOSEPH MCGARRY
Pre-Inspection 8/31/2022 Corrections Issued JULIAN AMAYA
Special/Order Compliance 10/7/2022 Partial Approval JOSEPH MCGARRY
Final 10/19/2022 OK to Issue CofO JEFFREY MEAD