2657 N LARMAR ROAD 90068

Certificate Information: 2657 N LARMAR ROAD 90068

Application / Permit
19010-10000-02505
Plan Check / Job No.
B19LA12134
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. SHAPED 2 STORY SINGLE FAMILY DWELLING WITH 1 LEVEL BASEMENT AND A 2 CAR GARAGE. PERMIT 1 OF 3
Permit Issued
Issued on 7/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 JESSE VIDUYA
Corrections Issued 7/2/2019 JEFFREY MACHADO
Quality Review Completed 7/20/2019 STANLEY RAAP
Building Plans Picked Up 7/31/2019 APPLICANT
Applicant returned to address corrections 12/10/2019 JESSE VIDUYA
Green Plans Picked Up 12/11/2019 APPLICANT
Applicant returned to address corrections 2/20/2020 JESSE VIDUYA
Plan Check Approved 4/9/2020 JESSE VIDUYA
Issued 7/14/2020 APPLICANT
CofO in Progress 9/25/2025 BRIAN SULLIVAN
Permit Finaled 9/26/2025 DEROLD HAUFF
CofO Issued 9/26/2025 DEROLD HAUFF
Permit Finaled 9/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 8/21/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 8/21/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 8/21/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/21/2019 JEANETTE VONG
Hydrant and Access approval Cleared 8/21/2019 JOHN CONNEALLY
Landscape for retaining wall Cleared 8/21/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 8/21/2019 SOPHIE GABEL-SCHEINBAU
Permit Cleared 8/21/2019 JEANETTE VONG
Specific Plan Cleared 8/21/2019 SOPHIE GABEL-SCHEINBAU
Trees in Parkway Cleared 8/22/2019 ADRIAN SANCHEZ
Green Code Cleared 1/6/2020 DONALD CRICHLOW
Low Impact Development Cleared 2/14/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/14/2020 JUAN ASHTON
Sewer availability Cleared 2/14/2020 JUAN ASHTON
Excavation more than 5-ft deep Cleared 4/6/2020 CALOSHA APPROVED
GPI Written Notices Cleared 4/6/2020 JEFFREY MACHADO
Grading Pre-Inspection Cleared 4/6/2020 JEFFREY MACHADO

Contact Information

Contractor Owner-Builder       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/15/2021 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 4/28/2021 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 4/28/2021 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 4/28/2021 Off-Hour Fees Due
Piling/Pier/Caisson 4/30/2021 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/11/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/10/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/16/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 6/25/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/26/2021 Partial Approval BRIAN SULLIVAN
Green Building Rough 7/26/2021 Not Ready for Inspection BRIAN SULLIVAN
Structural Steel Frame 7/26/2021 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/26/2021 Not Ready for Inspection BRIAN SULLIVAN
Piling/Pier/Caisson 8/17/2021 Partial Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 9/1/2021 Conditional Approval BRIAN SULLIVAN
Piling/Pier/Caisson 9/1/2021 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 9/3/2021 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 9/29/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/14/2021 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 11/2/2021 Partial Approval BRIAN SULLIVAN
Underground Mechanical 11/2/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/19/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/22/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 11/30/2021 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 11/30/2021 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/7/2021 Partial Approval BRIAN SULLIVAN
Green Building Rough 1/6/2022 Not Ready for Inspection BRIAN SULLIVAN
Structural Steel Frame 1/6/2022 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 1/6/2022 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/18/2022 Partial Approval BRIAN SULLIVAN
Deputy Steel/Welding 1/31/2022 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 1/31/2022 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 1/31/2022 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/24/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 2/24/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval BRIAN SULLIVAN
Masonry Wall/Backfill 4/5/2022 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 4/22/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval BRIAN SULLIVAN
Green Building Rough 4/22/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 4/22/2022 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 4/22/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/31/2022 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 5/31/2022 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 5/31/2022 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 5/31/2022 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/24/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 8/24/2022 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 8/24/2022 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 8/24/2022 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 8/24/2022 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 11/3/2022 Not Ready for Inspection BRIAN SULLIVAN
Grounding or Bonding 11/17/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 11/17/2022 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Partial Approval RAUL BARAJAS
Sewer 12/30/2022 Approved RAUL BARAJAS
Service/Power Release 2/2/2023 Corrections Issued BRIAN SULLIVAN
Service/Power Release 2/6/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 5/22/2023 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 5/22/2023 Approved BRIAN SULLIVAN
Shower Pan 5/22/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 6/23/2023 Not Ready for Inspection RAUL BARAJAS
Wood Frame 6/23/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 6/27/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 6/27/2023 Approved BRIAN SULLIVAN
Green Building Rough 6/27/2023 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 6/27/2023 Approved BRIAN SULLIVAN
Insulation 12/12/2023 Approved BRIAN SULLIVAN
Drywall Nailing 3/1/2024 Partial Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 5/5/2025 Approved BRIAN SULLIVAN
Final 9/8/2025 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 9/15/2025 Approved BRIAN SULLIVAN
Drywall Nailing 9/15/2025 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 9/15/2025 Approved BRIAN SULLIVAN
Green Building Final 9/15/2025 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved BRIAN SULLIVAN
Structural Steel Frame 9/15/2025 Approved BRIAN SULLIVAN
Final 9/19/2025 Corrections Issued BRIAN SULLIVAN
Smoke Detectors 9/19/2025 Corrections Issued BRIAN SULLIVAN
Final 9/24/2025 OK to Issue CofO BRIAN SULLIVAN
Smoke Detectors 9/24/2025 Approved BRIAN SULLIVAN