4703 E YORK BLVD 90042
Certificate Information: 4703 E YORK BLVD 90042
- Application / Permit
- 19010-10000-02494
- Plan Check / Job No.
- B18LA13673
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- NEW ONE STORY RETAIL. CORE AND SHELL ONLY. SEPARATE PERMIT FOR TENANT IMPROVEMENT.
- Permit Issued
- Issued on 4/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2018 | APPLICANT |
| Green Plans Picked Up | 7/30/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 7/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | JOE VO |
| Corrections Issued | 8/15/2018 | JOE VO |
| Quality Review Completed | 8/17/2018 | GARO TELMI |
| Building Plans Picked Up | 8/22/2018 | APPLICANT |
| Plan Check Approved | 3/27/2020 | JOE VO |
| Issued | 4/9/2020 | LADBS |
| TCO Issued (Expire Date: 12-24-2023) | 6/27/2023 | TED RIES |
| CofO in Progress | 1/22/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 1/25/2024 | ERNESTO CORRAL |
| CofO Issued | 1/25/2024 | ERNESTO CORRAL |
| Permit Finaled | 1/25/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/9/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | JUAN ASHTON |
| "Q" conditions | Cleared | 3/11/2020 | RICHARD REASER |
| Address approval | Cleared | 3/11/2020 | THOMAS LANG |
| DAS Clearance | Cleared | 3/11/2020 | ELIZABETH TOMS |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/11/2020 | GILBERT URREA |
| Sewer availability | Cleared | 3/13/2020 | THOMAS LANG |
| Green Code | Cleared | 3/18/2020 | JOE VO |
| Comm Cor/Mini-Mall | Cleared | 3/19/2020 | TERRI OSBORNE |
| Comm Cor/Mini-Mall | Cleared | 3/19/2020 | TERRI OSBORNE |
Contact Information
| Contractor | Analog Construction; Lic. No.: 1058496-B | 1910 W SUNSET BLVD #660 LOS ANGELES, CA 90026 |
| Engineer | Louks,, Daniel Robert; Lic. No.: C56332 | 16950 AVENIDA DE SANTA YNEZ PACIFIC PALISADES, CA 90272 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/11/2020 | Partial Inspection | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 5/26/2020 | Not Ready for Inspection | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 5/29/2020 | Partial Approval | NICK DANERI |
| Masonry Wall/Backfill | 6/4/2020 | Partial Approval | NICK DANERI |
| Reinforced Masonry Frame | 6/4/2020 | Partial Approval | NICK DANERI |
| Deputy Reinf. Masonry | 6/5/2020 | Conditional Approval | NICK DANERI |
| Deputy Reinf. Masonry | 6/19/2020 | Conditional Approval | NICK DANERI |
| Masonry Wall/Backfill | 6/22/2020 | Conditional Approval | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 7/7/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Masonry Wall/Backfill | 7/7/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 7/8/2020 | No Access for Inspection | NICK DANERI |
| Masonry Wall/Backfill | 7/8/2020 | No Access for Inspection | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 7/14/2020 | Partial Approval | NICK DANERI |
| Reinforced Masonry Frame | 7/14/2020 | Not Ready for Inspection | NICK DANERI |
| Reinforced Masonry Frame | 7/23/2020 | Partial Inspection | NICK DANERI |
| Reinforced Masonry Frame | 7/27/2020 | Partial Approval | NICK DANERI |
| Wall Anchors | 7/27/2020 | Partial Approval | NICK DANERI |
| Deputy Reinf. Masonry | 7/29/2020 | Conditional Approval | NICK DANERI |
| Green Building Rough | 8/27/2020 | Not Ready for Inspection | NICK DANERI |
| Interior/Exterior Lathing | 8/27/2020 | Partial Approval | NICK DANERI |
| Verify Sprinkler Sign Off | 8/27/2020 | Partial Inspection | NICK DANERI |
| Wood Frame | 8/27/2020 | Partial Approval | NICK DANERI |
| Special/Order Compliance | 6/3/2021 | Partial Inspection | NICK DANERI |
| Special/Order Compliance | 6/15/2021 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/5/2021 | Partial Approval | RAFAEL ESPINOZA |
| Final | 8/23/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/23/2022 | Approved | RAFAEL ESPINOZA |
| Green Building Final | 8/23/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Rough | 8/23/2022 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 8/23/2022 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 8/23/2022 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 8/23/2022 | Approved | RAFAEL ESPINOZA |
| Final | 12/13/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Final | 12/13/2022 | Approved | RAFAEL ESPINOZA |
| Special/Order Compliance | 11/28/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 1/12/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 1/22/2024 | OK to Issue CofO | RAFAEL ESPINOZA |